Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M.Haneefa vs The Pathanamthitta Municipality
2024 Latest Caselaw 5705 Ker

Citation : 2024 Latest Caselaw 5705 Ker
Judgement Date : 20 February, 2024

Kerala High Court

M.Haneefa vs The Pathanamthitta Municipality on 20 February, 2024

Author: Sathish Ninan

Bench: Sathish Ninan

            IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                PRESENT
            THE HONOURABLE MR. JUSTICE SATHISH NINAN
   TUESDAY, THE 20TH DAY OF FEBRUARY 2024 / 1ST PHALGUNA, 1945
                          RFA NO. 375 OF 2016
AGAINST THE JUDGMENT IN OS 203/2009 OF    SUB COURT, PATHANAMTHITTA
                                 -----
APPELLANT/PLAINTIFF:

          M.HANEEFA,
          AGED 63 YEARS,
          S/O.MUSTHAFA MEERAVU RAWTHER, KUREEKATTIL HOUSE,
          CHITTUR WARD,PATHANAMTHITTA.

          BY ADV SRI.S.ABDUL RAZZAK



RESPONDENTS/DEFENDANTS:

    1     THE PATHANAMTHITTA MUNICIPALITY,
          REPRESENTED BY ITS SECRETARY,MUNICIPAL OFFICE,
          PATHANAMTHITTA689 645.

    2     MR.ZAKIR HUSSAIN,
          AGED 44 YEARS, S/O.THANKAKUTTY, [FORMERLY CHAIRMAN,
          PATHNAMTHITTA MUNICIPALITY],BEENA MANZIL, AZHOOR,
          PATHANAMTHITTA, 689 645.

    3     M.MUHAMMED HUWAIZ,
          AGED 43 YEARS, S/O.K.MUHAMMED KUNJU, [FORMERLY
          SECRETARY, PATHANAMTHITTA MUNICIPALITY],KALEELIL
          HOUSE, PUTHENCHANTHA P.O, CHAVARA, 691 583,
          KOLLAM DISTRICT.
 RFA NO. 375 OF 2016              -2-


    4     STATE OF KERALA,
          REPRESENTED BY PRINCIPAL SECRETARY, LOCAL SELF
          GOVERNMENT DEPARTMENT,GOVERNMENT SECRETARIAT,
          THIRUVANANTHAPURAM 695 001.

          BY ADVS.
          SRI.V.K.SUNIL(SC) B/O
          SRI.MANU RAMACHANDRAN
          SMT.KRIPA ELIZABETH MATHEWS
          SMT.PRIYANKA VARGHESE
          SMT.P.F.ROSY
          SRI.V.M.SYAM KUMAR
          SMT.K.B.SONY, GOVT. PLEADER (B/O)




     THIS REGULAR FIRST APPEAL HAVING COME UP FOR HEARING ON
20.02.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
                       SATHISH NINAN, J.
             = = = = = = = = = = = = = = = = = =
                     R.F.A. No.375 of 2016
             = = = = = = = = = = = = = = = = = =
          Dated this the 20th day of February, 2024

                              J U D G M E N T

The suit for money under a construction contract

was decreed in part. Dissatisfied with the decree, the

plaintiff is in appeal.

2. On 14.09.2007, Ext.A1 agreement was entered into

between the plaintiff and the defendants with regard to

metalling work in the bus stand yard of the

Municipality. The period fixed for completion of the

work was three months. There occurred delay in

completion and there arose disputes between the parties.

The contract was terminated and the work was re-

tendered. There were various litigations with regard to

the same which are not being adverted to herein as they

are not relevant for the purpose of disposal of this

case. The work was completed by the subsequent

contractor. The suit is for money for the work done by

the plaintiff, the cost of materials, loss caused to the

plaintiff consequent to the delay allegedly caused by

the defendants etc.

3. The defendants allege that the plaintiff was

responsible for the delay and that the contract had to

be terminated consequent on the failure of the plaintiff

to complete the work in terms of the contract. He prayed

for dismissal of the suit.

4. The trial court found that, the plaintiff though

had not completed the work, had done part thereof and

was entitled for its value. Accordingly the suit was

decreed in part. This appeal has been filed by the

plaintiff in so far as it relates to the portion of the

plaint claim which was not granted by the trial court.

There is no appeal by the defendants.

5. I have heard Sri.S.Abdul Razzak, the learned

counsel for the appellant and Sri.V.K.Sunil, the learned

counsel for the defendant-Muncipality, and Sri.Manu

Ramachandran and Sri. V.M. Syam Kumar, on behalf of the

party respondents.

6. The points that arise for consideration are,

(i) Is the plaintiff entitled for value for the work done in addition to the cost of the materials utilized?

(ii) Is not the plaintiff entitled for return of the security deposit?

(iii) Is the plaintiff entitled for value of the metal provided for at the site for the second phase of work, which he was not able to carry out?

7. Ext.A1 agreement which was entered into on

14.09.2007, fixed three months for completion of the

work. It is not in dispute that the site was handed over

to the plaintiff only belatedly, in February, 2008. On

account of the various differences, the contract was

terminated. We are not concerned about the

justifiability or otherwise of the termination.

8. Ext.A1 agreement related to five items of work;

out of the same items 1, 2 and 3 related to supply of

materials, and items 4 and 5 related to labour. The work

was to be done in two stages-firstly, the soling and

secondly, the layer on its top. It is not in dispute

that the materials in items 1 and 3 are necessary for

carrying out the first phase of work namely, soling.

9. Though there is some dispute between the parties

with regard to the area of work done under phase-I it is

not in dispute that phase-I was completed by the

plaintiff. The engineer reported that the plaintiff had

carried out the phase-I for an area of 12030 sq. metres

though he claimed to have done work for an area of 15550

sq. meters. The quantity of materials used in item No.1

viz. hard blue granite broken stone was found to be

1203.10 M3. It was found that though the thickness was

to be 7 centimeter, the average thickness of the work

done was only 6.25 centimeters. The quantity of the

materials was measured by the engineer, as noted above.

So the court concluded that the plaintiff did excess

area with less quantity of material.

10. It is not in dispute that the subsequent

contractor carried out the second phase of the work upon

the first phase already carried out by the plaintiff.

There is no case for the defendants that the subsequent

contractor had to do extra work over the first phase

resulting in extra cost. Taking note of the same the

trial court has held that the plaintiff is entitled for

value of the materials collected under item No.1 for

completion of phase-I.

11. However, the trial court did not take note of

the fact that item No.3 was also essential for

completing phase-I, which was also utilized by the

plaintiff. So also the labour under item No.4 for

completion of phase-I was not taken note of by the trial

court. As noticed, there is no claim for the defendants

that they had sustained any damages. There is no counter

claim for any damages, much less a plea to the said

effect. Therefore, the plaintiff is entitled for the

value of the materials supplied under item Nos.1 and 3

and also the value of the labour for item No.4.

12. Coming to the quantity of material under item

No.3, Ext.A1 specifies the quantity at 473.00 M 3. The

rate fixed is ` 220/- per M3. However, in Ext.A14 report

of the Superintending Engineer it is reported that as

per the M. Book, the quantity of gravel earth supplied

is noted as 270 M3. The total value for the same is

` 59,400/-. The rate quoted by the plaintiff was 23.1%

below the estimated rate. Therefore, the same has to be

deducted to arrive at the amount that the plaintiff is

entitled for. The said amount comes to ` 45,679/-.

Though the learned counsel for the plaintiff would

contend that the entire quantity as was specified in the

tender was and had to be utilised to do the work, as

noticed above, records show otherwise. Hence the said

argument can only be repelled.

13. Now coming to the cost of the labour namely

item 4, as per Ext.A1, the quantity of materials in

Serial No.1 required for an area of 13514 square metres,

as mentioned in serial number 4, is 1352 M 3. The

engineer had reported that the quantity of item No.1

collected/supplied by the plaintiff is 1203.10 M 3. The

proportionate area would accordingly be roughly 12030

M2. Though going by Ext.A15 report of the Executive

Engineer to the Chief Engineer the area is 14002.54 M 2

as was noticed by the trial court, the plaintiff has

used only lesser quantity for completing the larger area

and the thickness is also less than what was required.

Therefore, it is not appropriate to grant the cost of

labour for the excess area done by him. In Ext.A14

report of the Superintending Engineer referred to supra

it has been reported that, with the quantity of

materials supplied the area that could be metaled is

12072 M2. The plaintiff could be granted the cost of

labour for the area which alone he could have done with

the said material supplied viz. 12072 M 2. Ext.A1

specifies the rate of item No.4 as ` 304/- per 10 M2.

Thus the total cost is 1207.2 x 304 = ` 3,66,989/-. As

noticed earlier the quoted rate of the plaintiff is less

23.1% below the estimated rate. Therefore, the said

amount is to be deducted therefrom ie. 3,66,989 - 84,774

= ` 2,82,215. The plaintiff is entitled for that much

amount under item No.4.

14. The plaintiff has a claim for the cost of

materials supplied under item No.3 in Ext.A1 agreement.

With regard to the said materials, the Municipality had

informed the plaintiff under Ext.A34 that the materials

supplied under item No.2 is not in accordance with the

specification and are to be removed from the site. In

spite of the same, the plaintiff did not remove the

same. The learned counsel for the plaintiff would

contend that clause 10 in Ext.A1 specifically prohibited

the plaintiff from removing the materials from the site.

Clause-10 of Ext.A1 reads thus:-

"IcmÀ ZpÀ-º-e-s¸-Sp-¯p-t¼mÄ {]-hr-¯n \-S-¯p-ó Øe-¯v kw-`-cn-¨p-sh-¨n-«p-Å Fñm \nÀ½m-W km-[-\- §fpw b-t{´m-]-I-c-W-§fpw {]-hr-¯n \-S-¯p-ó Ø-e- ¯p-\n-óv I-cm-dp-Im-c³ am-äm³ ]m-Sp-ÅXñ. {]-kvXp-X km-[-\-§-sfñmw A-f-sh-Sp-¯-ti-jw {]-hr-¯n-¡p-th- ïn D-]-tbm-Kn¡mt\m te-ew sN-bv-Xv hn-äv B h-I-bnð e-`n-¡p-ó Xp-I \-ã-]-cn-lm-c-¯p-I-bnð h-I-bn-cp-¯p- óXnt\m ]-ôm-b-¯v/ap³-kn-¸m-en-än/tImÀ-¸-tdj-\v ]- cn-]qÀ-®am-b A-[n-Im-c-ap-ïm-bn-cn-¡p-ó-XmWv."

Clause-10 enables the defendants to utilize the

materials available at the site or to auction it and

appropriate the amount towards damages. It does not

prohibit the defendants from requiring the plaintiff to

remove the materials from the site. In fact it would

only be more advantageous to the plaintiff. In spite of

the specific demand under Ext.A34, the plaintiff failed

to remove the materials. The plaintiff having failed to

remove the materials, they cannot claim its value as

damages. The plaintiff could be permitted to remove such

materials from the site.

15. The next head of claim is return of the

security deposit of one lakh. In the absence of any

claim for damages, the defendants are bound to return

the security deposit. The plaintiff is entitled to get

return of the same.

16. The above heads under which the plaintiff is

entitled for a decree have not been taken into

consideration by the trial court. The decree and

judgment of the trial court is liable to be modified to

the above extent.

17. The learned counsel for the Municipality would

contend that an error has crept in the decree of the

trial court since the Court had failed to deduct 23.1%

from the estimated rate, it being the rate quoted by the

plaintiff. It is to be noted that, the defendants never

chose to challenge the decree on any ground. However, it

is apparent that the trial court has calculated the

amount payable based on the estimated rate and not the

quoted rate. Thus there has to be a deduction of 23.1%

from the amount decreed by the trial court. Though there

is no appeal by the defendants, the mistake/error being

apparent, this Court is entitled to have the same

corrected in exercise of the powers under Order XLI Rule

33 of the Code of Civil Procedure. Thus deducting 23.1%,

the amount payable to the defendant in the place of the

trial court decree is ` 5,84,674-00.

18. Therefore, the plaintiff is entitled for a

decree under the following heads :-

(i) Cost of materials supplied under item No.1 in

Ext.A1. = `5,84,674-00

(ii) Cost of materials supplied under item No.3 in

Ext.A1 = ` 45,679-00

(iii) Cost of labour for the work done under item

No.4 in the agreement = ` 2,82,215-00

(iv) Security deposit = ` 1,00,000-00

Total = ` 10,12,568

19. Referring to the judgment of the Apex Court in

Ramachandra Narayan Nayak v. Karnataka Neeravari Nigam Ltd. And

Ors. 2013 AIR SCW 5913, the learned counsel for the

plaintiff would contend that the plaintiff is entitled

for interest at the rate of 9% per annum on the amount

payable. Considering the entire facts of the case in the

light of the judgment of the Apex Court afore, I am of

the opinion that the plaintiff is entitled for interest

at the rate of 9% on the amount due, from the date of

suit till the date of decree. The plaintiff shall be

entitled for interest at the rate of 6% from the date

of decree till realisation.

Resultantly, this appeal is allowed. The decree and

judgment of the trial court is set aside and a decree is

passed allowing the plaintiff to realise an amount of

` 10,12,568-00 (Ten lakhs Twelve Thousand Five Hundred

and Sixty Eight Only), with interest thereon at the

rate of 9% per annum from the date of suit till date of

decree, and thereafter at the rate of 6% per annum, from

the first defendant and its assets. The plaintiff shall

be entitled for proportionate costs throughout.

Sd/-

SATHISH NINAN JUDGE

kns/-

//True Copy// P.S. to Judge

PETITIONER ANNEXURES

ANNEXURE A1 PHOTOCOPY OF THE CALCULATION STATEMENT

-----

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter