Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

K.Ummer vs Chief Electrical Engineer
2023 Latest Caselaw 4131 Ker

Citation : 2023 Latest Caselaw 4131 Ker
Judgement Date : 31 March, 2023

Kerala High Court
K.Ummer vs Chief Electrical Engineer on 31 March, 2023
W.P.(C). No.12192 of 2021              1




                  IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                    PRESENT
                  THE HONOURABLE MR. JUSTICE SHAJI P.CHALY
       FRIDAY, THE 31ST DAY OF MARCH 2023 / 10TH CHAITHRA, 1945
                            WP(C) NO. 12192 OF 2021
PETITIONER:

              K.UMMER
              AGED 63 YEARS
              S/O. MOIDEEN, RESIDING AT KUTTEERI HOUSE, AMBALAVAYAL
              P.O, WAYANAD 673 593
              BY ADVS.
              V.HARISH
              RAJAN VISHNURAJ


RESPONDENTS:

              CHIEF ELECTRICAL ENGINEER,
              PUBLIC WORKS DEPARTMENT (ELECTRICAL WING) OFFICE OF THE
              CHIEF ELECTRICAL ENGINEER, THIRUVANANTHAPURAM 695 001



              BY SMT.RESHMI.K.M. - SENIOR GOVERNMENT PLEADER


       THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
31.03.2023, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 W.P.(C). No.12192 of 2021                  2




                                     JUDGMENT

Dated this the 31st day of March, 2023

This writ petition is filed by an A Class Contractor challenging Exhibit P12

order passed by the Chief Engineer, Public Works Department, Building Section,

Thiruvananthapuram dated 20.2.2021, declining to renew the electrical

contractor licence of the petitioner, apparently on the basis of the termination of

works at the risk and cost of the petitioner still pending consideration; and for a

writ of mandamus directing the respondent to renew the petitioner's contractor

licence by processing Exhibit P7 application.

2.Brief material facts for the disposal of the writ petition are as follows:

2.1 According to the petitioner, in the year 2011, the petitioner had

undertaken works under LI Scheme for the electrification works of various

irrigation projects of 5 Panchayats in Wayanad District. Petitioner executed an

agreement for six works under one agreement. It is the case of the petitioner

that the civil and mechanical works in the said irrigation sites were not

completed and consequent to which, petitioner could not complete the work in

time. It is further submitted that in spite of the non completion of civil and

mechanical works, petitioner had installed panel boards in the pump houses in 5

Panchayats. According to the petitioner, petitioner has submitted various

representations before the statutory authorities narrating the difficulties faced by

the petitioner in completing the work. It is the case of the petitioner that 95% of

the works were completed and communicated the inability for completing the

remaining 5% of the works.

3. Anyhow, the work awarded to the petitioner was terminated at the risk

and cost of the petitioner and directed to recover an amount of Rs.69,100/-,

evident from Exhibits P5 and P6 orders dated 17.1.2020 and 16.10.2020,

respectively. The case projected by the petitioner is that in order to avoid any

further complex and other situations, petitioner did not challenge the termination

of the work at the risk and cost of the petitioner and the adjustment of the

amount made from the bill amount due to the petitioner. It is further submitted

that now several years have elapsed and merely because 5% work could not be

completed by the petitioner, the renewal of licence of the petitioner cannot be

withheld by the respondent indefinitely.

4. The respondent has filed a detailed counter affidavit justifying his stand.

Petitioner has filed a reply affidavit reiterating the stand adopted in the writ

petition. It is an admitted fact that in so far as the termination of the contract at

the risk and cost of the petitioner and the adjustment of the amount of

Rs.69,100/- from the bill amount due to the petitioner, it is not under challenge.

The sole relief sought for by the petitioner is consideration of Exhibit P7

application.

5. I have heard learned counsel for petitioner - Sri.Harish Vasudevan and

learned Senior Government Pleader - Smt.Reshmi.K.M.

6. The deliberation made above would make it clear that the petitioner has

conceded to the termination of contract and the recovery of the amounts due

from the bill amount due to the petitioner. According to the petitioner, the

electrical work could not be completed due to multiple factors, including failure

on the part of the contractors, who were doing civil and mechanical works, to

complete the work enabling the petitioner to carry out electrical works.

7. Whatever that be, it is clear from Exhibits P5 and P6 that the risk and cost

element involved is only Rs.69,100/-, which was credited to the account of the

Government. Merely because there was some default on the part of the

petitioner to complete a portion of the work, it cannot be said that the petitioner

is liable to be disqualified forever. Now three years have elapsed from the date

of termination of the work i.e., Exhibit P5 dated 17.1.2020. Taking into account

the risk and cost amount involved in the case of the petitioner, I think it is only

appropriate that the respondent is directed to consider Exhibit P7 application

submitted by the petitioner for renewal of registration dated 30.12.2019 bearing

in mind the observations contained above.

8. Therefore, the writ petition is allowed to the extent of directing the

respondent to consider Exhibit P7 application submitted by the petitioner taking

into account the observations made above, and the trivial nature of risk and cost

factor imposed against the petitioner by imposing liquidated damages of

Rs.69,100/- for not completing the electrical work undertaken by the petitioner;

at the earliest, at any rate, within a month from the date of receipt of a copy of

this judgement.

Sd/-

                                                 SHAJI P.CHALY

smv                                                   JUDGE





                            APPENDIX OF WP(C) 12192/2021

PETITIONER'S EXHIBITS
Exhibit P1            A TRUE COPY OF THE CONTRACTOR'S REGISTRATION
                      CARD ISSUED BY THE PWD TO THE PETITIONER.
Exhibit P2            A TRUE PHOTOCOPY OF LETTER DATED 15-09-2014
                      ISSUED BY THE PETITIONER TO THE EXECUTIVE
                      ENGINEER, PWD (ELECTRICAL DIVISION),
                      KOZHIKODE
Exhibit P3            A TRUE PHOTOCOPY OF THE COMMUNICATION DATED
                      25-05-2015 ISSUED BY THE PETITIONER TO THE
                      ASSISTANT ENGINEER, PWD (ELECTRICAL
                      DIVISION), KALPETTA
Exhibit P4            A TRUE PHOTOCOPY OF THE REPRESENTATION DATED

07-03-2019 PREFERRED BY THE PETITIONER BEFORE THE MINISTER, PWD.

Exhibit P5 A TRUE PHOTOCOPY OF THE ORDER NO. EL2-598 E/2020 DATED 17-01-2020 ISSUED BY THE RESPONDENT Exhibit P6 A TRUE PHOTOCOPY OF THE ORDER NO. EL2-598 E/2020 DATED 16-10-2020 ISSUED BY THE RESPONDENT Exhibit P7 A TRUE PHOTOCOPY OF THE APPLICATION FOR RENEWAL DATED 30-12-2019 PREFERRED BY THE PETITIONER BEFORE THE RESPONDENT.

Exhibit P8 A TRUE PHOTOCOPY OF THE COMMUNICATION DATED 29-02-2020 ISSUED FROM THE OFFICE OF THE RESPONDENT TO THE PETITIONER.

Exhibit P9 A TRUE PHOTOCOPY OF THE G.O(RT) NO 402/2020/PWD DATED 07-04-2020 ISSUED BY THE DEPARTMENT OF PUBLIC WORKS Exhibit P10 A TRUE PHOTOCOPY OF THE LETTER DATED 22-04-

2020 SUBMITTED BY THE PETITIONER BEFORE THE RESPONDENT.

Exhibit P11 A TRUE PHOTOCOPY OF THE PERFORMANCE COMPLETION CERTIFICATE DATED 22-02-2021 ISSUED BY THE ASSISTANT EXECUTIVE ENGINEER, PWD (ELECTRICAL) Exhibit P12 A TRUE PHOTOCOPY OF THE LETTER NO. EL4 5227 E/95 DATED 20-02-2021 ISSUED BY THE RESPONDENT.

SENT TO THE EXECUTIVE ENGINEER, KERALA PWD ELECTRICAL DIVISIOON KOZHIKODE DISTRICT AS WELL AS ASSISTANT EXECUTIVE ENGINEER, ELECTRICAL SUB DIVISION , KALPETTA, WAYANAD Exhibit P14 A TRUE PHOTOCOPY OF THE LETTER NO EL 1.219/2021 DATED 17.2.2022 FROM THE OFFICE OF THE EXECUTIVE ENGINEER, KERALA PWD ELECTRICAL DIVISION, KOZHIKODE DISTRICT RESPONDENT EXHIBITS Exhibit R1(a) True copy of the letter number D1-422/09 dated 21-08-2013 Exhibit R1(b) True copy of the letter number D1-422/09 dated 03-10-2013 Exhibit R1(c) True copy of the letter number D1-422/09 dated 24-04-2013 Exhibit R1(d) True copy of the final notice dated 10-05-

Exhibit R1(e) True copy of the termination order dated 17-

01-2020

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter