Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sukesini Constructions And Developers ... vs State Of Kerala
2024 Latest Caselaw 5422 Ker

Citation : 2024 Latest Caselaw 5422 Ker
Judgement Date : 16 February, 2024

Kerala High Court

Sukesini Constructions And Developers ... vs State Of Kerala on 16 February, 2024

Author: Devan Ramachandran

Bench: Devan Ramachandran

             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                              PRESENT
          THE HONOURABLE MR. JUSTICE DEVAN RAMACHANDRAN
     FRIDAY, THE 16TH DAY OF FEBRUARY 2024 / 27TH MAGHA, 1945
                      WP(C) NO. 2368 OF 2024
PETITIONER:
           SUKESINI CONSTRUCTIONS AND DEVELOPERS (INDIA)
           PVT. LTD., SUKESINI BUILDING, MARAKKADA MUKKU,
           PALACHIRA P.O., VARKALA, THIRUVANANTHAPURAM
           DISTRICT-695143 REPRESENTED BY ITS DIRECTOR.,
           PIN - 695143

          BY ADV LATHEESH SEBASTIAN


RESPONDENTS:
     1     STATE OF KERALA, REPRESENTED BY THE CHIEF SECRETARY,
           SECRETARIAT, THIRUVANANTHAPURAM, PIN - 695001

    2     SECRETARY, IRRIGATION DEPARTMENT, SECRETARIAT,
          THIRUVANANTHAPURAM, PIN - 695001

    3     CHIEF ENGINEER, IRRIGATION AND ADMINISTRATION,
          IRRIGATION DEPARTMENT, CWC BUILDING, LMS COMPOUND,
          THIRUVANANTHAPURAM, PIN - 695033

    4     SUPERINTENDING ENGINEER, IRRIGATION SOUTH CIRCLE,
          2ND FLOOR, CWC BUILDING, LMS COMPOUND,
          THIRUVANANTHAPURAM, PIN - 695033

    5     EXECUTIVE ENGINEER, OFFICE OF THE EXECUTIVE ENGINEER,
          IRRIGATION DIVISION,ASRAMAM, KOLLAM, PIN - 691002

    6     ASSISTANT EXECUTIVE ENGINEER, OFFICE OF THE ASSISTANT
          EXECUTIVE ENGINEER, IRRIGATION SUB DIVISION, ASRAMAM,
          KOLLAM, PIN - 691002

    7     ASSISTANT ENGINEER, OFFICE OF THE ASSISTANT ENGINEER,
          IRRIGATION SECTION, ASRAMAM, KOLLAM, PIN - 691002

          BY ADV
          SRI. SUJITH MATHEW JOSE - SPL GP


     THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
16.02.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 WPC 2368/24
                                         2

                                JUDGMENT

The petitioner is stated to be a construction company, awarded

with the contract of construction of groyne field between chainage

9.00 k.m. to 10.00 k.m. at 'Kulathilpadam' to 'Garfil Nagar' area, in

Eravipuram Constituency on 19.08.2015. They say that, though the

work has been completed substantially, eligible amounts due to them

have been denied on various untenable reasons; and thus assail

Ext.P4 order of the 5th respondent - Executive Engineer (Irrigation

Division), arguing that, what is stated therein is factually incorrect

and baseless. They, therefore, pray that Ext.P4 be quashed and the

respondents be directed to pay them an amount of

Rs.1,01,50,401.70, which is the amount due to them, when the

contract had been terminated.

2. Sri.Latheesh Sebastian - learned counsel for the petitioner,

submitted that, since the termination of contract was compelled for

reasons which were beyond the control of his client, the imputations

made by the respondents against them are uncharitable and

unfortunate; and that, therefore, before any liability could be cast

upon them, the respondents ought to have re-audited their works, as

also the accounts, to verify whether such action was tenable or

otherwise. He relied upon Ext.P5 judgment of this Court - which was

obtained by another contractor - in substantiation, saying that, on a

similar set of circumstances, this Court directed the competent

Authority to constitute a Committee for re-auditing the work of the

petitioner therein and take a fresh decision regarding the amounts

payable to them. He thus prayed that the respondents be directed to

adopt a procedure as ordered by this Court in Ext.P5 in his client's

case also.

3. Pertinently, Sri.Sujith Mathews Jose - learned Government

Pleader, submitted that Ext.P4 suffers from no vice, particularly

because the contract of the petitioner had earlier been terminated.

He, however, submitted that if this Court is only inclined to direct

the procedure as ordered by this Court in Ext.P5 judgment, the

competent Authority would not stand in the way of appropriate

orders being issued. He, however, prayed that no affirmative

declaration be made in favour of the petitioner in this judgment.

4. When I evaluate and consider the afore submissions, it is

evident that Ext.P4 has been issued by the Authorities adverting to

various factual and documentary inputs, as are available, consequent

to the contract having been entered into between the parties.

Normally, this Court cannot enter into the merits of the same

conclusively, while acting under Article 226 of the Constitution of

India, because any re-evaluation of such factors are proscribed.

5. I have, however, examined Ext.P5 judgment and notice

that it was delivered in a case where the petitioner therein had been

notified of a negative amount as regards his claim, after having been

imposed with fines. In that case, the petitioner also impelled similar

claims as the petitioner herein; and alleged that amounts due to

them had not been properly evaluated or assessed.

6. Since the learned Government Pleader concedes that the

course adopted by this Court in Ext.P5 can be made applicable to

the petitioner in this case also, I deem it necessary that it be so

ordered.

Resultantly, this Writ Petition is allowed and the 3rd respondent

- Chief Engineer, is directed to constitute a Committee to audit the

works executed/completed by the petitioner, leading to the said

Authority to take a decision regarding the amounts payable to them,

adverting to their claim.

The afore exercise shall be completed, after affording the

petitioner an opportunity of being heard; thus culminating in an

appropriate order/necessary action thereon, as expeditiously as is

possible, but not later than four months from the date of receipt of a

copy of this judgment.

Needless to say, on the afore being completed, the eligible

amounts due to them shall be disbursed within a period of two

months thereafter.

Sd/-

RR DEVAN RAMACHANDRAN JUDGE

APPENDIX OF WP(C) 2368/2024

PETITIONER EXHIBITS ExhibitP 1 TRUE COPY OF THE SCHEDULE OF WORK FOR THE CONSTRUCTION OF GROYNE FIELD BETWEEN CHAINAGE 9.00 KM TO 10.00 KM AT KULATHILPADAM TO GARFIL NAGAR AREA IN ERAVIPURAM CONSTITUENCY OF KOLLAM DISTRICT Exhibit P2 TRUE COPY OF THE CLOSURE AGREEMENT EXECUTED BY THE PETITIONER AND THE 4TH RESPONDENT DATED 01.12.2020 Exhibit P3 TRUE COPY OF THE JUDGMENT OF THIS HON'BLE COURT IN W.P(C)NO 11005/2022 DATED 17.06.2022 Exhibit P4 TRUE COPY OF THE ORDER OF THE 5TH RESPONDENT DATED 05.09.2022 Exhibit P5 TRUE COPY OF THE JUDGMENT OF THIS HON'BLE COURT IN W.P(C) NO.29685/2022 DATED 20.10.2022 Exhibit P6 TRUE COPY OF THE ORDER OF THE 1ST RESPONDENT DATED 15.07.2023 BEARING NO.G.O.(RT)641/2023/WRD

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter