Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Irikkur Construction Company vs The Project Director
2024 Latest Caselaw 5041 Ker

Citation : 2024 Latest Caselaw 5041 Ker
Judgement Date : 15 February, 2024

Kerala High Court

Irikkur Construction Company vs The Project Director on 15 February, 2024

Author: Devan Ramachandran

Bench: Devan Ramachandran

WP(C) No.16780/2023                        1/8

                         IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                         PRESENT
                      THE HONOURABLE MR. JUSTICE DEVAN RAMACHANDRAN
            Thursday, the 15th day of February 2024 / 26th Magha, 1945
                   IA.NO.1/2024 IN WP(C) NO. 16780 OF 2023 (V)
   PETITIONER/PETITIONER :

          IRIKKUR CONSTRUCTION COMPANY, MH TOWER, IRIKKUR P.O., IRUKKUR,
          KANNUR - 670593, REPRESENTED BY ITS MANAGING PARTNER

   RESPONDENTS/RESPONDENTS :

      1. THE PROJECT DIRECTOR, KERALA ROAD FUND BOARD, BSNL BUILDING, PMG
         JUNCTION, TRIVANDRUM - 695003
      2. URALUNGAL LABOUR CONTRACT CO-OPERATIVE SOCIETY LIMITED, MADAPPALLI
         COLLEGE P.O., VADAKARA, KOZHIKODE - 673102, REPRESENTED BY ITS
         CHAIRMAN
      3. STATE OF KERALA REPRESENTED BY SECRETARY TO GOVERNMENT, PUBLIC WORKS
         DEPARTMENT, GOVERNMENT SECRETARIAT, THIRUVANANTHAPURAM - 695001


        Application praying that in the circumstances stated in the
   affidavit filed therewith the High Court be pleased to amend the writ
   petition incorporating the additional paragraphs 20 to 28 and, Grounds I
   to S and additional prayers (g) and (h) 19 and to accept the additional
   documents produced along with the affidavit and marked & produced as
   Exhibit P-12, P-13 and P-14 on file.

          2. The following be added as Paras 20 onwards to the Writ Petition:

        20. The very stand taken by the first respondent in this regard is
   against the government orders and prevailing law. It is true that as per
   Exhibit P5 Labour Contract Societies are entitled for Price Preference up
   to 10% over the quoted amount of the lowest bidder. That is the typical
   condition that the bidder with the lowest evaluated Bid price will be
   awarded the work as been modified such that if there is an approved labour
   Contract Society within 10% of the quoted amount of the lowest bidder, the
   work will be awarded to the Labour Contract Society.

        21.The Exhibit P-5 government order is illegal, arbitrary, and
   against the fundamental rights of petitioner. It is further submitted that
   by implementing Exhibit P-5 huge loss will be caused to the Public
   Exchequer as the Bid of the Labour Contract Societies are not the lowest
   Bid but preference to be given. Thus, preference to the Labour Contract
   Societies in the high-priced bids would certainly be a loss to the
   Government itself.

        22 It is submitted that the conditions extracted above flow from
   Exhibit P-5 order as well as a series of earlier notification that sought
   to confirm certain benefits on Labour Contract Societies. It is further
   submitted that Government initially issued an order to entrust work on
   preferential terms and conditions to Labour Contract Corporative
 WP(C) No.16780/2023                      2/8

   societies, as per Government Order dated 13/11/1997. A true copy of the
   GO(MS) No.135/ 97/Co- op dated 13/11/1997 is produced herewith and marked
   as Exhibit P-12.

        23 Subsequently, in the year 2004 another Government Order was
   issued modifying Exhibit P-12 to the extent that Clause 8(1)(b) of Exhibit
   P-12 will not be applicable to contracts administered with the Public
   Works Department. A true copy of the GO (MS) No. 44/04/PWD dated
   19/03/2004 is produced herewith and marked as Exhibit P-13.

        24 It is submitted that the rationale behind the issuance of Exhibit
   P-13, which applies only to PWD tenders, applies with equal force to non
   PWD tenders as well. Additionally, it is submitted that the rules and
   provisions governing non PWD tenders also do not permit post-tender
   negotiations except with the lowest bidder, which is what is effectively
   achieved by the operation of Exhibit P-12 as recognised in Exhibit P-13
   itself. Exhibit P-13 has not been superseded and is still in force. It is
   also pertinent to point out that the challenge against the same by the
   second Respondent ended in vain.

        25 It is further submitted that Exhibit P-5, P-12 and P-13 and other
   orders giving priority to second respondent were challenged before this
   Hon'ble Court by another Contractor and same was ended in dismissal. The
   Writ Appeal, (Wa No.44/2021 and 47/2021) are pending before the Division
   Bench of this Hon'ble Court.

        26 Subsequently, in all the tenders invited by the PWD and the
   Bodies under it incorporated the conditions stated in the above Government
   Order with an intention to give more benefits to the second respondent.
   Such action on the part of the respondents are arbitrary, illegal,
   malafide and discriminatory in nature.

        27 Meanwhile on 04/11/2020, the Department of Corporation of the
   State issued an order granting special permission to the second respondent
   to undertake work over and above the scope of what is permitted under
   Exhibit P-13, such as National Highways, Multistorey Buildings, Irrigation
   Works, Bridges etc. A true copy of the GO(RT) No.568/2020/Co.op dated
   04/11/2020 is produced herewith and marked as Exhibit P-14. Exhibit P-14
   arbitrarily and illegally favors second respondent to the exclusion of all
   others and ensures that the benefits envisioned under the earlier
   Government Orders are extended to them across all works undertaken by the
   state Government, despite the same being specifically restricted earlier.

        28 In the year 2021, the government had considered the issue and by
   a comprehensive Government order, Exhibit P-6 it was notified that Labour
   Contract Societies are entitled for price preference with a ceiling limit
   and going by that no preference can be granted in respect of subject work.

          3. The following paragraphs may be added as GROUND I onwards:-

          I. The impugned conditions incorporated in various government orders
 WP(C) No.16780/2023                    3/8

   under challenge in this writ petition is illegal and liable to be set
   aside and they are discriminatory in nature and confer an unlawful
   advantage upon the second respondent.

        J. Award the work to the second respondent by replying to the
   impugned conditions in Exhibit P-5. P-12, P-13 & P-14 are violative of the
   fundamental rights of the petitioner guaranteed under the Constitution of
   India.

        K. It is a basic principle enshrined in the Constitution that any
   discrimination among the people can only be affected through a law passed
   by the legislature. The special conditions that favor the second
   respondent in the Government Orders under challenge are tantamount to
   creating economic reservations. The Government Orders under challenge here
   are not Laws and therefore reservations put into effect through them
   cannot stand. Furthermore, the discrimination sort to be effected by them
   failed the tests of intelligible differentia and rational nexus as laid
   down in State Of West Bengal Vs. Anwar Ali Sarkar(1952 SCR 284), that must
   be an order for classification to be legal. The system that favors the
   second respondent to the exclusion of all other bidders when it comes to
   high value tenders is in the teeth of these Constitutional Principles.

        L. The conditions under challenge in Exhibit P-5, P-12, P-13 and
   P-14 do not merely extent certain concession to Labour Contract societies,
   but do so in a manner that effectively ensures that whenever such a body
   participating in a tender, it can be awarded a work irrespective of who
   submitted the lowest bid. Thus, it effectively negates any reasonable
   chance of private contractors must be awarded the work. The private
   contractor like the petitioner with the lowest bid can be awarded the work
   only if the second respondent do not participate in the tender or with its
   consent. This is fundamentally opposed to the principles of competition,
   fairness, and equality that underly the process of tendering. Therefore,
   this Hon'ble Court will be justified in interfering with the Government
   Orders under challenge.

        M. The second respondent is not eligible for the benefits extended
   to Labour Contracts Cooperative Societies under the challenged conditions
   of Exhibit P-5 and the other Government Orders under which the price
   preference in question has been awarded to such societies the eligibility
   criteria for obtaining the same are specified in Clause 4 of Exhibit P-12
   G.O. It is submitted that the price preference is being granted to the
   bids of the second respondent without application of mind, and that in-
   fact the second respondent does not satisfy the eligibility criteria.
   Therefore, the steps being taken by the first respondent to award the
   tender to the second respondent is to be interdicted.

        N. The impugned conditions in Exhibit P-5, P-12, P-13 and P-14 are
   arbitrary, illegal and opposed to public interest. BY awarding the
   contracts to the second respondent the state is losing huge amount, which
   otherwise entitled and offered by the private contractors like the
   petitioner. A price preference in such case cannot be granted since the
 WP(C) No.16780/2023                    4/8

   same is being done at the cost of all citizens, to enrich a select entity
   or group.

        O. The preferential treatment sought to be extended to the second
   respondent is indicative of an attempt to bring about a "spoils system".
   The Apex Court in Supreme Court Advocates On Record Association Vs. Union
   Of India (2016 (5) SCC 1) held that it is necessary to appreciate that the
   constitution does not envisage the 'spoils system' ( also known as
   patronage system) wherein the political party which wins an election gives
   Government position to its supporters, friends and relatives as a reward
   for working towards victory and as an incentive to keep the party in
   power.

        P. It is relevant to note that the second respondent who is having
   wide influence in the government is getting the work flouting the Central
   Vigilance Commission and all the prevailing Government orders. The action
   of the first respondent would implied make it clear the political
   influence of the second respondent.

        Q. In Air India Ltd. Vs. Cochin International Airport Ltd., (2000
   (2) SCC 617) the Hon'ble Court had held that the state, its corporations,
   instrumentalities, and agencies are bound to adhere to the norms,
   standards and procedure laid down by them and cannot depart from them
   arbitrarily and that they have the public duty to be fair to all
   concerned. While a decision itself may fall outside the scope of Judicial
   Review, the Court can examine the decision-making process and interfere if
   it is found vitiated by malafide, unreasonableness and arbitrariness. It
   is submitted that in the instant case, the process followed to arrive at
   the exemption granted to the second respondent under Exhibit P8 and
   determination that second respondent is eligible to take benefits of the
   price preference provided under the Government orders under challenge, is
   tailored to favor the second respondent in an unreasonable and malafide
   manner. The unreasonableness and arbitrariness, explicitly clear from the
   actions of the first respondent, warrants interference of this Hon'ble
   Court.

        R. It is the duty of the tendering authority to secure maximum
   public participation in the procurement process as held by the Apex Court
   in Karnataka State Industrial Investment And Development Corporation Ltd.
   Vs Cavalet India Ltd., and others (2005 (4) SCC 456). However, in the case
   of the second respondent the state has made considerable efforts to
   minimize the public participation as much as possible and tailored the
   process relating to tenders to favor the second respondent, to the extent
   that no other contractors shall be able to compete in the process. Such
   action on the part of the State as well as the first respondent are to be
   interdicted.

        S. In Union of India Vs. Hindustan Development Corporation (AIR 1994
   SC 988), The Hon'ble Supreme Court held that "Government had the right to
   either accept or reject the lowest offer but that of course, if done on a
   policy, should be on some rational and reasonable grounds". The price
 WP(C) No.16780/2023                      5/8

   preference provided exclusively to second respondent in this case is
   neither rational nor reasonable.

          The following prayer also to incorporated as Prayer (g) & (h):-

        Prayer (g) : issue a writ of certiorari or any other writ or order
   or direction calling for the records leading to Exhibits P-5, P-12, P- 13,
   & P-14 and quash the same.

        h). issue a mandamus or any other writ or order or direction
   declaring that the second respondent is not entitled for the price
   preference granted under various government orders such as Exhibit
   Exhibits P-5, P-12, P-13, & P-14;


        This Application coming on for orders upon perusing the application
   and the affidavit filed in support thereof, and this Court's order dated
   05.02.2024 and upon hearing the arguments of M/S.DEEPU THANKAN, UMMUL
   FIDA, LAKSHMI SREEDHAR, LEKSHMI P. NAIR & NAMITHA K.M., Advocates for the
   petitioner, SRI.K.V.MANOJ KUMAR Advocate for R1 in I.A/WP(C), GOVERNMENT
   PLEADER for R1 & R3 in I.A/WP(C) and of SRI.M.SASINDRAN, Advocate for R2
   in I.A/WP(C), the Court passed the following:
 WP(C) No.16780/2023                            6/8




                           DEVAN RAMACHANDRAN, J.
                      --------------------------------------------------
      I.A.Nos.1/2024 in WP(C) Nos.16780/2023 & 20252/2023
                      --------------------------------------------------
                      Dated this the 15th day of February, 2024


                                        O R D E R

The petitioner seeks that these Writ Petitions be allowed to

be amended in the manner prayed for and offers to produce the

amended ones on or before 20.02.2024.

Sri.S.Kannan - learned Senior Government Pleader, objected

to the amendments; but thereafter, sought liberty for his client to

contest the prayers - to be brought in such amendment - on

their maintainability.

In the afore circumstances, with the afore requested liberty

being reserved to the official respondents, I allow these

applications.

The petitioner will file the amended Writ Petitions on or

before 20.02.2024.

WP(C)16780/23 & 20252/23

Post the Writ Petitions on 21.02.2024.

Sd/-

DEVAN RAMACHANDRAN, RR JUDGE

15-02-2024 /True Copy/ Assistant Registrar

APPENDIX OF WP(C) 16780/2023 Exhibit P-5 TRUE COPY OF THE GOVERNMENT ORDER DATED 09/02/2021 Exhibit P-6 TRUE COPY OF GO(MS).NO.21/2022/PWD DATED 29/07/2022 Exhibit P-8 TRUE COPY OF THE JUDGMENT RENDERED BY THE DIVISION BENCH OF THIS HON'BLE COURT IN W.A.NO.132/2023 DATED 31/01/2023 Exhibit P12 A TRUE COPY OF THE GO(MS) NO.135/ 97/CO-OP DATED 13/11/1997 Exhibit P13 A TRUE COPY OF THE GO (MS) NO. 44/04/PWD DATED 19/03/2004 Exhibit P14 A TRUE COPY OF THE GO(RT) NO.568/2020/CO.OP DATED 04/11/2020

15-02-2024 /True Copy/ Assistant Registrar

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter