Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Devchand Construction vs Union Of India
2022 Latest Caselaw 1707 Ker

Citation : 2022 Latest Caselaw 1707 Ker
Judgement Date : 16 February, 2022

Kerala High Court
M/S. Devchand Construction vs Union Of India on 16 February, 2022
             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                             PRESENT
        THE HONOURABLE MR. JUSTICE P.B.SURESH KUMAR
                                &
              THE HONOURABLE MRS. JUSTICE C.S. SUDHA
WEDNESDAY, THE 16TH DAY OF FEBRUARY 2022 / 27TH MAGHA, 1943
                       ARB.A NO. 29 OF 2018
AGAINST THE ORDER/JUDGMENT IN OP(ARB.) 105/2015 OF DISTRICT
                         COURT, KASARAGOD
APPELLANT/S:

         M/S. DEVCHAND CONSTRUCTION,
         THOKKOTTU-PERUMANNUR POST, MANGALORE - 575017,
         REPRESENTED BY ITS PROPRIETOR, MR.DINAKAR ULLAL.

         BY ADVS.
         SMT.SANTHA VARGHESE
         SRI.RANJITH VARGHESE
         SRI.RAHUL VARGHESE



RESPONDENT/S:

         UNION OF INDIA,
         REPRESENTED BY THE DEPUTY CHIEF ENGINEER
         (CONSTRUCTION), SOUTHERN RAILWAY, KANNUR-670001.

         BY ADV SRI.S.ANANTHAKRISHNAN, SC, RAILWAYS




     THIS ARBITRATION APPEALS HAVING COME UP FOR ADMISSION
ON 16.02.2022, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
 Arb. Appeal No.29 of 2018

                                      -2-




                                                                     "C.R."
                P.B. SURESH KUMAR & C.S. SUDHA, JJ.
                   -----------------------------------------------
                         Arb. Appeal No.29 of 2018
                   -----------------------------------------------
                 Dated this the 16th day of February, 2022

                                 JUDGMENT

C.S.Sudha, J.

This appeal filed under Section 37 of the Arbitration and Conciliation

Act, 1996 (the Act), is against the order dated 04.12.2017 in O.P.(Arb.)

No.105/2015 of the District Court, Kasaragod.

2. The appellant herein is the petitioner before the court below and

the claimant before the Arbitral Tribunal (AT). The respondent herein is the

respondent before the court below and the respondent before the AT. The

parties in this appeal will be referred to as described in the arbitral

proceedings.

3. The respondent awarded the work of 'doubling of track between

Shornur and Mangalore, Cannanore-Uppala section: collection and stacking

of 50mm size machine crushed hard stone ballast alongside the

alignment/station yards/ on top of the new formation between Kottikulam Arb. Appeal No.29 of 2018

and Kasaragod stations (Balance works)' to the claimant on 19.09.2000 for a

value of ₹ 1,19,39,274/-. Letter of Acceptance (LoA) was issued on

19.09.2000. The work was to be completed within a period of nine months,

that is, by 18.06.2001. Alleging breach on the part of the claimant, the

contract was terminated by the respondent before the expiry of the

completion period. Disputes arose between the parties. Arbitration

proceedings was initiated. The AT consisting of three Arbitrators passed an

award on 24.04.2015. The AT disallowed all the claims of the claimant

except claim no. 1 for release of an amount of ₹ 3,46,959/-, which amount

had been forfeited by the respondent towards risk liability amount. This

claim was partly allowed to the tune of ₹ 46,959/-. All the other claims

including the prayer for return of the Earnest Money Deposit (EMD) was

rejected. Aggrieved, the claimant/contractor took up the matter before the

District Court. The said Original Application filed under s.34 of the Act was

dismissed by the impugned order.

4. Heard Shri.Rahul Varghese, the learned counsel for the

appellant and Shri.Ananthakrishnan, the learned Standing Counsel for the

Railways.

5. In the appeal memorandum it is stated that during the pendency Arb. Appeal No.29 of 2018

of the proceeding before the court below, the respondent released the EMD

amounting to ₹50,000/-. This according to the claimant has been done when

the respondent realized that it was illegal for them to have withheld the

same, especially when they had not suffered any loss or damage. Therefore,

the only point to be decided in this appeal is whether there is any infirmity in

the finding of the AT that the respondent is entitled to forfeit the security

deposit of ₹ 3 lakhs towards risk liability in the absence of any loss or

damage. According to the AT, the claimant had failed to execute the work

and hence the contract had been terminated at his risk and cost in terms of

Clause 62 of the General Conditions of Contract. An amount of ₹ 3 lakhs

deposited as security deposit and an amount of ₹ 46,959/- towards

advertisement charges had been deducted by the respondent from the final

bill as the amount towards risk liability. The AT concluded that since the

breach of the contract had been committed by the claimant/contractor, the

security deposit of ₹ 3 lakhs is liable to be forfeited and therefore out of the

total amount of ₹3,46,959/- claimed by the claimant, only an amount of ₹

46,959/- was allowed. However, in the award itself it is stated that no

loss/damage had been caused to the respondent. Therefore, it is submitted

by the learned counsel for the claimant/contractor that in such circumstances Arb. Appeal No.29 of 2018

the forfeiture of ₹3 lakhs deposited as security deposit is patently wrong,

illegal and perverse. Reference was made to the decisions in Fateh Chand

vs. Balkishan Dass [1963 SC 1405]; State of Kerala vs. United Shippers

and Dredgers Ltd. [AIR 1982 Ker 281]; Abdulla vs. State of Kerala

[2001 KHC 822] and Kailash Nath Associates vs. Delhi Development

Authority [(2015)4 SCC 136] in support of this argument.

6. Here we need to refer to Sections 73 and 74 of the Indian

Contract Act, 1872. Section 74 of reads thus -

"74 Compensation for breach of contract where penalty stipulated for:-[When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for."

7. As laid down in the aforesaid decisions, in a case coming under

Section 74, it is not necessary for the party claiming compensation under

this Section to prove that actual damage or loss has been caused. Then the

question is whether even in the absence of legal injury, compensation is

liable to be paid for breach simplicitor. Under Section 74, whether it is a Arb. Appeal No.29 of 2018

case of liquidated damages or penalty, what the party faced with the breach

gets is only reasonable compensation, subject to the limit of the amount

stipulated in the contract itself. Section 74 dispenses with proof of the extent

of real or actual or factual loss or damage, but provides for grant of

reasonable compensation, subject to the condition that it shall not exceed the

sum stipulated as penalty in the contract. The proof of the extent of loss or

damage suffered in fact, i.e., proof of the extent of actual damage or loss

suffered is dispensed with in Section 74. This would not mean that there

need not be any loss or damage. What is meant is only that proof of actual

damage or loss is not necessary.

8. In the case on hand, it cannot be Section 74 that could have

been invoked, because the Award does not say that any sum has been named

in the contract as the amount to be paid in case of breach. In other words,

the parties had never made a genuine pre-estimate of the amount to be paid

in the event of any damage or loss likely to be caused by the breach or that

there is any clause relating to liquidated damages in the contract.

9. Section 73 reads-

"When a contract has been broken, the party who suffers by such breach is entitled to receive, from the party who has broken the Arb. Appeal No.29 of 2018

contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from such breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it. Such compensation is not to be given for any remote and indirect loss or damage sustained by reason of the breach."

10. The words 'loss or damage' in the aforesaid sections would

necessarily indicate that the party who complains of breach must have really

suffered some loss or damage apart from being faced with the mere act of

breach of contract. That is because every breach of every contract need not

necessarily result in actual loss or damage. Compensation payable under

Section 73, 74 as also under Section 75 is only for loss or damage caused by

the breach and not account of the mere act of breach. If in any case the

breach has not resulted in or caused any loss or damage to a party, he cannot

claim compensation.

11. Further, in Union of India v. Rampur Distillery and

Chemical Co. Ltd. (AIR 1973 SC 1098) the Apex Court held that a party

to a contract taking security deposit from the other party to ensure due

performance of the contract, is not entitled to forfeit the deposit on ground of

default when no loss is caused to him in consequence of such default. When

the question is one of forfeiture of security deposit in case of breach of Arb. Appeal No.29 of 2018

contract, such sum does not ipso facto go to the respondents. If the party

complaining is in a position to adduce evidence whereby the court can assess

reasonable compensation, then without proof of actual loss, damages will

not be awarded and amount mentioned by the contract will be penalty. In

such circumstances, it has been held that the security amount is liable to be

forfeited.

12. As noticed earlier, the Award in this case clearly says that no

loss or damage has been caused to the respondent. That being the position,

neither the provisions of Sections 73, 74 or 75 could have been invoked nor

are they applicable in this case. That being the position, the AT was certainly

wrong in rejecting the claim of the claimant for release of the amount of

security deposit of ₹ 3 lakhs. This finding in violation of the provisions of

Sections 73 to 75 of the Contract Act, is certainly in contravention of the

fundamental policy of Indian Law as contemplated in Section 34(2)(b)(ii) of

the Act.

In the result, the appeal is allowed. The impugned order dated

4.12.2017 in O.P.(Arb.) No.105/2015 is set aside. The Award to the extent it

disallows Claim No.1 for the release of security deposit of ₹ 3 lakhs towards

risk liability amount, is set aside and the said claim shall stand allowed. The Arb. Appeal No.29 of 2018

amount has been withheld without any justification and therefore the amount

of ₹ 3 lakhs will be returned by the respondent to the claimant with interest

@ 6% p.a. from the date of moving the claim before the AT till realisation

and costs.

sd/-

P.B.SURESH KUMAR, JUDGE.

sd/-

C.S.SUDHA, JUDGE.

STK

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter