Citation : 2023 Latest Caselaw 3370 Ker
Judgement Date : 24 March, 2023
C.R.
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE A.MUHAMED MUSTAQUE
&
THE HONOURABLE MRS. JUSTICE SHOBA ANNAMMA EAPEN
FRIDAY, THE 24TH DAY OF MARCH 2023 / 3RD CHAITHRA, 1945
RFA NO. 36 OF 2019
AGAINST THE JUDGMENT DATED 24.11.2017 IN OS 67/2013 OF
SUB COURT, ERNAKULAM
APPELLANTS/DEFENDANTS:
1 STATE OF KERALA
REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM
2 THE EXECUTIVE ENGINEER,
OFFICE OF THE EXECUTIVE ENGINEER, MAJOR
IRRIGATION DIVISION, KAKKANAD, ERNAKULAM
3 THE ASSISTANT EXECUTIVE ENGINEER,
MAJOR IRRIGATION SUB- DIVISION, KAKKANAD,
ERNAKULAM
BY ADV GOVERNMENT PLEADER
ADV. K.V. MANOJ KUMAR SR. GP
RESPONDENT/PLAINTIFF:
BABY VARGHESE, S/O. VARGHESE, NADAKKAL HOUSE,
KIZHUURY P.O., RAMAMANGALAM, ERNAKULAM,PIN-686
663
BY ADVS.
SRI.RAJESH CHERIAN
SRI.V.VINAY MENON
P.T.MOHANKUMAR(K/78/1983)
THIS REGULAR FIRST APPEAL HAVING COME UP FOR
ADMISSION ON 22.03.2023, THE COURT ON 24.03.2023
DELIVERED THE FOLLOWING:
RFA NO. 36 OF 2019
..2..
C.R.
A.MUHAMED MUSTAQUE & SHOBA ANNAMMA EAPEN, JJ.
----------------------------------------------
R.F.A No. 36 of 2019
----------------------------------------------
Dated this the 24th day of March, 2023
J U D G M E N T
A. Muhamed Mustaque, J
This appeal was filed by the State
challenging a decree allowing the plaintiff to
recover Rs.62,58,000/- together with 6% interest
from the State.
2. The plaintiff is a contractor and he was
engaged by the Public Works Department (PWD) for
dredging, cleaning and improving the boundary
canal in West Cochin known as Rameswaram-Calwati
Canal. The nature of work has been specifically
mentioned in the agreement executed between the
plaintiff and the Department. The plaintiff had a
two-fold claim. One is based on the agreement
and the other is based on the work undertaken on RFA NO. 36 OF 2019
..3..
the alleged instruction of the Department and the
local MLA. According to the plaintiff, though he
was entitled for more than Rs.97,45,032/- from
the Department, he limited his claim to Rs.47
Lakhs for the purpose of valuation and court fee.
Besides the above claim, he also demanded the
return of the retention amount of Rs.9 Lakhs and
Rs.1 Lakh deposited towards security. The
plaintiff also claimed damages to the tune of
Rs.5 Lakhs from the Department.
3. The trial court allowed all other claims
except the claim for damages. We are not able to
discern from the trial court judgment as to how
the trial court arrived at the calculation of the
amount. At the appellate stage, the learned
counsel for the appellant pointed out that a
calculation statement was made based on
measurements recorded in Ext.B2 series and that
statement was given to the trial court Judge. A
copy of the calculation statement was also made RFA NO. 36 OF 2019
..4..
available before us for perusal.
4. The learned Senior Government Pleader
Sri. K.V. Manoj Kumar pointed out that the trial
court having declined the relief as against the
declaration to the effect that the plaintiff was
not liable to execute the remaining part of the
work and that the balance work shall not be at
his risk and cost, this Court could not have
granted the decree sought by the plaintiff for
recovering the money. The learned Government
Pleader further submitted that the contract
having been terminated at the risk of the
plaintiff, he is liable to compensate the
government for the loss.
5. Before we proceed to decide the question
involved in this case, we need to state the law
regarding quantification of loss and recovery by
the State based on contract. There are different
views expressed at the Bar in regard to the
unilateral determination of loss and retention of RFA NO. 36 OF 2019
..5..
the amount due as well as also recovery by the
State based on the alleged breach of contract.
It is to be noted that the State is empowered to
recover its dues by raising demand as public dues
of revenue on land under the Revenue Recovery
Act, 1890. The question is whether the State can
unilaterally determine its loss and has any right
to retain any amount payable to the plaintiff
contractor.
6. In Union of India v. Raman Iron Foundry
[(1974) 2 SCC 231], a two judges Bench of the
Apex Court opined that based on a Government
contract, the Government had no right or
authority to appropriate the amounts of a
contractor from pending bills towards
satisfaction of its claim for damages without
independent adjudication by the adjudicating
authority. This decision was overruled by a
three judge bench decision of the Apex Court in
Kamaluddin Ansari and Co. v. Union of India RFA NO. 36 OF 2019
..6..
[(1983) 4 SCC 417]. The Apex Court is of the view
that though the Government can be injuncted from
recovering or appropriating the amount under the
bills of the contractor for the damages claimed,
it cannot be injuncted from withholding such
amount under the bills. In State of Gujarat
through Chief Secretary and Another v. Amber
Builders [(2020) 2 SCC 540], the views of the
three bench decision in Ansari's case has been
reiterated.
7. In the State, the Kerala Public Works
Department manual is followed as part of the
works awarded by the State Government and the
Public Works Department. Clause 2116.2.1
stipulates realisation of loss on account of
termination, which reads thus:
"Realisation of loss on account of termination.
An amount equal to 30% of the cost of the remaining works at agreed rates of the terminated contract shall be recovered from the defaulted contractor towards the risk and cost. The contractor shall be directed to remit the risk and cost RFA NO. 36 OF 2019
..7..
amount within three months. There is no need to wait till the work is arranged alternatively through another contractor and the total loss sustainable due to the default of the original contractor is assessed. Such loss, if any, shall be realised after completion of the work. If he fails to remit the amount within this periods following steps can be adopted for realisation of loss. The amount can be realised from the following.
EMD/Security Bill amount/retention if any due to the contract.
Any dues from department to the contractor Bank guarantee/Performance Guarantee of By filling civil suit against the contractor"
8. In the light of the above clause, PWD
can unilaterally determine the loss and retain
any amount due to the contractor under the bill
for the dues, though it cannot appropriate the
amount due calculated towards the loss. The
remedy, in such a situation, for a contractor is
to challenge the determination in an appropriate
manner. The authority of PWD to retain any amount
due under the bill cannot be questioned in the
light of the contract. However if the State or
the Department wants to recover any amount RFA NO. 36 OF 2019
..8..
towards loss in excess of the amount retained, it
has to file a suit or counter claim.
9. A problem may arise in a civil suit
filed by the contractor against the State or the
Department, where the latter would raise a claim
based on the loss calculated unilaterally by the
Department. At the Bar it was addressed that the
defendant-State or Department will have to raise
a plea of set-off or counterclaim and in the
absence of such plea of set-off or counterclaim,
such determination of loss cannot be considered
by the Civil Court. This is not a correct
position of law. Raising a plea of set-off or
counterclaim would arise only when a party has no
authority to decide upon the claim made by him.
If no challenge is made by the plaintiff, the
State or Department is entitled to retain it as
they have the authority under the contract to
retain the amount calculated unilateraly towards
the loss. The remedy in such a situation for the RFA NO. 36 OF 2019
..9..
aggrieved is to challenge such determination.
However, if the state or department wants to
recover any excess amount than the retained
amount towards the loss, they will have to raise
a plea of set-off or counter claim in such a
suit.
The legal position is as follows:
i) In a contract with the State or its
Department, if the contract allows the Department
to recover loss, the amount calculated towards
the loss cannot be directed to be paid without
there being a challenge against the determination
of loss.
ii) In a suit for recovery laid down by the
plaintiff/contractor, the State or Department
need not raise a plea of set-off or counterclaim
for any amount retained by them towards loss
based on the contract.
iii) if the state or department wants to
recover any amount over and above the retained RFA NO. 36 OF 2019
..10..
amount, they will have to file a separate suit or
will have to raise a plea of set-off or
counterclaim in a suit against them.
iv) In the absence of any contract, the
State or Department will have to raise a plea of
set-off or counterclaim in a suit filed by the
contractor.
10. The suit in this case was filed on
14.01.2013. The three points that arise for
consideration in this matter are:-
i). The calculation of the amount of
Rs.47,00,000/- as cost of unpaid work, as per
the agreement.
ii). The right of the plaintiff to recover
the cost of extra work not covered by the
agreement.
iii).The right of Authority or the State to
recover the loss.
Point No.i
The plaintiff appears to have relied on RFA NO. 36 OF 2019
..11..
Ext.B2 series measurement for calculating the
amount recovered. It is not discernible from the
impugned judgment as to how the trial Judge
arrived at the amount with reference to the
measurement referred to in Ext.B2 series. It is
the fundamental principle in adjudication that
disputed claims have to be substantiated on legal
evidence. The trial court could have directed the
plaintiff to file the calculation statement
detailing the measurements and amount claimed and
mark the same as an exhibit. This could have
given an opportunity to the defendants to object
to the calculation. The trial Judge completely
erred in framing the issue and assimilating the
evidence thereon to decide the issue. We are,
therefore, of the view that the calculation shall
be reworked after remand.
Point No.ii
Admittedly, the additional work has been
carried out in respect of the four branch canals. RFA NO. 36 OF 2019
..12..
The Government refused sanction for the
additional work. Nobody has a case that the
plaintiff has not done any additional work. The
additional work also has been recorded in Ext.B2
series. That means, the additional work was done
with the consent and knowledge of the Department.
This would probablise the case of the
plaintiff/contractor that the additional work was
done at the behest of the local MLA and as
instructed by PWD officials. Under Section 70 of
the Indian Contract Act, 1872, a person who
enjoys the benefits of non-gratuitous act is
bound to make compensation to the person from
whom such service is availed. Therefore, the
administrative sanction is an internal matter
between the Government and the Department. Thus,
the defendants are bound to pay for the
additional work done by the plaintiff. However,
we again see here that no calculation has been
made for the additional work carried out. RFA NO. 36 OF 2019
..13..
Therefore, for the purpose of calculation, the
matter has to be remanded back to the trial
court.
Point No.iii
The suit was filed on 14.01.2013. The written
statement was filed on 22.05.2013. In the written
statement, no specific plea has been raised on
the determination of loss and the recovery to be
effected from the plaintiff. It is seen from the
proof affidavit filed by PW1 that the plaintiff
was terminated from the contract by an order
dated 30.01.2013 at his risk and costs,
forfeiting the security deposit based on the
agreement. It is also seen that by an order dated
25.01.2014, the contractor was found liable to
pay Rs.54,98,879/-. The suit was disposed of only
on 24.11.2017. The plaintiff had no case that he
was not aware of the determination of loss. In
fact, pending suit, the plaintiff challenged the
determination of loss in a writ petition filed RFA NO. 36 OF 2019
..14..
before this Court in WP(C)No.10334/2015. This
Court did not interfere with the termination of
the contract. This Court, taking note of the
pendency of the civil suit, relegated the parties
to workout their remedy before the civil court.
This judgment has been marked as Ext.A17. The
learned counsel for the plaintiff/contractor
pointed out to the observation of this Court in
para 5, which reads thus:
"It is settled law that, if at all any loss has been resulted, it cannot be quantified and realised by one of the parties to the contract and the same has to be got adjudicated by appropriate Forum. This being the position, it is open for the respondents to take appropriate proceedings, in accordance with law, to get the alleged loss/ amount quantified . It is also open for them to file counter claim, if so advised, in the civil suit filed by the petitioner as O.S.67 of 2013 before the Sub Court, Ernakulam and to pursue the matter accordingly."
Therefore, the argument is that without a
plea of set-off or counterclaim, the State or the
Department cannot now raise a claim based on
loss. It is true that in intra-party cases, RFA NO. 36 OF 2019
..15..
certain observations have been made in regard to
the claim made by the Department. It is to be
noted that it was only an observation and no
issue has been adjudicated. The challenge itself
has been negatived in the writ petition with a
liberty to work out their remedy in civil court.
In such circumstances, the plaintiff ought to
have amended the prayer raising a challenge
against the termination and loss of demand. We
are of the view that an opportunity should be
given to the plaintiff to amend the prayer and
raise a challenge against the demand.
11. We, thus, allow this appeal, set aside
the impugned judgment and remand back the case to
trial court for considering the following issues:
i) On the calculation of the amount for the
unpaid work under the agreement.
ii) On the calculation of the amount payable
for the additional work not covered by the
agreement, and;
RFA NO. 36 OF 2019
..16..
iii) The above claim will depend upon the
challenge being made by the plaintiff as against
the decision on the termination and calculation
of loss.
The parties are directed to appear before the
trial court on 22.05.2023. The records are being
sent forthwith. The parties are also given
liberty to adduce fresh evidence. The trial court
shall dispose of the case before the court closes
for Onam holidays.
Sd/-
A.MUHAMED MUSTAQUE JUDGE
Sd/-
SHOBA ANNAMMA EAPEN JUDGE PR
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!