Citation : 2022 Latest Caselaw 1578 Ker
Judgement Date : 15 February, 2022
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
TUESDAY, THE 15TH DAY OF FEBRUARY 2022 / 26TH MAGHA, 1943
WP(C) NO. 25425 OF 2021
PETITIONER:
M/s.CHICAGO CONSTRUCTIONS INTERNATIONAL PRIVATE
LIMITED,
HAVING ITS REGISTERED OFFICE AT TC 22/2703,
CHITHIRA LANE, KOCHAR ROAD, SASTHAMANGALAM,
THIRUVANANTHAPURAM-695010,
REPRESENTED BY ITS MANAGING DIRECTOR
SRI. S.MOHANA KUMAR.
BY ADVS.
N.KRISHNA PRASAD
DEEPAK VARUGHESE MATHEW
RESPONDENTS:
1 KERALA WATER AUTHORITY,
REPRESENTED BY ITS MANAGING DIRECTOR,
JALA BHAVAN, VELLAYAMBALAM,
THIRUVANANTHAPURAM-695033.
2 THE MANAGING DIRECTOR,
KERALA WATER AUTHORITY
JALA BHAVAN, VELLAYAMBALAM,
THIRUVANANTHAPURAM-695033.
3 THE SUPERINTENDING ENGINEER,
KERALA WATER AUTHORITY
P.H.CIRCLE, THRISSUR-680001.
4 THE EXECUTIVE ENGINEER,
KERALA WATER AUTHORITY
PROJECT DIVISION, NATTIKA,
THRISSUR DISTRICT, PIN-680966.
BY ADV. SHRI.P.BENJAMIN PAUL, SC, KERALA WATER
AUTHORITY
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
15.02.2022, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C)No.25425/2021
2
JUDGMENT
Dated this the 15th day of February, 2022
The petitioner, a Construction Company, has filed
this writ petition seeking to command the respondents to
release the trial run amounts deducted vide Ext.P8 as
expeditiously as possible and subject to the petitioner
furnishing a bond for the said amount and to declare that the
deduction of amounts towards "energisation" and
"miscellaneous" charges from the final bill namely Ext.P8
relating to the work awarded to the petitioner is arbitrary and
illegal.
2. The petitioner was awarded the work "AMRUT-WSS
to Guruvayur Municipality - in Thrissur Corporation - Package
I and II - Design, construction and commissioning of 9m dia
intake wellcum pumphouse, 15 MLD Water Treatment Plant,
clear water pump house at Kottapadi and supply, erection, WP(C)No.25425/2021
testing and commissioning of 4 nos RW pump sets having
discharge of 951ps against head of 62m and 2nos. CW pump
sets having discharge 182lps against head of 35m, 2 nos.
500KVA 11KV/433V transformers and other related works" by
the Kerala Water Authority. The petitioner has completed the
work, contends the petitioner. However, the retention amount
and amount withheld towards energisation charges are
indefinitely retained by the respondents. Unless the
respondents are compelled to pay the amount, the petitioner
will be put to untold hardship, contends the learned counsel for
the petitioner.
3. The learned Standing Counsel, on instructions,
submits that though the petitioner has completed his part of
the work, component works to be carried out by other
contractors are not completed. It is in such circumstances that
the amount payable to the petitioner was not paid.
4. I have heard the learned counsel for the petitioner
and the learned Standing Counsel representing the WP(C)No.25425/2021
respondents.
5. As long as the respondents have no dispute
regarding the bills submitted by the petitioner, this Court is of
the view that the respondents are not justified in withholding
the retention amount for the reason that other component
works are not over.
In such circumstances, the writ petition is disposed
of directing the respondents that if the petitioner submits an
indemnity bond in favour of the respondents, the retention
amount withheld by the respondents shall be released within a
period of three months. As regards the energisation charges
withheld, the 3rd respondent shall consider Exts.P10 and P11
representation submitted by the petitioner and take a decision
thereon within a period of two months.
Sd/-
N. NAGARESH JUDGE SR WP(C)No.25425/2021
APPENDIX OF WP(C) 25425/2021
PETITIONER'S EXHIBITS:
Exhibit P1 TRUE COPY OF THE NOTICE INVITING TENDER (NIT).
Exhibit P2 TRUE COPY OF THE PROCEEDINGS DATED 3.9.2018 OF THE SECOND RESPONDENT. Exhibit P3 TRUE COPY OF THE SELECTION NOTICE DATED 4.9.2018.
Exhibit P4 TRUE COPY OF THE ACCEPTED PRICE SCHEDULE OF THE LUMPSUM CONTRACT.
Exhibit P5 TRUE COPY OF THE BANK GUARANTEE FOR AN AMOUNT OF RS.29,12,500/-.
Exhibit P6 TRUE COPY OF THE AGREEMENT
NO.6/SE/PHC/TSR/2018-19 DATED
27.9.2018.
Exhibit P7 TRUE COPY OF THE EXPERIENCE CERTIFICATE
DATED 26.5.2021.
Exhibit P8 TRUE COPY OF THE REQUEST DATED
18.2.2021.
Exhibit P9 TRUE COPY OF FORM CB III VOUCHER DATED
17.2.2021.
Exhibit P9(A) STATEMENT SHOWING THE AMOUNTS RELEASED
TO THE PETITIONER.
Exhibit P10 TRUE COPY OF THE COMMUNICATION DATED
26.3.2021.
Exhibit P11 TRUE COPY OF THE COMMUNICATION DATED
27.5.2021 ISSUED BY THE PETITIONER TO THE FOURTH RESPONDENT.
Exhibit P12 TRUE COPY OF THE JUDGMENT DATED 8.1.2021 IN WRIT PETITION (CIVIL) 3766/2020.
SR
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!