Citation : 2022 Latest Caselaw 2684 Ker
Judgement Date : 11 March, 2022
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
FRIDAY, THE 11TH DAY OF MARCH 2022 / 20TH PHALGUNA, 1943
WP(C) NO. 28122 OF 2021
PETITIONER:
M/S THERUVATH BUILDERS
REPRESENTED BY ITS EXECUTIVE PARTNER, THERUVATH
BUILDING, UZHAVOOR POST-686634, KOTTAYAM
DISTRICT.
BY ADVS.
P.K.VIJAYAMOHANAN
AISWARYA V.S.
RESPONDENTS:
1 THE PROJECT DIRECTOR
PROJECT MANAGEMENT UNIT, KERALA ROAD FUND BOARD,
SREEBALA BUILDING, NANTHANCODE, KAWDIAR,
THIRUVANANTHAPURAM-695003.
2 THE CHIEF EXECUTIVE OFFICER
KIIFB, STATUE JUNCTION, THIRUVANANTHAPURAM-
695001.
BY ADVS.
S.CHANDRASEKHARAN NAIR
S.GOKUL BABU
RAJU GEORGE (KARUVATTA)
BALAMURALI K.P.
JEREES J.
AMALA.J.RAJ
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
11.03.2022, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
W.P.(C).No.28122 of 2021
2
JUDGMENT
Dated this the 11th day of March, 2022
The petitioner states that they undertook the work of
"Project under KIIFB 2016-17-Improvements to Changanassery
- Kaviyoor Road 0/000 to 13/300 in Pathanamthitta District."
Ext.P1 is the letter of acceptance dated 01.10.2018. The work
had to be completed within two years.
2. The petitioner submits that the contractors of Water
Authority took over the Site where the petitioner was
proceeding with the contract. Therefore, he could not complete
the work within the two year stipulated period. It is the specific
case of the petitioner that more than 90% of the work is
completed and the balance work remained to be completed for
the sole reason that the contractors of Water Authority took over
the site.
3. Learned counsel for the petitioner submitted that
there is a fundamental breach of contact as contemplated by W.P.(C).No.28122 of 2021
Ext.P2- Extract of General Conditions. As per Clause 54.1 of
Ext.P2, the Employer or the Contractor can terminate the
Contract if the other party causes a fundamental breach of the
contract. As per Clause 54.2, if an engineer instructs the
contractor to delay the progress of the work and the instruction
is not withdrawn within 28 days, the same would amount to
fundamental breach. The petitioner submits that the petitioner
was orally required to stop the work and even after 28 days
period, no further instruction was given and therefore, there is a
fundamental breach of contract. The learned counsel for the
petitioner submits that in such circumstances, the contract is
liable to be foreclosed without imposing any risk and cost on the
petitioner.
4. The learned Standing Counsel appearing for
respondents 1 and 2 controverted the contentions of the
petitioner made in the writ petition. According to the learned
Standing Counsel for the 1st respondent, the breach of contract
is committed by the petitioner and not by the respondents. W.P.(C).No.28122 of 2021
Going by the facts of the case, the respondents are entitled to
terminate the contract with the petitioner at their risk and cost,
contended the Standing Counsel for the respondents 1 and 2.
5. I have heard the learned counsel for the petitioner
and the respective Standing Counsel appearing for
respondents 1 and 2.
6. The petitioner states that they have completed 90%
of work. The respondents have disputed the said fact. This is a
question of fact which cannot be gone into by this Court. Going
by the pleadings, it is seen that the petitioner has preferred
Ext.P10 representation before the 1st respondent. To meet the
ends of justice, it will be sufficient that the 1st respondent is
directed to consider Ext.P10 representation submitted by the
petitioner in accordance with law.
Therefore, the writ petition is disposed of directing the 1 st
respondent to consider the grievance of the petitioner as
contained in Ext.P10 representation and take a decision
thereon within a period of one month after granting an W.P.(C).No.28122 of 2021
opportunity of hearing to the petitioner. It is made clear that this
Court has not passed any orders on merits, of the claim by the
petitioner.
Sd/-
N.NAGARESH,
JUDGE rpk W.P.(C).No.28122 of 2021
APPENDIX OF WP(C) 28122/2021
PETITIONER EXHIBITS Exhibit P1 THE TRUE COPY OF THE LETTER OF ACCEPTANCE DATED 01.10.2018 ISSUED BY THE 1ST RESPONDENT TO THE PETITIONER.
Exhibit P2 THE TRUE EXTRACT OF CLAUSES 50 TO 55 OF THE GENERAL CONDITIONS OF THE TENDER. Exhibit P3 THE TRUE COPY OF THE COMMUNICATION DATED 04.02.2020 OF THE PETITIONER TO THE 1ST RESPONDENT.
Exhibit P4 THE TRUE COPY OF THE COMMUNICATION DATED 08.05.2020 OF THE PETITIONER TO THE 1ST RESPONDENT.
Exhibit P5 THE TRUE COPY OF THE MINUTES OF THE MEETING DATED 14.09.2021.
Exhibit P6 THE TRUE COPY OF THE COMMUNICATION DATED 24.02.2021 OF THE PETITIONER TO THE 2ND RESPONDENT.
Exhibit P7 THE TRUE COPY OF THE LETTER NO.PWD004-62-
TIW-PIP-01 DATED 13.07.2021 OF KIIFB TO THE 1ST RESPONDENT.
Exhibit P8 THE TRUE COPY OF THE LETTER NO.KRFB-/PTA/KTM/AE1-19/2021 DATED 03.11.2021 OF THE 1ST RESPONDENT TO THE PETITIONER.
Exhibit P9 THE TRUE COPY OF THE LETTER DATED 11.11.2021 OF THE PETITIONER TO THE 1ST RESPONDENT.
Exhibit P10 THE TRUE COPY OF THE LETTER NO.17/TB/CKROAD/2019 DATED 18.11.2021 OF THE PETITIONER TO THE 1ST RESPONDENT. W.P.(C).No.28122 of 2021
RESPONDENTS' EXHIBITS Exhibit R2(A) THE TRUE COPY OF THE PROCEEDINGS ORDER NO.APR-1/144/2017/KIIFB DATED 18.09.2017
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!