Citation : 2024 Latest Caselaw 5067 Ker
Judgement Date : 15 February, 2024
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE DEVAN RAMACHANDRAN
THURSDAY, THE 15TH DAY OF FEBRUARY 2024 / 26TH MAGHA, 1945
WP(C) NO. 9080 OF 2021
PETITIONER:
DR.AMIN CONTROLLERS PRIVATE LIMITED
REPRESENTED BY ITS DIRECTOR
VIKRAM R AMIN S/O. DR. RAMANBHAI,
56 YEARS, WITH REGISTERED OFFICE
EMBASSY CHAMBERS, 6TH FLOOR, PLOT NO. 5,
ROAD NO. 3, KHAR WEST, MUMBAI 400 049
EMBASSY CHAMBERS, 6TH FLOOR, PLOT NO. 5,
ROAD NO. 3, KHAR (WEST), MUMBAI 400 052
BY ADVS.
V.JOHN MANI
ShRI.S.JAYANT
SRI.JACKSON JOHNY
SHRI.VARGHESE SABU
SHRI.SETHULAKSHMI K.K.
SMT.GAYATHRI MENON
RESPONDENTS:
1 STATE OF KERALA
REPRESENTED BY THE ADDITIONAL CHIEF
SECRETARY, KERALA WATER RSOURCES, MAIN BLOCK,
SECRETARIAT, THIRUVANANTHAPURA 690 001
2 THE MANAGING DIRECTOR,
KERALA WATER AUTHORITY, JALABHAVAN,
VELLAYAMBALAM, THIRUVANANTHAPURAM 695 033
3 THE CHIEF ENGINEER (JBIC)
OFFICE OF CHIEF ENGINEER, JBIC
ASSISTED KERALA WATER SUPPLY PROJECT,
WATER WORKS CAMPUS, VELLAYAMBALAM,
THIRUVANANTHAPURAM 695 033
4 THE BRANCH MANAGER,
SARASWAT CO OPERATIVE BANK LTD,
MADHUSAGAR MARG, N S ROAD NO. 13,
NEAR JUHU CHURCH, MUMBAI 400 049
BY ADVS.
SRI.P.BENJAMIN PAUL
V.V.JOSHI
GEORGIE JOHNY
W.P.(C).No. 9080 of 2021
:2:
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR
ADMISSION ON 15.02.2024, THE COURT ON THE SAME DAY
DELIVERED THE FOLLOWING:
W.P.(C).No. 9080 of 2021
:3:
JUDGMENT
The petitioner is conceded to be the "Third Party
Inspection Agency" qua certain works that were contracted by
the Kerala Water Authority (KWA) to different contractors, under
"Cherthala Package I" and "Cherthala Package II" - which were
essentially for laying pipelines for distribution of water under an
international collaboration. They impugn Ext.P19 proceedings of
the KWA, whereby, an amount of Rs.7,09,492/- has been found to
be their liability and they have been threatened with the
encashment of their Performance Bank Guarantee; and they
contend that this is illegal and unlawful. They thus assail
Ext.P19 as being untenable and unconstitutional.
2. Sri.John Mani - learned counsel for the petitioner,
explained the facts involved in this case saying, that his client
was entrusted with the predispatch inspection of materials, to
be used for the project; and that they have done so sincerely and
diligently. He says that, however, nearly four years after the
materials were thus supplied by the contractors, there are
alleged to be instances of burst in the pipelines; and that, in this
regard, an investigation is stated to have been done, leading to a
final conclusion against his client that they were responsible for
the afore sum, being the inspection charges disbursed to them
earlier.
3. Sri.John Mani argued that Ext.P19 is peremptorily illegal
because, it fixes two heads of liability against his client, namely,
to a sum of Rs.80,951/- qua the "Cherthala Package I" and
Rs.6,28,541/- qua the "Cherthala Package II". He argued that,
as far as the latter is concerned, it is wholly unlawful because it
has been fixed, without offering an opportunity of being heard to
his client; while, regarding the first component, it was issued
without considering any of their objections, including that,
under their contractual obligations, they were only to examine
the material on receipt at the consignee end and that too, at the
predispatch stage; and hence they cannot be held responsible
for its malfunction subsequently, on account of wrong
installation or otherwise. He argued that, as per the
agreements entered into with his client by the 'KWA', namely
Exts.P1 and P2, they were expected to only conduct third party
inspection of the pipes, which he asserted, they had done
sincerely; and that it is his client's specific case that the pipes,
after installation, had burst due to improper installation
practices and after four years of inspection. He pointed out
that, this is irrefutable because, the "GRP pipeline" is directly
buried, which is not advisable in areas like Cherthala, where the
groundwater level is high; and that the factum of his client
being not responsible for any such failure is manifest from the
fact that the aforesaid pipes are only one of the items inspected
by them and that there have been no quality deficiencies found
against any other. He thus prayed that Ext.P19 be set aside.
4. Sri.Georgie Johny - learned standing counsel for the
'KWA', in response, submitted that the allegation of the
petitioner, that they were not heard before Ext.P19 was issued is
belied from the last paragraph in its second page, wherein, it
has been clearly recorded that their replies/explanations were
considered by the High Level Committee. He then pointed out
that the liability in Ext.P19 was not fixed immediately, but only
after the Authorities obtained another quality inspection report
from CIPET - which is a premiere Government of India
Institution - whose test results show "failure". He submitted
that, therefore, this is a case where the doctrine of Res ipsa
loquitur would apply; and that the petitioner, by the very factum
of the test results from CIPET being as afore, would have to be
held responsible even for the burst of the pipeline, but which
has been spared to them, by confining their liability only to the
extent of the inspection charges paid to them - which he argued
was not eligible to them on account of their failure specifically
mentioned in Ext.P19. He thus prayed that this writ petition be
dismissed.
5. Before I go on with the evaluation of the rival
submissions, I must place on record one pertinent development.
6. The petitioner concededly had furnished a bank
guarantee to the KWA and noticing the same, a learned Judge of
this Court had, on 09.04.2021, issued an order to the fourth
respondent, not to encash the same, provided they renew it
within a particular period from then. It is now brought to my
notice by Sri.Georgy Johny - learned standing counsel for the
'KWA', that the bank guarantee was renewed by the petitioner
only for a short while thereafter, until 30.09.2022; and that it
has not been renewed thereafter.
7. I must say that the actions of the petitioner, in refusing
to extend the bank guarantee, after obtaining an interim order
as afore, is rather unfortunate because, this amounts to an
attempt to circumvent legal processes. If they had a case that
they had renewed the bank guarantee until 30.09.2022 and that
there were no orders to extend it further, propriety demands
that pending litigation, they ought to have approached this
Court and sought further clarification, particularly when they
enjoyed an interim order, which was granted by this Court solely
under the impression that the bank guarantee would be kept
alive. The consequence is that the said order now stands
frustrated because, the bank guarantee has not been renewed;
and obviously, therefore, the petitioner cannot be granted any
benefit, if they continue with such a conduct.
8. That being said, when I examine Ext.P19, I must say that
I find force with some of the submissions made on their behalf
by their learned counsel - Sri.John Mani.
9. This is because, even though the said order says that
replies and explanations of the petitioner were placed before the
High Level Committee, there is absolutely nothing in it, as to
how it was dealt with and what were the observations of that
Committee, or the decisions that were taken thereafter.
10. As argued by Sri.Georgie Johny, the 'KWA' appears to
have been swayed by the factum of CIPET having issued a
"failure" report. But the specific contention of the petitioner -
that the "GRP pipes" are only one of the components certified by
them, with the others having been found to be without defect;
and further that it was the installation of the pipes which has
created the burst - does not appear to have been adverted to,
much less considered. To add to this, their singular imputation,
that the "GRP pipeline" ought not to have been buried in areas
like Cherthala, where the groundwater level is high, has also not
been examined or answered.
11. Apart from the afore, as regards the fixing of liability of
Rs.6,28,541/-, the petitioner asserts that they were never heard
and this is a specific averment in this writ petition also.
According to them, the other component of Rs.80,951/- has also
been imposed upon them illegally because, they were
responsible only for the predispatch inspection, until the
consignee end, but not after it has been put to use for the laying
of the pipelines.
12. As long as the afore issues remain unanswered in
Ext.P19, I cannot find favour with it.
13. I have, therefore, no doubt that the claims of the
petitioner will certainly have to be reconsidered by the
competent Authority, after giving them an opportunity of being
heard and of preferring their version; and that this is imperative
to ensure fairness in procedure.
14. However, as I have already said above, the conduct of
the petitioner, in not renewing the bank guarantee stands
against them; and hence, any relief can be granted by this Court
only if they agree to do so. I, therefore, put it to Sri.John Mani
V. - learned counsel for the petitioner, whether his client will
renew the bank guarantee, to which, his reply was to the
affirmative; and undertook that, until such time as the exercise
to be ordered by this Court is completed, the same will be kept
alive.
15. In the afore circumstances, I order this writ petition
with the following directions:
(a) The impugned Ext.P19 will stand set aside, qua
the petitioner .
(b) The competent Authority of the 'KWA' will
reconsider the claims of the petitioner, after affording
them an opportunity of being heard, and of preferring
an explanation / objection to the action proposed
against them; thus culminating in an appropriate
fresh order, as expeditiously as is possible, but not
later than four months from the date of receipt of a
copy of this judgment
(c) I, however, make it clear that the afore directions
will inure to the benefit of the petitioner, only if they
renew the bank guarantee for a minimum period of
one year, and furnish the same before the 'KWA',
within a period of one week from the date of receipt
of a copy of this judgment. If they fail to do so, the
directions in this judgment will stand vacated, and the
'KWA' will be at full liberty to recover the amounts
quantified under Ext.P19 from them, without any
further orders having to be obtained from this Court.
This writ petition is thus ordered.
Sd/-
DEVAN RAMACHANDRAN JUDGE stu/anm
APPENDIX OF WP(C) 9080/2021
PETITIONER EXHIBITS EXHIBIT P1 A TRUE COPY OF WORK ORDER NO. KWA /JBIC/HQ/W-1620/04 DATED 9/2/2007 IN THE NAME OF ITENG ENGINEERING EXHIBIT P2 A TRUE COPY OF AGREEMENT EXECUTED BY THE 3RD RESPONDENT AND PETITIONER DATED 20-02-2007 EXHIBIT P3 A TRUE COPY OF SUPPLEMENTAL AGREEMENT EXECUTED BY 3RD RESPONDENT AND PETITIONER IN THE MONTH OF AUGUST 2007 EXHIBIT P4 A TRUE COPY OF INSPECTION REPORT ISSUED BY ITENG ENGINEERING AS REPORT NO KWA GRAPHITE BA-01 DATED 11-10-2008 EXHIBIT P4(a) TRUE COPY OF INSPECTION REPORT ISSUED BY ITENG ENGINEERING AS REPORT NO. KWA GRAPHITE BA-02 DATED 21-10-2008 EXHIBIT P4(b) TRUE COPY OF INSPECTION REPORT ISSUED BY THE ITENG ENGINEERING AS REPORT NO.
KWA GRAPHITE BA-03 DATED 21-10-2008 EXHIBIT P4(c) TRUE COPY OF INSPECTION REPORT ISSUED BY ITENG ENGINEERING AS REPORT NO. KWA GRAPHITE BA-04 DATED 21-10-2008 EXHIBIT P5 TRUE COPY OF LETTER ISSUED BY DEPUTTY CHIEF ENGINEER, KERALA WATER AUTHORITY, DATED 20-01-2009 EXHIBIT P6 A TRUE COPY OF LETTER ISSUED BY 3RD RESPONDENT DATED 23-04-2010 EXHIBIT P7 TRUE COPY OF LETTER ISSUED BY TECC TO PETITIONER VIDE LETTER NO TEC/SKK/30/39/12/661 DATED 6-10-2012 EXHIBIT P8 THE TRUE COPY OF REPLY SUBMITTED BY PETITIONER TO TEC VIDE LETTER NO.
IEC/TEC/2012/444 ON 11-10-2012 EXHIBIT P9 A TRUE COPY OF LETTER ISSUED BY 2ND RESPONDENT ISSUED A LETTER VIDE NO.
KWA/JICA/CE/W-3118/12 DATED 28-02-2014 TO VICE PRESIDENT M/S. ITENG ENGINEERING.
EXHIBIT P10 A TRUE COPY OF REPLY SUBMITTED BY PETITIONER TO 2ND RESPONDENT AGAINST THE EXHIBIT P9 LETTER VIDE LETTER NO DACPL/KWA-JBIC/176/2014 DATED 10-03-
EXHIBIT P11 TRUE COPY OF LETTER NO WS-
B1/145/2016/WRD ISSUED BY 1ST RESPONDENT TO 2ND RESPONDENT DATED 17- 05-2019 EXHIBIT P12 A TRUE COPY PROCEEDINGS NO.
KWA/JICA/CE/W-3118/12 DATED 25-11-2019 EXHIBIT P13 A TRUE COPY OF LETTER ISSUED BY PETITIONER TO 2ND RESPONDENT ON 19-12- 2019 VIDE LETTER DACPL/KWA/2019-20/680 EXHIBIT P13(a) AN EXTRACT OF TENDER CONDITION CLAUSE 1 TO 13 OF WORK ORDER NO.
KWA/JBIC/HQ/W-1620/04 DATED 9-2-2007 EXHIBIT P14 TRUE COPY OF LETTER ISSUED BY 3RD RESPONDENT AS NO. KWA/JICA/E5- 1448/2015 DATED 29-05-2020 TO BRANCH MANAGER, SARASWAT COOPERATIVE BANK LTD MUMBAI.
EXHIBIT P15 A TRUE COPY OF PETITION TO ACCEPT ADDITIONAL DOCUMENTS ALONG WITH DOCUMENTS FILED AS I.A NO. 1 OF 2020 IN W.P(C) NO. 13408 OF 2020 EXHIBIT P16 A TRUE COPY OF JUDGMENT IN W.P(C) NO.
13408 OF 2020 DATED 06-10-2020 OF THIS HON'BLE COURT EXHIBIT P17 A TRUE COPY OF LETTER ISSUED BY 3RD RESPONDENT AS KWA/JICA/E5-1448/2015(1) DATED 25-02-2021 EXHIBIT P18 A TRUE COPY OF REPLY SUBMITTED BY THE PETITIONER TO EXHIBIT P17 LETTER DATED 10-03-2021 EXHIBIT P19 A TRUE COPY OF PROCEEDINGS OF 2ND RESPONDENT AS NO. KWA/JICA/CE/W-
3118/AMIN-CTRLS/2020 DATED 15-03-2021 EXHIBIT P20 A TRUE COPY OF LETTER NO.
KWA/JICA/CE/W-3118/AMIN CTRLS/2020 DATED 17-03-2021 ISSUED BY 2ND RESPONDENT.
RESPONDENTS' EXHIBITS Exhibit R2(a) TRUE COPY OF THE TEST RESULTS CONDUCTED ON 26.3.2013 AT THE CENTRAL INSTITUTE OF PLASTICS ENGINEERING AND TECHNOLOGY(CIPET), HYDERABAD, A CENTRAL GOVERNMENT OTGANIZATION Exhibit R2(b) TRUE COPY OF THE MINUTES, IN THE MEETING CONDUCTED BY THE HON'BLE MINISTER FOR WATER RESOURCES ON 10.12.2014, IT HAD BEEN DIRECTED TO
REPLACE THE FRP PIPES IN PACKAGE II CHERTHALA SCHEME Exhibit R2(c) TRUE COPY OF THE TEST RESULTS DATED 15.11.2016 CONDUCTED THROUGH M/S. CIPET, HYDERABAD Exhibit R3(a) TRUE COPY OF THE LETTER DATED 8/8/2022 GIVEN TO THE 4TH RESPONDENT IN WP(C) Exhibit R3(b) TRUE COPY OF THE LETTER DATED 8/8/2022, TO THE PETITIONER BY THIS RESPONDENT IN WP(C) Exhibit R3(c) TRUE COY OF THE LETTER DATED 4/10/2022,FROM PETITIONER TO THIS RESPONDENT IN WP(C)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!