Citation : 2024 Latest Caselaw 5403 Ker
Judgement Date : 16 February, 2024
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE V.G.ARUN
FRIDAY, THE 16TH DAY OF FEBRUARY 2024 / 27TH MAGHA, 1945
CRP NO. 356 OF 2021
AGAINST THE ORDER/JUDGMENT OPELE 549/2013 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:
1 T.K.MURALEEDHARAN
AGED 71 YEARS
X
2 T.K.MURALEEDHARAN
AGED 71 YEARS
S/O.NARAYANNIAMMA, VADAKKINIMARATH HOUSE,
CHERANELLUR, KOOVAPPADY VILLAGE, KUNNATHUNADU
TALUK
BY ADV P.T.JOSE
RESPONDENT/S:
1 POWER GRID CORPORATION OF INDIA
CONSTRUCTION AREA OFFICE, KAKKANAD, NOW IN
PAO/400, 220KV SUBSTATION, KUMARAPURAM P.O.,
PALLIKARA, KOCHI 682 303, REP.BY DEPUTY MANAGER
2 THE SPECIAL TAHASILDAR (L.A.)
POWER GRID CORPORATION OF INDIA LTD.,
CHEVARAMBALAM, KOZHIKODE, NOW IN KAKKANAD
P.O.682 030
3 STATE OF KERALA
REP.BY DISTRICT COLLECTOR, ERNAKULAM KOCHI 682
031
4 KERALA STATE ELECTRICITY BOARD
REP.BY CHAIRMAN AND MANAGING DIRECTOR, KSEB
LTD., THIRUVANANTHAPURAM 695 001
BY ADV R.HARISHANKAR
OTHER PRESENT:
GP SYLAJA S.L.; SC FOR KSEB B.PREMOD
THIS CIVIL REVISION PETITION HAVING BEEN FINALLY
HEARD ON 20.12.2023, ALONG WITH CRP.188/2022, THE COURT
ON 16.2.2024 DELIVERED THE FOLLOWING:
CRP Nos.356/2021 & 188/22
-2-
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE V.G.ARUN
FRIDAY, THE 16TH DAY OF FEBRUARY 2024 / 27TH MAGHA, 1945
CRP NO. 188 OF 2022
AGAINST THE ORDER/JUDGMENT OPELE 549/2013 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:
POWER GRID CORPORATION OF INDIA
CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
KAKKANAD, COCHIN - 682 030, PRESENTLY AT
CONSTRUCTION AREA OFFICE, 400/220, KV SUB
STATION, KUMARAPURAM P.O, PALLIKKARA, ERNAKULAM
REPRESENTED BY ITS SENIOR GENERAL MANAGER, PIN -
683565
BY ADV MILLU DANDAPANI
RESPONDENT/S:
1 T K MURALEDHARAN
S/O NARAYANIAMMA, AGED 72 YEARS, VADAKKININARATH
HOUSE, CHERANELLOR, KOOVAPADI VILLAGE ,
KUNNATHUNADU TALUK, ERNAKULAM DISTRICT, PIN -
683544
2 THE SPECIAL TAHSILDAR (LA)
POWER GRID CORPORATION OF INDIA LTD.
CHEVARAMBALAM, KOZHIKODE, PIN - 673017
BY ADV P.T.JOSE
THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
20.12.2023, ALONG WITH CRP.356/2021, THE COURT ON 16.2.2024
DELIVERED THE FOLLOWING:
CRP Nos.356/2021 & 188/22
-3-
CRP Nos.356/2021 & 188/22
-4-
ORDER
Dated this the 16th day of February, 2024
These revision petitions are filed
challenging the common order passed by the
Additional District Judge-VI, Ernakulam in O.P.
(Electricity) No.549 of 2013. The original
petition was filed by the revision petitioner in
CRP No.356 of 2021 (hereinafter called 'the
claimant'), being dissatisfied with the
compensation awarded towards the damage and loss
sustained due to the drawing of 400 KV lines
across his property by the Power Grid Corporation
of India Ltd (hereinafter called 'the
Corporation'). The essential facts are as under;
The claimant is in ownership and possession
of landed property having an extent of 14.15 Ares
in Sy.Nos.38/16-2 and 44/8-2 of Koovappady
Village in Kunnathunadu Taluk. The land was
cultivated with various yielding and non-yielding CRP Nos.356/2021 & 188/22
trees. According to the claimant, to facilitate
drawing of the lines and smooth transmission of
power, large number of trees were cut from their
property. The drawing of high tension lines
rendered the land underneath and adjacent to the
lines useless, resulting in diminution of the
value of the property. In spite of the huge loss
suffered by the claimant, only an amount of
Rs.27,909/- was paid as compensation towards the
value of yielding and non-yielding trees cut.
Surprisingly, no compensation was granted for
diminution in land value. Hence, the original
petition was filed, seeking enhanced compensation
towards the value of trees cut and diminution in
land value.
2. The court below rejected the claim for
enhanced compensation for the value of trees cut
since no evidence in support of the claim was
produced. As far as the claim for enhanced
compensation towards diminution in land value is CRP Nos.356/2021 & 188/22
concerned, the court below relied on Ext.A7
document as well as Exts.C10 and C10(a)
commission report and sketch. Relying on
Ext.C10(a) sketch, the extent of central corridor
was held to be 0.915 cents and of the outer
corridor was held to be 7.067 cents. For the
central corridor, 40% of the land value was
granted as compensation and for the outer
corridor, 20% of the land value. Accordingly, the
claimant was found entitled to compensation of
Rs.3,02,391/-. Dissatisfied with the quantum of
enhancement, the claimant has filed CRP No.356 of
2021, whereas the Corporation has filed CRP
No.188 of 2022 contending that the enhancement
ordered is far in excess of the actual damage
sustained.
3. Heard Adv.P.T.Jose for the claimant and
Adv.Millu Dandapani for the Corporation.
4. Learned Counsel for the claimant
contended that the court below committed gross CRP Nos.356/2021 & 188/22
illegality in refusing to grant enhanced
compensation for the loss sustained due to the
cutting of valuable trees, in spite of the
Advocate Commissioner assessing and reporting the
loss. The findings in the Commissioner's report
were not relied on by the court below for the
reason that the property was inspected much after
the trees were cut. The said reasoning is flawed
since the trees were cut much after issuance of
notification by the Corporation and the cause of
action for filing the original petition arose
only on payment of the initial compensation,
even later.
5. It is submitted that the court below
grossly erred in granting only 40% of the land
value fixed for the central corridor and 20% for
the outer corridor. Considering the extent of
damage sustained and the diminution in land value
consequent to the drawing of lines, the court
below ought to have granted compensation as CRP Nos.356/2021 & 188/22
claimed.
6. Learned Counsel for the Corporation
contended that, compensation towards diminution
in land value granted is exorbitant and there is
no rationale in granting 9% interest on that
amount. The court below also erred in relying on
Ext.A7 for fixing the land value of the
claimant's property. As the drawing of electric
lines does not prohibit the landowner from
conducting agricultural activities and putting up
small structures, 40% of the land value granted
for the central corridor and 20% for the outer
corridor are exorbitant.
7. A careful scrutiny of the impugned order
reveals that the claim for enhancement of
compensation towards the value of trees cut was
rightly rejected since no supporting material,
other than the findings in the Advocate
Commissioner's report, was made available. As
found by the court below, apart from the CRP Nos.356/2021 & 188/22
interested testimony of a solitary witness, who
is the claimant in some of the connected cases,
no other independent witness was examined to
prove the claim. It is also not in dispute that
the trees were cut in the year 2011 and the
commissioner inspected the property after a long
period and had assessed the value of the trees on
a comparison with the trees standing in the
remaining property and nearby properties. Such
comparison, having no scientific basis, is not
sufficient to discard the contemporaneous
valuation statement prepared by the Corporation.
8. As far as the diminution in land value
is concerned, the factors to be taken into
consideration, as laid down in KSEB v. Livisha
[(2007) 6 SCC 792] are as under;
"10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line CRP Nos.356/2021 & 188/22
passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."
On careful scrutiny of the impugned order, it is
seen that the compensation was enhanced after
taking all the above factors into consideration.
The nature of the land, the cultivation therein,
and the manner in which the land was affected by
drawing of the lines have all been considered
fixing the land value as well as the percentage
of diminution. For the central corridor, 40% of
the land value is granted as compensation and for
the outer corridor, 20% is granted, which I find
to be just and proper. As such, there is no
illegality or material irregularity in the
impugned order, warranting intervention by this
Court in exercise of the revisional power under CRP Nos.356/2021 & 188/22
Section 115 of the Code of Civil Procedure.
For the aforementioned reasons, the civil
revision petitions filed by the claimant as well
as the Corporation are dismissed. The Power Grid
Corporation shall pay the enhanced compensation
fixed by the court below within three months of
receipt of a copy of this order.
Sd/-
V.G.ARUN JUDGE Scl/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!