Citation : 2023 Latest Caselaw 1924 Ker
Judgement Date : 3 February, 2023
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE MOHAMMED NIAS C.P.
FRIDAY, THE 3RD DAY OF FEBRUARY 2023 / 14TH MAGHA, 1944
WP(C) NO. 7782 OF 2013
PETITIONERS:
1 KOTTAYAM DISTRICT CO-OPERATIVE BANK LTD.
DISTRICT CO-OPERATIVE BANK BUILDINGS,
KOTTAYAM 686001,
REPRESENTED BY ITS GENERTAL MANAGER
2 THE KOTTAYAM DISTRICT CO-OPERATIVE BANK EMPLOYEES
WELFATE FUND
REPRESENTED BY ITS SECRETARY,
KOTTAYAM DISTRICT CO-OPERATIVE BANK LTD,
HEAD OFFICE, DISTRICT CO-OPERATIVE BANK
BUILDINGS, KOTTAYAM 686001
BY ADVS.
N.ANAND
SRI.ATHUL SHAJI, SC, KOTTAYAM DISTRICT
CO.OPERATIVE BANK LTD.
ARUN CHANDRAN
RESPONDENT:
M.T.THOMAS
S/O THOMAS,MULAKAPPADAM HOUSE,
INDUSTRIAL NAGAR P.O
CHASNGANACHERRY 6
BY ADVS.
SRI.K.V.GEORGE
SRI.B.ASHOK SHENOY
SMT.C.G.PREETHA
SRI.P.N.RAJAGOPALAN NAIR
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR
ADMISSION ON 03.02.2023, THE COURT ON THE SAME DAY
DELIVERED THE FOLLOWING:
WP(C)No.7782 of 2013
2
MOHAMMED NIAS. C.P.,J
-----------
WP(C)No.7782 of 2013
- - - - - - - - - - - - - - - - - - ----
Dated this the 3rd day of February, 2023
JUDGMENT
The Kottayam District Co-operative Bank Ltd. and the Secretary
of the Kottayam District Co-operative Bank Employees Welfare Fund
have filed this writ petition challenging Ext.P10 order of the Kerala Co-
operative Tribunal, Thiruvananthapuram, allowing the appeal by
setting aside the order of the Arbitration Court, Thiruvananthapuram
in ARC 64 of 2006.
2. The relevant facts leading to the writ petition are as follows:-
The respondent herein had joined the service of the appellant Bank on
1.12.1967 and had retired from service as General manager on
30.11.2004 on superannuation and this Court by judgment dated
20.5.2005 in WP(C)No.27477 of 2004 had directed the Bank to pay him
the retiral benefits within two months on finding that he is entitled to
get the salary and other emoluments of General Manager. The
appellant was paid an amount of Rs.2,16,921/- on 9.11.2005 as the
amount entitled to him from the welfare fund. The respondent
contended that the payment was made only on 9..11.2005 though his WP(C)No.7782 of 2013
retirement was on 30.11.2004, and that he was eligible to get an
amount of Rs.2,42,948.17/- and accordingly, a sum of Rs.26,027/- more
is due under that Scheme. It was the further contention of the
petitioner that a sum of Rs.2657/- was recovered from the salary
arrears after his retirement as contribution towards the welfare fund
and adding 50% of the Banks' share, a further sum of Rs.3986/- was
due in addition to the above mentioned sum of Rs.26,027/- as the
balance amount after the payment on 9.11.2005. In short, the
respondents contended that as per the welfare fund scheme applicable
to him, the employee on superannuation is entitled to get his
contribution to the welfare fund scheme along with 50% of the
contribution of employer's contribution and compound interest thereon
at the rate of 11% per annum. It was the admitted case that an amount
of Rs.1,44,614.32/- was the accumulation in his welfare fund account as
his contribution and interest thereon as of 30.11.2004. It is also not
disputed that apart from the above, the employer was also entitled to
get a sum of Rs.72307.16/- as the employer's contribution, which was
50% of the employee's contribution and the interest thereon. Alleging
that there was delay in making the payment and claiming interest as
provided for under the scheme till the date of payment from the fund.
When the respondent had made the claim, the Co-operative Arbitration
Court, which considered the issue, found that the claim made for the WP(C)No.7782 of 2013
alleged delay between 1.12.2004 to 9.11.2005 was unsustainable,
possibly on the ground that the writ petition that directed the amounts
to be paid to the respondent was disposed only on 20.05.2005. Finding
that the bank did not make any delay after getting the copy of the
judgment and holding that there was no laches on the part of the Bank
in disbursing the retirement benefits, it found that the employee was
not entitled to claim interest. It was the said order of the Arbitration
Court that was challenged by the respondent herein before the
Tribunal.
3. The Tribunal allowed the appeal preferred by the employee
and found that he was entitled to an amount of Rs.26027/- as also
Rs.2000/- as costs to be paid to him within two months from the date of
the order and in case the amount was not paid within the said time, the
respondent was given the right to realise a sum of Rs .26027/- with
interest at the rate of 9% per annum from 9.10.2006 till realisation
apart from the sum of Rs.2000/- as costs from the respondent. This
order of the Tribunal is impugned by the Bank.
4. The learned counsel for the petitioner submits that the delay
occurred because the benefits were quantified and became payable
only after the final judgment was passed; therefore, the Bank had not WP(C)No.7782 of 2013
caused any delay. It is also argued that the interest could not be
claimed that there was no provision for the same.
5. The learned counsel for the respondent reiterated the
submissions made before the Tribunal and sought to sustain Ext.P10.
6. I have heard the learned counsel on both sides.
7. The Tribunal had found that the scheme of Rule 8(5) of the
District Co-operative Bank Employees Welfare Fund would show that
there was a direction for payment of compound interest at the rate of
11% per annum till the payment of the amount, which meant that the
employee was entitled to get interest on its contribution and the
employer's contribution together with compound interest as
stipulated above till the payment of the amount and that the
accumulation of the interest cannot be seen as stopped on
superannuation but only on payment being effected. It was also not
shown that the Bank had withdrawn the amount on 30.11.2004, the
date of retirement on superannuation of the employee, and therefore
no interest was earned on that amount after 30.11.2004. I find the
reason given by the Tribunal for granting interest as correct and legal
more so as there was no dispute either regarding the quantum of the
amount paid as appellant's contribution or the accumulation thereon as WP(C)No.7782 of 2013
interest or about the share of the Bank and the interest thereon as on
30.11.2004. As a necessary corollary, the time between 30.11.2004 and
the date on which the employee was actually paid the amounts, for
that period, the employee has to be compensated with interest as his
entitlement was crystallized as on 30.11.2004. I am not prepared to
accept the contention on behalf of the petitioners that they are not
responsible for the delay as the decision by this Court was only on
20.07.2005. It cannot be taken as a reason for not making the payment
on time. I do not find the conclusions or the directions issued by the
Tribunal to be faulty in any manner so as to interfere in this writ
petition.
The writ petition fails, and the same is accordingly dismissed.
Sd/-MOHAMMED NIAS C.P., JUDGE
dlk/9.2.2023 WP(C)No.7782 of 2013
APPENDIX OF WP(C) 7782/2013
PETITIONERs EXHIBITS EXHIBIT P1 TRUE COPY OF THE ORDER NO EM(1) 17602/2004 DATED 29-06-2004 ISSUED BY THE REGISTRAR OF CO- OPERATIVE SOCIETIES EXHIBIT P2 TRUE COPY OF THE ORDER IN WPC NO 27477/2004 DATED 22-09-2004 EXHIBIT P3 TRUE COPY OF THE JUDGMENT IN WPC NO 27477/2004 DATED 20-05-2005 EXHIBIT P4 TRUE COPY OF THE BYE- LAWS OF THE KOTTAYAM DISTRICT CO-OPERATIVE BANK EMPLOYEES WELFATE FUND EXHIBIT P5 TRUE COPY OF THE ORDER NO G.O (MS), NO 133/98/CO-OP DATED 24-08-1998 EXHIBIT P6 TRUE COPY OF THE A.R.C NO 64 OF 2006 FILED BEFORE THE CO-OPERATIVE ARBITRATION CORUT, THIRUVANANTHAPURAM EXHIBIT P7 TRUE COPY OF THE WRITTEN STATEMENT FILED IN A.R.C. NO 64 OF 2006 BEFORE THE CO-OPERATIVE ARBITRATION COURT EXHIBIT P8 TRUE COPY OF THE AWARD IN ARC NO 64/2006 DATED 30-12-2010 PASSED BY THE CO-OPERATIVE ARBITRATION COURT, THIRUVANANTHAPURAM EXIBIT P9 TRUE COPY OF THE MEMORANDUM OF APPEAL (A.P NO 16/2011) FILED BY THE RESPONDENT BEFORE THE KERALA CO- OPERAITVE TRIBUNAL, THIRUVANANTHAPRUAM EXHIBIT P10 TRUE COPY OF THE JUDGMENT IN JUDGMENT IN APPELA NO 16/2011 DATED 29-09-2012
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!