Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

T.A.Xavier vs Ottapalam Municipality
2022 Latest Caselaw 7657 Ker

Citation : 2022 Latest Caselaw 7657 Ker
Judgement Date : 28 June, 2022

Kerala High Court
T.A.Xavier vs Ottapalam Municipality on 28 June, 2022
        IN THE HIGH COURT OF KERALA AT ERNAKULAM
                        PRESENT
          THE HONOURABLE MR.JUSTICE N.NAGARESH
 TUESDAY, THE 28TH DAY OF JUNE 2022 / 7TH ASHADHA, 1944
                 WP(C) NO. 6117 OF 2021
PETITIONER:

         T.A.XAVIER,
         AGED 73 YEARS
         S/O. AUGUSTINE, CONTRACTOR,
         M/S. T.A.XAVIER AND SONS,
         THAREPARAMBIL HOUSE, PALLURUTHY P.O.,
         KOCHI-682 006

         BY ADVS.
         BABU JOSEPH KURUVATHAZHA
         SRI.M.G.SREEJITH


RESPONDENTS:

    1    OTTAPALAM MUNICIPALITY
         OTTAPPALAM P.O.,
         PALAKKAD DISTRICT,PIN-679 101,
         REPRESENTED BY ITS SECRETARY

    2    OTTAPPALAM MUNICIPAL COUNCIL,
         OFFICE OF THE OTTAPPALAM MUNICIPALITY,
         OTTAPPALAM P.O.,
         PALAKKAD DISTRICT,PIN-679 101,
         REPRESENTED BY ITS CHAIRPERSON

    3    MUNICIPAL ENGINEER,
         OTTAPPALAM MUNICIPALITY, OTTAPPALAM P.O.,
         PALAKKAD DISTRICT,PIN-679 101

    4    SUPERINTENDING ENGINEER,
         GREATER COCHIN DEVELOPMENT AUTHORITY (GCDA),
         KADAVANTHRA, ERNAKULAM, KOCHI-682 020
 W.P.(C) No.6117/2021
                             :2:


           BY ADVS.
           SRI.P.P.THAJUDEEN, SC, OTTAPALAM MUNICIPALITY
           SRI.VIPIN VARGHESE
           SHRI.SREESANKAR.M
           M.V.BOSE
           VINOD MADHAVAN
           P.M.MAZNA MANSOOR

     THIS WRIT PETITION (CIVIL) HAVING COME UP         FOR
ADMISSION ON 28.06.2022, THE COURT ON THE SAME         DAY
DELIVERED THE FOLLOWING:
 W.P.(C) No.6117/2021
                                       :3:




                           N. NAGARESH, J.

          `````````````````````````````````````````````````````````````
                       W.P.(C) No.6117 of 2021

          `````````````````````````````````````````````````````````````
                Dated this the 28th day of June, 2022

                            JUDGMENT

~~~~~~~~~

The petitioner, who is a Contractor by profession,

has approached this Court seeking to command respondents

1 to 3 to sanction and disburse the entire amount of

₹49,62,247/-, the subject matter of Exts.P4 and P4(a). The

petitioner further seeks to command respondents 1 to 3 to

get revised technical sanction from the 4 th respondent for the

23 items of work for which payment has been deferred as

detailed in Ext.P4(a).

2. The petitioner states that the construction work of

Municipal Bus Stand / Shopping Complex of Ottapalam

Municipality was given to the petitioner. The petitioner

satisfactorily completed the work by 08.10.2018. The W.P.(C) No.6117/2021

petitioner states that as per the tender conditions, the 1 st

respondent had to sanction and disburse 75% of the

payment in advance. The estimated PAC of the work was

₹19,97,59,931/-. The 4 th respondent subsequently revised

the technical sanction as per Ext.P2(a) for the value of

₹19,77,59,931/-.

3. After completion of the work, measurements were

taken and the total bill amount was computed as

₹19,78,23,898/-. There was a difference of ₹63,967/- in

comparison to the amount of ₹19,77,59,931/- for which

technical sanction was accorded.

4. The petitioner states that the total value of 11 th

part and final bill was ₹49,62,247/-. In the final bill, 23 works

had exceeded its quantity. However, there was no change in

the fixed rate for the 23 items of work. The respondents can

very well sanction the amount for those 23 items along with

the final bill, without awaiting technical sanction of the 4 th

respondent, contends the petitioner. However, against the

amount of ₹49,62,247/-, approval was given for disbursing W.P.(C) No.6117/2021

only ₹9,03,066/-. The payment of ₹40,59,181/- was deferred

by respondents 1 to 3. Along with 6% service tax, the

amount due to the petitioner under the 11 th part and final bill

would be ₹43,02,732/-.

5. The petitioner submitted Ext.P5 representation on

12.12.2019 requesting to sanction the payment for those 23

works. Ext.P7 is the last representation submitted by the

petitioner on 27.11.2020. The respondents have not cared

to settle the bills of the petitioner so far, contends the

petitioner.

6. The 1st respondent-Municipality filed a statement

dated 14.06.2022. The 1st respondent submitted that the

Municipality has prepared the revised estimate and

submitted before the GCDA for technical sanction in

compliance with all procedural formalities. Technical sanction

is not obtained till date. The Municipality can allow the final

bill only in compliance of legal formalities which mandate

technical sanction for the revised estimate for the work

carried out in variation to the sanctioned estimate. W.P.(C) No.6117/2021

7. The petitioner is an experienced contractor and he

has executed the work and is well aware that payment for the

extra work in variance with the sanctioned estimate can be

given only after obtaining technical sanction. The petitioner is

aware that the procedure for obtaining the technical sanction

is time consuming. The Municipality has not done anything

against the interest of the petitioner. The Municipality has

taken all steps for obtaining the technical sanction.

8. The technical sanction for revised estimate is

expected soon and steps for allowing the final bill will be

taken immediately thereafter. Ext.P9 relied on by the

petitioner is not applicable to the facts of this case. The

petitioner is not entitled for the order in Ext.P8 as the issue in

both the cases is not identical, contended the 1st respondent.

9. The Standing Counsel entered appearance on

behalf of the 4th respondent. On behalf of the 4 th respondent,

it was submitted that the Superintending Engineer of the

GCDA is on leave for a period of three months and the issue

of giving technical sanction to the revised bill, can be W.P.(C) No.6117/2021

resolved only after a period of three months. According to

the Standing Counsel, there is no person competent in the

GCDA to give approval to the revised estimate.

10. I have heard the learned counsel for the petitioner

and the respective learned Standing Counsel representing

respondents 1 to 3 and the 4th respondent.

11. The petitioner has undertaken the work of

construction of Municipal Bus Stand / Shopping Complex for

Ottapalam Municipality. This was in the year 2016. The

petitioner completed the work to the satisfaction of

respondents 1 to 3. During the construction, the petitioner

had to execute 23 works which had exceeded its quantity.

These works were not extra works, but only exceeded works.

In fact, a supplementary agreement was executed as is

evident from Ext.P4(a), in respect of these works.

12. There is no dispute that the work entrusted to the

petitioner by respondents 1 to 3, was carried out by the

petitioner to the satisfaction of respondents 1 to 3.

Respondents 1 to 3 are not seriously disputing the eligibility W.P.(C) No.6117/2021

of the petitioner to receive payments for the 23 exceeded

works. The difficulty expressed by respondents 1 to 3, is in

getting revised technical sanction for the afore works from

the 4th respondent.

13. On behalf of the 4th respondent, the Standing

Counsel would submit that revised estimate cannot be

sanctioned since the Superintending Engineer is on leave for

three months. In this regard, it is to be noted that it is the

specific case that he is entitled to 75% of the amount in

advance, as per the terms of the contract. The petitioner

also states that he has availed advances from various

sources for completing the work and the delay in payment

would cause undue hardship and loss to the petitioner.

14. This Court finds that the reason advanced by the

4th respondent for not approving the revised estimate, cannot

be a reason to delay the payments due to the petitioner. The

work undertaken by the petitioner was completed as early on

08.10.2018. When there is no complaint against the work of

the petitioner, the amount due to the petitioner has to be paid W.P.(C) No.6117/2021

immediately. The fact that the Superintending Engineer,

GCDA, is on long leave, cannot be a reason to delay

payments to the petitioner.

In the facts and circumstances stated above, the

writ petition is disposed of directing the 4 th respondent and

the Greater Cochin Development Authority to consider grant

of approval for the revised estimates for advice forwarded by

respondents 1 to 3 and take a decision thereon within a

period of six weeks. Respondents 1 to 3 are directed to pay

the amount found due to the petitioner within a further period

of two weeks.

Sd/-

N. NAGARESH, JUDGE aks/30.06.2022 W.P.(C) No.6117/2021

APPENDIX OF WP(C) 6117/2021

PETITIONER'S EXHIBITS

EXHIBIT P1 TRUE COPY OF THE AGREEMENT NO.35/11-12 DATED 5.3.2012 EXECUTED BETWEEN THE 1ST RESPONDENT AND PETITIONER EXHIBIT P1A TRUE COPY OF THE TENDER DOCUMENT PUBLISHED BY THE 1ST RESPONDENT, INCLUDING FORM NO.83 OF THE TENDER DATE 4.10.2008 EXHIBIT P2 TRUE COPY OF THE MINUTES OF THE MEETING HELD ON 24.2.2016., CHAIRED BY THE HON'BLE MINISTER FOR LSGD PERTAINING TO THE AUTHORITY TO ISSUE THE TECHNICAL SANCTION EXHIBIT P2A TRUE COPY OF THE REVISED TECHNICAL SANCTION DATED 13.6.2016 ISSUED BY THE 4TH RESPONDENT, FOR THE VALUE OF RS.19,77,59,931/-

EXHIBIT P3 TRUE COPY OF THE LETTER DATED 27.4.2016 ISSUED BY THE GOVERNMENT TO THE VARIOUS MUNICIPAL SECRETARY/ CHAIRMAN, PERTAINING TO THE SANCTIONING OF THE RATES EXHIBIT P4 TRUE COPY OF THE RELEVANT PAGES OF THE 11TH PART AND FINAL BILL OF THE WORK, EXHIBIT P4A TRUE COPY OF THE DETAILS OF 23 ITEMS OF WORK, WHEE VARIATIONS WERE OCCURRED FROM THE ORIGINALLY ACCEPTED SUPPLEMENTARY AGREEMENT SCHEDULE OF WORK EXHIBIT P5 TRUE COPY OF THE REPRESENTATION DATED 13.12.2019 SUBMITTED BY THE PETITIONER BEFORE THE RESPONDENTS 1 T0 3 EXHIBIT P6 TRUE COPY OF THE RESOLUTION NO.8 DATED 14.5.2020 TAKEN BY THE 2ND RESPONDENT EXHIBIT P7 TRUE COPY OF THE REPRESENTATION DATED 27.11.2020 SUBMITTED BY THE PETITIONER BEFORE THE RESPONDENTS 1 AND 2 Exhibit P8 TRUE COPY OF THE ORDER DATED 05/07/2021 IN W.P(C) 12896/2021 W.P.(C) No.6117/2021

Exhibit P9 TRUE COPY OF THE RELEVANT PORTION OF STANDARD BID DOCUMENT FOR E-TRAINING, PERTAINING TO CLAUSE 39.6, PUBLISHED BY THE PUBLIC WORKS DEPARTMENT UNDER THE GOVERNMENT OF KERALA, AS PER G.O(P) 3/2017/PWD DATED 09/08/2017

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter