Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Fayis M.D vs Secretary To Government
2022 Latest Caselaw 1446 Ker

Citation : 2022 Latest Caselaw 1446 Ker
Judgement Date : 2 February, 2022

Kerala High Court
Fayis M.D vs Secretary To Government on 2 February, 2022
        IN THE HIGH COURT OF KERALA AT ERNAKULAM
                        PRESENT
          THE HONOURABLE MR.JUSTICE N.NAGARESH
WEDNESDAY, THE 2ND DAY OF FEBRUARY 2022/13TH MAGHA, 1943
                 WP(C) NO. 396 OF 2022
PETITIONER:

         FAYIS M.D.
         AGED 39 YEARS
         S/O.M.D.ABDULLA, P.W.D.CONTRACTOR,
         BERKKA HOUSE, CHENGALA P.O.,
         KASARGOD - 686 605.

         BY ADV K.A.MANZOOR ALI


RESPONDENTS:

    1    SECRETARY TO GOVERNMENT
         PUBLIC WORKS (PS) DEPARTMENT,
         THIRUVANANTHAPURAM - 695 121.
    2    THE CHIEF ENGINEER (ROAD)
         PUBLIC WORKS DEPARTMENT,
         THIRUVANANTHAPURAM - 695 001.
    3    THE SUPERINTENDING ENGINEER
         PUBLIC WORKS DEPARTMENT, KOZHIKODE - 673 647.
    4    EXECUTIVE ENGINEER
         PUBLIC WORKS DEPARTMENT, NIRATH SECTION,
         PERAMBRA, PIN - 673 525.
    5    ASSISTANT ENGINEER
         PUBLIC WORKS DEPARTMENT, NIRATH SECTION,
         PERAMBRA, PIN - 673 525.


         SRI.K.V.MANOJKUMAR, SR.GOVT. PLEADER

     THIS WRIT PETITION (CIVIL) HAVING COME UP       FOR
ADMISSION ON 02.02.2022, THE COURT ON THE SAME       DAY
DELIVERED THE FOLLOWING:
 W.P.(C) No.396/2022
                                       :2:




                           N. NAGARESH, J.

          `````````````````````````````````````````````````````````````
                        W.P.(C) No.396 of 2022

          `````````````````````````````````````````````````````````````
              Dated this the 2nd day of February, 2022

                             JUDGMENT

~~~~~~~~~

The petitioner, who is a PWD Contractor, has

approached this Court seeking to quash Exts.P14 order and

Ext.P16 tender and to direct the 3rd respondent to return the

Security Deposit made by the petitioner before the 3 rd

respondent without delay and without deducting any amount

including the risk and cost, in the interest of justice. The

petitioner has also sought for certain other incidental reliefs.

2. The petitioner states that he was awarded with the

improvement work of Vadakkumpad-Vanchippara-

Gopurathilidam Road between 0/000 and 3/300 under the

control of the 3rd respondent-Superintending Engineer,

PWD. The Work Agreement was executed on 10.12.2019. W.P.(C) No.396/2022

The worksite was handed over on 19.12.2019. The work had

to be completed on or before 18.08.2020. The petitioner

states that the original estimate was for constructing the road

of a width of 3.8 metres. When the work was about to start,

the local residents and beneficiaries demanded the

authorities to have 5.5 metres tarring width, with 8 metres

ROW. As there was no official communication in this regard,

the work could not be started.

3. The petitioner on 16.07.2020, requested the 5 th

respondent to take action for removal of electric poles. The

issues were not resolved. Later, the period of work was

extended up to 30.04.2021. As there was no revised

proposal, the petitioner could not start the work. In the

meanwhile, General Elections were declared and the District

Collector required to stop all works. Ext.P1 letter was issued

on 15.03.2021. The Assistant Executive Engineer, however,

issued Ext.P2 letter dated 24.03.2021 to the petitioner

threatening that he would recommend legal action for failure

to complete the work.

W.P.(C) No.396/2022

4. The petitioner states that later, the Changaroth

Grama Panchayat decided to enhance the tarring width of

the road to 5.5 metres. The said decision was taken at the

intervention of the road beneficiaries and the local MLA. Yet,

the issue was not finalised. On 23.07.2021, by Ext.P3, the

petitioner informed the 5th respondent that he is willing to

construct the road with 3.5 metres width but the local

residents are not permitting to do the work. The petitioner

expressed his inability to do the work in Ext.P3. The

respondents but pressurised the petitioner to complete the

work. The petitioner submitted Ext.P4 letter dated

06.08.2021 to the 4th respondent requesting to extend the

work till 20.04.2021 with fine. The petitioner could not start

the work as the revised estimate was not sanctioned.

5. The petitioner again submitted Ext.P9 letter dated

27.10.2021 requesting to extend the time to complete the

work till 31.03.2022. To Ext.P9, the 3 rd respondent issued

Ext.P10 letter dated 12.11.2021 stating that the work would

be retendered at the risk and cost of the petitioner. The 4 th W.P.(C) No.396/2022

respondent as per Ext.P11, informed the 2 nd respondent that

the work is in progress and revised estimate may be

approved. The 3rd respondent, however, unilaterally

terminated the contract at the risk and cost of the petitioner

as per Ext.P14 communication dated 04.12.2021. The

petitioner submitted Ext.P15 appeal dated 06.12.2021 to the

2nd respondent. Without considering Ext.P15 appeal, Ext.P16

re-tender notification was published on 05.01.2022.

6. The learned counsel for the petitioner argued that

initially the work could not be commenced due to the

obstructions made by beneficiaries of the road. Covid-19

lockdown was also imposed during this time. The work was

resumed in July, 2021. But, by then, the Grama Panchayat

passed a resolution recommending to widen the road to 5.5

metres. Apart from these uncertainties, utilities were not

removed from the worksite. In the meanwhile, the work could

not be proceeded with from 12.03.2021 to 07.04.2021 due to

general elections.

W.P.(C) No.396/2022

7. The learned counsel for the petitioner pointed out

that even the communications between the respondents

would establish that there was a proposal for widening the

road. The issue was not finalised and revised estimate was

not approved. The petitioner had mobilised all requisite men

and material to carry out the work. The work could not be

proceeded with for the aforesaid reasons. The petitioner had

brought to the notice of the respondents the afore facts. The

respondents did not take any decision. The contract with the

petitioner was arbitrarily terminated at the risk and cost of the

petitioner. The termination of the contract at the risk and cost

of the petitioner and the re-tendering of the work are highly

illegal, arbitrary and unsustainable.

8. Respondents 3 and 5 filed a counter affidavit

contesting the contentions of the petitioner. They submitted

that Ext.P14 communication would show the circumstances

under which the agreement had to be cancelled. The

petitioner was lethargic from the very beginning. The

petitioner even delayed execution of agreement. The time W.P.(C) No.396/2022

granted for completion of the work was extended imposing

fine, which obviously would show that the petitioner was at

fault.

9. It was the duty of the petitioner to take initial

levels. The petitioner did not take any steps to take initial

levels even after six months. The petitioner cannot be heard

to complain that utilities were not shifted. As per the

agreement and the PWD Manual, shifting of utilities is a paid

item and it is the duty of the contractor to take initiatives for

the same. The agreement was executed on 10.12.2019. The

work had to be completed within eight months. The execution

of the work ought to have been completed by 18.08.2020.

The petitioner was granted extension more than once. The

contract was terminated only on 04.12.2021. In the facts and

circumstances of the case, termination of the agreement at

the risk and cost of the petitioner is amply justified,

contended the Senior Government Pleader.

10. Heard the learned counsel for the petitioner and

the learned Senior Government Pleader representing the W.P.(C) No.396/2022

respondents.

11. The issue arising in the writ petition is as to who is

responsible for the delay in executing the work. Admittedly,

the worksite was handed over to the petitioner on

19.12.2019. It is the allegation of the petitioner that

beneficiaries of the road and local residents obstructed the

work. The petitioner would also take umbrage under the

Covid-19 lockdown for non-execution of the work. The

petitioner would, however, submit that the work was resumed

in July, 2021. Thereafter, the work had to be stopped in view

of the resolution of the Grama Panchayat recommending

widening of the road.

12. The said contention of the petitioner cannot be

accepted. The petitioner had executed agreement with the

respondents. The respondents have been time and again

requiring the petitioner to proceed with the work. Any

decision taken by the beneficiaries of the road or the local

MLA or any demand made by them for widening the road,

cannot be an excuse for the petitioner not to proceed with the W.P.(C) No.396/2022

work. As long as the respondents have not required the

petitioner to stop the work, the petitioner ought to have

proceeded with the work. The petitioner also cannot rely on

any resolution passed by the Panchayat for widening the

road or on any interdepartmental communications between

the respondents on the proposed revision of estimates, for

not carrying out the work.

13. It is true that elections were declared in the

meanwhile and the petitioner could not have proceeded with

the work from 12.03.2021 to 07.04.2021. The said period is

less than three months. The petitioner has delayed work by

more than 15 months. The petitioner was granted extension

of time for completion of the works. Yet, the petitioner did not

complete the work. A perusal of the pleadings in the writ

petition and the documents made available, would amply

show that the petitioner was not at all vigilant in executing the

work within the time stipulated in the contract or even within

the extended time.

W.P.(C) No.396/2022

In the facts and circumstances of the case, this

Court finds no reason to interfere with Ext.P14 or Ext.P16.

The writ petition is devoid of any merit and it is hence

dismissed.

Sd/-

N. NAGARESH, JUDGE aks/31.01.2022 W.P.(C) No.396/2022

APPENDIX OF WP(C) 396/2022

PETITIONER'S EXHIBITS

Exhibit P1 TRUE COPY OF THE LETTER DATED 15/3/21 ISSUED BY THE 5TH RESPONDENT.

Exhibit P2 TRUE COPY OF THE LETTER DATED 24/3/21 ISSUED BY THE ASSISTANT EXECUTIVE ENGINEER, KOZHIKODE TO THE PETITIONER. Exhibit P3 TRUE COPY OF THE LETTER DATED 23/7/2021 ISSUED BY THE PETITIONER TO THE 3RD RESPONDENT.

Exhibit P4 TRUE COPY OF THE LETTER DATED 6/8/2021 SUBMITTED BY THE PETITIONER TO THE 4TH RESPONDENT.

Exhibit P5 TRUE COPY OF THE LETTER DATED 12/8/2021 SEND BY THE PETITIONER TO THE 3RD RESPONDENT.

Exhibit P6 TRUE COPY OF THE LETTER DATED 2/9/2021 ISSUED TO THE PETITIONER BY THE 5TH RESPONDENT.

Exhibit P7 TRUE COPY OF THE LETTER DATED 13/10/2021 SEND BY THE 5TH RESPONDENT.

Exhibit P8            TRUE   COPY   OF    THE   LETTER  DATED
                      20/10/2021    ISSUED    BY    THE   1ST
                      RESPONDENT TO THE 2ND RESPONDENT.
Exhibit P9            TRUE   COPY  OF    THE   REQUEST  DATED

27/10/2021 SEND TO THE 3RD RESPONDENT BY THE PETITIONER.

Exhibit P10           TRUE   COPY   OF    THE   LETTER  DATED
                      12/11/2021    ISSUED    BY    THE   3RD
                      RESPONDENT TO THE PETITIONER.
Exhibit P11           TRUE   COPY   OF    THE   LETTER  DATED

20/11/2021 SEND TO THE 2ND RESPONDENT BY THE 4TH RESPONDENT.

Exhibit P12 TRUE COPY OF THE LETTER DATED 20/11/2021 ISSUED BY THE PETITIONER TO THE 3RD RESPONDENT.

Exhibit P13 TRUE COPY OF THE LETTER DATED 27/11/2021 ISSUED BY THE PETITIONER TO THE 3RD RESPONDENT.

W.P.(C) No.396/2022

Exhibit P14 TRUE COPY OF THE PROCEEDINGS DATED 4/12/2021 OF THE 3RD RESPONDENT.

Exhibit P15 TRUE COPY OF THE REVIEW PETITION DATED 6/12/2021 FILED BY THE PETITIONER BEFORE THE 2ND RESPONDENT.

Exhibit P16 TRUE COPY OF THE TENDER DATED 05/01/2022.

P17 COPY OF JUDGMENT IN WPC.5972/2016 DT 20.1.2021

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter