Citation : 2023 Latest Caselaw 8628 Ker
Judgement Date : 9 August, 2023
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE SATHISH NINAN
WEDNESDAY, THE 9TH DAY OF AUGUST 2023 / 18TH SRAVANA, 1945
RFA NO. 165 OF 2012
AGAINST THE JUDGMENT AND DECREE DATED 27.10.2011 IN OS 70/2010 OF
SUB COURT, PALA
-----
APPELLANT/PLAINTIFF:
RENJITH A.,
AGED 32 YEARS, CIVIL ENGINEER, S/O.ARAVINDAKSHAN NAIR,
PULIMOOTTIL HOUSE, ETTUMANOOR P.O., KIZHAKKUM BHAGAM KARA,
ETTUMANOOR VILLAGE, KOTTAYAM TALUK, PROPRIETOR,
"VASTHUKENDRA" BUILDING SOLUTIONS, KOLLAPPALLY P.O.,
KADANADU VILLAGE
BY ADVS.
SRI.SANTHEEP ANKARATH
SRI.SUMODH MADHAVAN NAIR
RESPONDENT/DEFENDANT:
P.P.PHILIP,
AGED 73 YEARS, S/O.PHILIPPOSE, POOVATHANIYIL HOUSE, KADANADU
P.O., KADANADU VILLAGE, MEENACHIL TALUK, PIN - 686653.
BY ADVS.
SRI.FIROZ K.ROBIN
SRI.J.JULIAN XAVIER
SRI.K.C.THOMAS PALA
THIS REGULAR FIRST APPEAL HAVING COME UP FOR HEARING ON 09.08.2023,
THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
SATHISH NINAN, J.
= = = = = = = = = = = = = = = = = =
R. F. A. No.165 of 2012
= = = = = = = = = = = = = = = = = =
Dated this the 9th day of August, 2023
J U D G M E N T
The plaintiff in a suit for money under a
construction contract, is the appellant. The defendant
raised a counter claim for recovery of excess amounts
paid. The trial court dismissed the suit and decreed the
counter claim.
2. On 26.07.2008, Ext.A1 construction contract was
entered into between the plaintiff (builder) and the
defendant (owner) for construction of a commercial
building for the defendant. As per Ext.A1, the cost of
construction is 775 per sq. ft. for the built-up area of
3856 sq. ft. The total amount for construction is
` 29,88,400/-. The amount was to be paid in various
stages as specified in Ext.A1. According to the
plaintiff, in the course of the construction work, the
defendant required execution of additional construction. R. F. A. No.165 of 2012
The additional construction thus carried out is 346.4
sq. ft. The same was neither endorsed on the agreement
nor a separate agreement executed. It was done by an
oral agreement. Though 97% of the works are completed,
the payments due have not been made. The plaintiff
claims that an amount of ` 1,38,400/- is outstanding in
terms of the original agreement and an amount of
` 4,83,860/- for the additional work. Thus, the suit is
filed for realisation of a total amount of ` 6,22,260/-
with interest.
3. The defendant though admitted the Ext.A1
agreement, contended that page 3 of Ext.A1 is fabricated
one. The said page contains the specifications with
regard to construction. The original of page 3 was
replaced with a fabricated one and produced before the
court. As per the agreement the work to be done includes
electrification, plumbing, flooring etc. The said works
were not done by the plaintiff. The construction carried
out by the plaintiff is not as per the specifications R. F. A. No.165 of 2012
contained in the agreement. The materials used and the
workmanship are of inferior quality. The claim of the
plaintiff that 97% of the construction is over was
denied and it was contended that only 60% of the work
has been completed. The defendant claimed that he has
paid an amount of approximately ` 9 lakhs in excess of
the actual amount due to the plaintiff. The defendant
raised a counter claim limiting the amount to ` 8 lakhs.
4. The plaintiff filed a written statement to the
counter claim denying the averments and the claim in the
written statement.
5. The trial court held that the construction
carried out by the plaintiff was not in accordance with
the specifications. It was held that the rate of ` 775/-
per sq.ft could not be for construction of the structure
alone. The Court adopted the PWD rate towards the cost
of construction of the structure, and held that the
total cost of construction is ` 16,18,925/-. Admittedly
the plaintiff was paid an amount of ` 28,50,000/-. R. F. A. No.165 of 2012
Accordingly, the counter claim was decreed for return of
` 8 lakhs as claimed by the defendant and the plaint
claim was dismissed.
6. I have heard Sri.Santheep Ankarath on behalf of
the appellant-plaintiff and Sri.J.Julian Xavier, the
learned counsel for the respondent-defendant.
7. According to the plaintiff, by the time disputes
arose between the parties, 97% of the construction was
completed. However, according to the defendant only 60%
of the work was completed. The state of the construction
obtaining at that time was reported by a Commissioner
with the assistance of an expert who were deputed in
another suit that was filed by the plaintiff as OS
228/2010, before the Munsiff's Court, Pala. That was a
suit filed by the plaintiff for prohibitory injunction
to restrain the defendant from entrusting the work to
others. Therein, the Commissioner originally filed a
report stating the value of construction at ` 16 lakhs
(approximately). The Commissioner's report was set aside R. F. A. No.165 of 2012
and the very same commission was reissued. Thereafter,
the Commissioner submitted a report, marked as Ext.A8 in
the present suit, wherein the cost of construction at
the rate as specified in Ext.A1 agreement was reported
as, ` 36,53,149/-.
8. The main dispute between the parties is, whether
the rate fixed in Ext.A1 agreement includes the
electrical, plumbing and other works, or is it only for
the structure. In Ext.A1 agreement, the rate fixed for
construction is ` 775/- per sq. ft. for the built-up
area. According to the defendant, the rate includes
expenses for electrification, plumbing, flooring etc.
According to the plaintiff, the rate is only for the
structure of the building to be completed in terms of
the specifications in the agreement and the plan. The
plans are marked as Exts.B1 and B2.
9. Clause 1 of Ext.A1 agreement provide that, the
work will be executed in accordance with the plan,
specification attached to the agreement and the rates R. F. A. No.165 of 2012
mutually agreed by the parties. The specifications were
contained at page 3 of Ext.A1. Going by page 3 in
Ext.A1, electrical, plumbing and wood work are not
included. The genuineness of page 3 of Ext.A1 is stoutly
disputed by the defendant, including his signature
therein. It is his case that the original of page 3 has
been replaced by the plaintiff with a fabricated one.
The trial court found that, in spite of the specific
denial, the plaintiff did not take any steps to prove
the genuineness of the disputed signature. Further, on a
perusal of the signatures, the court noticed the
differences at page 3 with the signatures at the other
pages. The court has observed the details of such
differences. On a perusal of page 3 of Ext.A1, it is
seen that the observations of the trial court with
regard to the signatures found at the disputed page are
justified. The trial court was right in having refused
to consider page 3 of Ext.A1.
R. F. A. No.165 of 2012
10. Though the genuineness of page 3 of Ext.A1
agreement is disputed, the defendant has not produced a
copy of the authentic Ext.A1 agreement. In the
replication filed by the plaintiff at paragraph 4, it is
contended that a copy of Ext.A1 was given to the
defendant. As DW1, the defendant would deny the same.
However, it is not probable that he would not have
retained even a copy of the agreement. Though in the
written statement the defendant contended that the
original page of Ext.A1 was replaced with a fabricated
one, as DW1, he would in cross-examination say that the
original did not contain the specification. His
deposition reads thus :-
"Exhibit A1 ð hm-Zn ]-d-ªn-«m-Wv H-¸n-«Xv. sI«n-S ]-Wn-bp- sS I-cmÀ BtWm F-óv a-\-Ên-em-¡nbm-tWm H-¸n«Xv (Q). AsX, hm-Zn ]-dª-Xv A-\p-k-cn-¨m-Wv H-¸n«Xv (A). H-¸n«¸w specification Dï-m-bn-cptóm (Q). Cñm-bn- cpóp. ]n-óo-Sv A-hÀ H-sc-®w Xóp. (A)"
Claiming to be the detailed specification with regard to
the construction as given by the plaintiff, the R. F. A. No.165 of 2012
defendant produced Ext.B3. According to the plaintiff,
Ext.B3 happened to be issued as claimed by the defendant
to enable availing of a loan from Bank. When PW1 is
cross-examined, a suggestion is made by the learned
counsel for the defendant with regard to availing of
loan from the Bank. That Ext.B3 was not prepared along
with Ext.A1 agreement and Exts.B1 and B2 plan is evident
for the reason, Ext.B3 contains provisions for
"handrails" for balcony whereas going by Exts.B1 and B2
plan what is provided for is "parapet". Therefore, the
case of the plaintiff that Ext.B3 does not reflect the
specifications agreed between the parties cannot be
brushed aside. Relying on Ext.B3, the trial court
concluded that the rate agreed to between the parties
under Ext.A1 agreement was for the works of the building
to be made in a 'ready to occupy' condition. Here it is
to be noticed that, at the undisputed pages of Ext.A1
agreement what is provided for is "for the construction
of structure of the building". At pages 1 and 2 it has R. F. A. No.165 of 2012
been repeatedly mentioned as "construction of structure"
of the building. At the opening part of the agreement it
is recited thus "Agreement entered into on this ... as
one part (..... the contractor) and ... as second part
(..... the owner) by entering into an agreement with the
following conditions for construction of structure of
the building for the owner ...". The terms mentioned at
clause 4, page 2 of Ext.A1 agreement reads thus: -
"Payments will be strictly in accordance with the stages mentioned below.
Total amount of construction of the Structure @ 775/- (Seven Hundred and Seventy Five Only) per square feet of the built up area i.e. 3856 x 775 = 29,88,400.00 a. Advance 10% of the total construction cost mutually agreed by both the parties i.e. Rs.2,98,840.00 b. 10% of the total amount after the completion of plinth level i.e. Rs.2,98,840.00 c. 20% of the total amount after the completion of ground floor columns i.e. Rs.5,97,680.00 d. 15% of the total amount after Floor Concrete i.e. Rs.4,48,260.00"
e. 15% of the total amount after the completion of first R. F. A. No.165 of 2012
floor columns i.e. Rs.4,48,260.00 f. 10% of the total amount after Roof Concrete i.e. Rs.2,98,840.00 g. 10% of the total amount after hollow blocks masonry i.e. Rs.2,98,840.00 h. 5% of the total amount after plastering i.e. Rs.1,49,420.00 i. 5% of the total amount after the completion i.e. Rs.1,49,420.00 j. Rate for the construction of structure of the commercial building as per the plan specification in this agreement is Rs.775/-"
11. Noticeably, at clause (4) what is stated is
total amount for construction of the "structure".
Clause-(j) provides the rate of construction of the
structure of the commercial building as per the plan
specification. Sub-clauses (a) to (i) in clause No.4
above refers to the stage-wise payments. The stages
mentioned are only "plinth level" "completion of ground
floor columns", "floor concrete", "completion of first
floor columns", "completion of roof concrete", "hollow R. F. A. No.165 of 2012
blocks", "masonry and plastering". The stage-wise
payment of the total amount as above does not make any
reference to electrical, plumbing, sanitary works etc.
There is nothing to indicate that other works like
sanitation, plumbing, electrical etc. are included in
the stages mentioned therein. Therefore, the disputed
document Ext.B3, alone cannot made the basis to find
that the rate mentioned in Ext.A1 agreement included the
cost of electrical, sanitary and other works. On the
other hand, pages 1 and 2 of Ext.A1 which are
undisputed, suggest that the rate agreed is only for the
structure of the building.
12. Deliberating on the rate of construction, the
trial court has proceeded observing that "nobody will
agree to construct structures at the rate of ` 775/- per
sq.ft." There was no material before the Court, oral or
documentary, to arrive at the said conclusion. There was
no plea for the defendant that the rate, ` 775/- per
sq.ft. for construction of the structure was an R. F. A. No.165 of 2012
exorbitant rate which was not prevalent at that time. No
evidence was adduced by the defendant that such rate for
structure was exorbitant during that period. If the rate
was so excessive, then evidence regarding the same could
have been adduced. It is pertinent to note that, even
when the expert was examined as PW3 or when the Advocate
Commissioner was examined as CW1, not even a suggestion
is made to them that the rate of ` 775/- per sq. ft. for
structure alone is an exorbitant rate and that under
normal circumstances a contract would not be entered
into at that rate for the construction of structural
works alone. In the absence of any such evidence, the
conclusions arrived at by the trial court that, the rate
agreed to between the parties was inclusive of all works
to make the building in a ready to occupy condition,
including electrical, sanitary and other works, cannot
be sustained.
13. Thus, I find that the rate of ` 775/- per sq.
ft. agreed to in Ext.A1 is only for construction of the R. F. A. No.165 of 2012
structure, for a built-up area of 3856 sq. ft.
14. Though the plaintiff would allege that the
construction carried out by the defendant was using low
quality materials and that the foundation does not
conform to the required specifications, such aspects
were not ascertained by the defendant through the expert
Commissioner. He having not been asked to report
regarding the same, it could only be found that the said
allegations have no substance. There is no claim for
damages alleging that the defendant had to do any extra
work to make the committed work in accordance with the
standards.
15. It is the case of the defendant that the
extra/additional works were done by the plaintiff on an
agreement that it will be in lieu of the cost of the
wood work which had to be replaced at the cost of the
defendant since the work done by the plaintiff was found
to be of inferior quality. However, but for such a
contention to be subsist there is no evidence regarding R. F. A. No.165 of 2012
the same. Hence such contention is only to be negatived.
The plaintiff is thus entitled to the value of
extra/additional works also.
16. The stage up to which the plaintiff carried out
construction is evident from Ext.A8 the Commissioner's
Report prepared in OS 228/2010. The Commissioner was
examined as CW1 and the expert who accompanied the
Commissioner was examined as PW3. There is no dispute
with regard to the stage of construction as reported
therein. The value/cost of such construction based on
the rate as agreed in Ext.A1 viz. ` 775/- per sq.ft.,
has been reported to be ` 36,53,149/-. The value of such
construction at the PWD rate has been assessed and
reported by the very same Commissioner and expert, who
were deputed in the present case, through Ext.C1 and
C1(a) as ` 16,18,925/-. Incidentally it is also to be
noted that, though the difference is ` 20,34,224/-, and
even the defendant does not have a case that he has paid
so much excess amount. According to him the excess R. F. A. No.165 of 2012
payment made is only ` 9 lakhs (approximately).
17. Having found that the agreed rate for
construction is ` 775/- per sq. ft., the plaintiff is
entitled to get ` 36,53,149/- towards the work carried
out by him. It is not in dispute that only an amount of
` 28,50,000/- was paid to him. Therefore, he is entitled
for the balance amount of ` 6,22,260/-. The claim of the
defendant that he has paid amounts in excess of that due
to the plaintiff, is thus incorrect. The finding of the
trial court to the contrary is thus liable to be
interfered with and I do so.
18. With regard to the entitlement of interest,
considering the conduct of the plaintiff in having
tampered with page 3 of Ext.A1 agreement, I deem it
appropriate to decline interest till the date of decree
and also the costs. From the date of decree the
plaintiff shall be entitled for interest at the rate of
6% per annum.
R. F. A. No.165 of 2012
Resultantly, the appeal is allowed. The decree and
judgment of the trial court are set aside. The suit is
decreed allowing the plaintiff to realise an amount of
` 6,22,260/- with interest at the rate of 6% per annum
from the date of decree till realisation, from the
defendant and his assets. Costs disallowed.
Sd/-
SATHISH NINAN JUDGE
kns/-
//True Copy// P.S. to Judge
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!