Citation : 2024 Latest Caselaw 5409 Ker
Judgement Date : 16 February, 2024
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE V.G.ARUN
FRIDAY, THE 16TH DAY OF FEBRUARY 2024 / 27TH MAGHA, 1945
CRP NO. 109 OF 2022
AGAINST THE ORDER/JUDGMENT OPELE 562/2013 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:
P.O.JOSE
AGED 71 YEARS
S/O.OUSEPH, PUTHUSSERY HOUSE, PADUVAPURAM, ALUVA
- 683 576
BY ADV P.T.JOSE
RESPONDENT/S:
1 POWER GRID CORPORATION OF INDIA LTD, CONSTRUCTION AREA
OFFICE, MAVELIPURAM COLONY, KAKKANAD, COCHIN-682 030,
NOW IN PAO/400, 200KV SUBSTATION, KUMARAPURAM PO,
PALLIKARA, KOCHI-682303, REP. BY DEPUTY MANAGER.
2 THE SPECIAL TAHSILDAR (LA), POWERGRID CORPORATION OF
INDIA LT, CHEVARAMBALAM, KOZHIKODE-673 017, NOW IN
THRIKKAKARA VILLAGE, KANAYANNOOR TALUK, KAKKANAD, PO-
682030.
3 STATE OF KERALA, REPRESENTED BY DISTRICT COLLECTOR,
ERNAKULAM, KOCHI-682030.
OTHER PRESENT:
SC FOR KSEB B.PREMOD; SR.GP.PREETHA K.K. GP
SYLAJA S.L.
THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
20.12.2023, ALONG WITH CRP.260/2022, THE COURT ON 16.02.2024
DELIVERED THE FOLLOWING:
CRP Nos.109 & 260 of 2022
-2-
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE V.G.ARUN
FRIDAY, THE 16TH DAY OF FEBRUARY 2024 / 27TH MAGHA, 1945
CRP NO. 260 OF 2022
AGAINST THE ORDER/JUDGMENT OPELE 562/2013 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:
POWER GRID CORPORATION OF INDIA LTD.
CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
KAKKANAD, COCHIN - 682 030, PRESENTLY AT
CONSTRUCTION AREA OFFICE, 400/220, KV SUB
STATION, KUMARAPURAM P.O, PALLIKKARA, ERNAKULAM
REPRESENTED BY ITS SENIOR GENERAL MANAGER, PIN -
683565
BY ADV MILLU DANDAPANI
RESPONDENT/S:
1 P.O JOSE
AGED 72 YEARS
S/O OUSEPH , PUTHUSSERRY HOUSE, PADUVAPURAM,
MUKKANNUR, ALUVA, PIN - 683576
2 THE SPECIAL TAHSILDAR (LA)
POWER GRID CORPORATION OF INDIA LTD.
CHEVARAMBALAM, KOZHIKODE, PIN - 673017
3 STATE OF KERALA
REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM,
KOCHI, PIN - 682030
4 KERALA STATE ELECTRICITY BOARD - KSEB
REPRESENTED BY ITS CHAIRMAN & MANAGING DIRECTOR
KSEB LTD., THIRUVANANTHAPURAM ., PIN - 695001
CRP Nos.109 & 260 of 2022
-3-
BY ADVS.
P.T.JOSE
S.ASHITHA(K/000357/2018)
ALTHAF P.A.(K/000535/2022)
ABEY AUGUSTINE(K/000923/2022)
THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD
ON 20.12.2023, ALONG WITH CRP.109/2022, THE COURT ON
16.02.2024 DELIVERED THE FOLLOWING:
CRP Nos.109 & 260 of 2022
-4-
ORDER
Dated this the 16th day of February, 2024
These revision petitions are filed
challenging the common order passed by the
Additional District Judge-VI, Ernakulam in O.P.
(Electricity) No.562 of 2013. The original
petition was filed by the revision petitioner in
CRP No.109 of 2022 (hereinafter called 'the
claimant'), being dissatisfied with the
compensation awarded towards the damage and loss
sustained due to the drawing of 400 KV lines
across his property by the Power Grid Corporation
of India Ltd (hereinafter called 'the
Corporation'). The essential facts are as under;
The claimant is in ownership and possession
of landed property having an extent of 13.34 Ares
comprised in Sy.No.125/8 of Mukkannur Village in CRP Nos.109 & 260 of 2022
Aluva Taluk. The land was cultivated with various
yielding and non-yielding trees. According to the
claimant, to facilitate drawing of the lines and
smooth transmission of power, large number of
trees were cut from his property. The drawing of
high tension lines rendered the land underneath
and adjacent to the lines useless, resulting in
diminution of the value of the property. In
spite of the huge loss suffered by the claimant,
only an amount of Rs.33,103/- was paid as
compensation towards the value of yielding and
non-yielding trees cut. Surprisingly, no
compensation was granted for diminution in land
value. Hence, the original petition was filed,
seeking enhanced compensation towards the value
of trees cut and diminution in land value.
2. The court below rejected the claim for
enhanced compensation for the value of trees cut
since no evidence in support of the claim was
produced. As far as the claim for enhanced CRP Nos.109 & 260 of 2022
compensation towards diminution in land value is
concerned, the court below relied on Ext.A5
document as well as Exts.C7 and C7(a) commission
report and sketch. The Advocate Commissioner
reported that claimant's property lies 500 metres
away from SNDP Junction and 1.5 Km from Tabor
Junction and SCMS College. Moreover, a Government
Hospital and a Milk Society are also seen in
close proximity to his property. Based on these
factors, the court below fixed the land value of
the claimant's property by deducting 20% of the
value shown in Ext.A5 property. Relying on
Ext.C7(a) sketch, it was found that no electric
line was drawn over the claimant's property and
only the outer corridor passes through 2 cents of
the property. For outer corridor, 20% of the land
value was granted as compensation. Accordingly,
the claimant was found entitled to compensation
of Rs.72,025/-. Dissatisfied with the quantum of
enhancement, the claimant has filed CRP No.109 of CRP Nos.109 & 260 of 2022
2022, whereas the Corporation has filed CRP
No.260 of 2022 contending that the enhancement
ordered is far in excess of the actual damage
sustained.
3. Heard Adv.P.T.Jose for the claimant and
Adv.Millu Dandapani for the Corporation.
4. Learned Counsel for the claimant
contended that the court below committed gross
illegality in refusing to grant enhanced
compensation for the loss sustained due to the
cutting of valuable trees, in spite of the
Advocate Commissioner assessing and reporting the
loss. The findings in the Commissioner's report
were not relied on by the court below for the
reason that the property was inspected much after
the trees were cut. The said reasoning is flawed
since the trees were cut much after issuance of
notification by the Corporation and the cause of
action for filing the original petition arose
only on payment of the initial compensation, even CRP Nos.109 & 260 of 2022
later. It is submitted that claimant's property
is situated 500 metres away from SNDP Junction
and 1.5 Km away from Tabor Junction and SCMS
College. Moreover, a Government Hospital and a
Milk Society are situated in close proximity to
the claimant's property. Without considering
these crucial factors, 20% deduction was made
from the value of the property involved in Ext.A5
document.
5. It is submitted that the court below
grossly erred in granting only 20% for the outer
corridor. Considering the extent of damage
sustained and the diminution in land value
consequent to the drawing of lines, the court
below ought to have granted compensation as
claimed.
6. Learned Counsel for the Corporation
contended that, compensation towards diminution
in land value granted is exorbitant and there is
no rationale in granting 9% interest on that CRP Nos.109 & 260 of 2022
amount. The court below also erred in relying on
Ext.A5 for fixing the land value of the
claimant's property. As the drawing of electric
lines does not prohibit the landowner from
conducting agricultural activities and putting up
small structures, 20% for the outer corridor is
exorbitant.
7. A careful scrutiny of the impugned order
reveals that the claim for enhancement of
compensation towards the value of trees cut was
rightly rejected since no supporting material,
other than the findings in the Advocate
Commissioner's report, was made available. As
found by the court below, apart from the
interested testimony of a solitary witness, who
is the claimant in some of the connected cases,
no other independent witness was examined to
prove the claim. It is also not in dispute that
the trees were cut in the year 2011 and the
commissioner inspected the property in the year CRP Nos.109 & 260 of 2022
2015 and assessed the value of the trees on a
comparison with the trees standing in the nearby
properties. Such comparison, having no scientific
basis, is not sufficient to discard the
contemporaneous valuation statement prepared by
the Corporation.
8. As far as the diminution in land value
is concerned, the factors to be taken into
consideration, as laid down in KSEB v. Livisha
[(2007) 6 SCC 792] are as under;
"10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to CRP Nos.109 & 260 of 2022
be used."
On careful scrutiny of the impugned order, it is
seen that the compensation was enhanced after
taking all the above factors into consideration.
The nature of the land, the cultivation therein,
the commercial importance of the area and the
manner in which the land was affected by drawing
of the lines have all been considered for fixing
the land value as well as the percentage of
diminution. The court below has deducted only 20%
of the land value in Ext.A5, which according to
me, is a reasonable deduction. For the outer
corridor, 20% is granted, which I find to be just
and proper. As such, there is no illegality or
material irregularity in the impugned order,
warranting intervention by this Court in exercise
of the revisional power under Section 115 of the
Code of Civil Procedure.
For the aforementioned reasons, the civil
revision petitions filed by the claimant as well CRP Nos.109 & 260 of 2022
as the Corporation are dismissed. The Power Grid
Corporation shall pay the enhanced compensation
fixed by the court below within three months of
receipt of a copy of this order.
Sd/-
V.G.ARUN JUDGE Scl/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!