Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Ashrae Clean Room Presentations ... vs The Department Of Industries And ...
2022 Latest Caselaw 1343 Ker

Citation : 2022 Latest Caselaw 1343 Ker
Judgement Date : 1 February, 2022

Kerala High Court
Ashrae Clean Room Presentations ... vs The Department Of Industries And ... on 1 February, 2022
        IN THE HIGH COURT OF KERALA AT ERNAKULAM
                        PRESENT
          THE HONOURABLE MR.JUSTICE N.NAGARESH
TUESDAY, THE 1ST DAY OF FEBRUARY 2022 / 12TH MAGHA, 1943
                WP(C) NO. 28448 OF 2021
PETITIONER:

         ASHRAE CLEAN ROOM PRESENTATIONS PRIVATE LTD
         A COMPANY INCORPORATED UNDER THE COMPANIES ACT,
         REP BY MANAGING DIRECTOR, MR.MS. ANAND,
         S/O. N.C.G.NAIR, AGED 74, D-73, 1ST FLOOR,
         MADHURA NAGAR, S.R.NAGAR P.O.,
         HYDERABAD-500038 , TELENGANA

         BY ADV NAVIA SEBASTIAN


RESPONDENTS:

    1    THE DEPARTMENT OF INDUSTRIES AND COMMERCE
         REPRESENTED BY ITS PRINCIPAL SECRETARY
         (INDUSTRIES), SECRETARIAT,
         THIRUVANANTHAPURAM-695 001
    2    THE KERALA STATE DRUGS & PHARMACEUTICALS LTD,
         KALAVOOR,
         ALAPUZHA, KERALA-688 522, REPRESENTED BY ITS
         MANAGING DIRECTOR

         BY ADV SHRI.P.C.SASIDHARAN, SC, KERALA STATE
         DRUGS AND PHARMACEUTICALS LIMITED
         SRI.P.SANTHOSHKUMAR, SPL.GP (INDUSTRIES)

     THIS WRIT PETITION (CIVIL) HAVING COME UP          FOR
ADMISSION ON 01.02.2022, THE COURT ON THE SAME          DAY
DELIVERED THE FOLLOWING:
 W.P.(C) No.28448/2021
                                      :2:




                           N. NAGARESH, J.

         `````````````````````````````````````````````````````````````
                     W.P.(C) No.28448 of 2021

          `````````````````````````````````````````````````````````````
              Dated this the 1st day of February, 2022

                            JUDGMENT

~~~~~~~~~

The petitioner is a Company doing business in

Heating, Ventilation and Air Conditioning. The petitioner is

also specialised in Clean Room Technology. The petitioner

has filed this writ petition seeking the following reliefs:

(i) Issue any appropriate Writ by declaring the action of the 2nd respondent in calling for Tender for Supply, Installation, Testing, Commissioning & Validation of HVAC Works as per GMP Standard for Non-Beta Lactam Project vide Ext.P14 Tender Reference Number KSDP/PRJ/NB/HVAC/10/21- 22/124 DATED 07/12/2021 AT 01:43 PM, as arbitrary, illegal and unreasonable.

(ii) Issue any appropriate Writ by declaring the action of the 2nd respondent in calling for Tender for Supply, Installation, Testing and Commissioning of Clean Room Panel Works Using PCGI Panels as per GMP Standard for Non-Beta Lactam Project vide Ext.P15 Tender Reference Number KSDP/PRJ/NB/PCGI/09/21-22/123 DATED W.P.(C) No.28448/2021

07/12/2021 01:48 PM, as arbitrary, illegal and unreasonable.

(iii) Issue any appropriate Writ by declaring the action of the 2nd respondent in calling for Tender for Supply, Installation, Testing, Commissioning and Validation of HVAC System as per GMP Standard for Beta Lactam Blister Packing Project vide Ext.16 Tender Reference Number KSDP/PRJ/BETA/11/21- 22/125 DATED 07/12/2021 01:45 PM, as arbitrary, illegal and unreasonable.

(iv) Issue Writ of Mandamus or any other appropriate writ directing the 2nd respondent to recall & cancel the Tender for Supply, Installation, Testing, Commissioning & Validation of HVAC Works as per GMP Standard for Non Beta Lactam Project vide Ext.P14 Tender Reference Number KSDP/PRJ/NB/HVAC/10/21-22/124 DATED 07/12/2021 AT 01:43 PM.

(v) Issue Writ of Mandamus or any other appropriate writ directing the 2nd respondent to recall & cancel the Tender for Supply, Installation, Testing and Commissioning of Clean Room Panel Works Using PCGI Panels as per GMP Standard for Non- Beta Lactam Project vide Ext.P15 Tender Reference Number KSDP/PRJ/NB/PCG1/09/21- 22/123 DATED 07/12/2021 01:48 PM.

(vi) Issue Writ of Mandamus or any other appropriate writ directing the 2nd respondent to recall & cancel the Tender for Supply, Installation, Testing, Commissioning and Validation of HVAC System as per GMP Standard for Beta Lactam Blister Packing Project vide Ext.P16 Tender Reference Number KSDP/PRJ/BETA/11/21-22/125 DATED 07/12/2021 01:45 PM.

(vii) Issue Writ of Mandamus or any other appropriate writ directing the 2nd respondent to cancel the Termination of Workup order dated 19/02/2018 and permit the petitioner to continue the works.

W.P.(C) No.28448/2021

(viii) Issue Writ of Mandamus or any other appropriate writ directing the 2nd respondent to cancel Termination Notice dated 28/09/2021 of Work order dated 19/02/2018 and permit the petitioner to continue the works.

(ix) Issue Writ of Mandamus or any other appropriate writ directing the 2nd respondent to cancel the Termination Notice dated 28/09/2021 of Work order 30/12/2017 and permit the petitioner to continue the works.

(x) Issue Writ of Mandamus or any other appropriate writ directing the 2nd respondent to cancel the Termination Notice dated 28/09/2021 of Work order dated 10/01/2018 and permit the petitioner to continue the works.

(xi) Issue Writ of Mandamus or any other appropriate writ directing the 2nd respondent to settle the accounts after conducting the measurements for the works done and release the payments to the petitioner.

2. In the writ petition, it has been pleaded as follows.

The 2nd respondent-Kerala State Drugs and Pharmaceuticals

Limited is a Government of Kerala Undertaking. The

petitioner has executed a number of works for the 2 nd

respondent. The 2nd respondent awarded three new works

and issued work order Nos.KSDP/PRJ/NBETA/HVAC/

30/1718/57 dated 30.12.2017, KDSP/PRJ/NBETA/PCGI/13/

17-18/38 dated 11.11.2017 and KDSP/PRJ/BETABLISTER/ W.P.(C) No.28448/2021

HVAC/38/17-18/77 dated 12.11.2018. Though the petitioner

has been executing these works, the 2 nd respondent

withheld payments. The petitioner was not provided with

structural drawings and site for progress of the work. At the

same time, the 2nd respondent tried to invoke Bank

Guarantee provided by the petitioner. The petitioner filed

O.S. No.1275/2019 before the XXI Junior Civil Judge,

Hyderabad. When the 2nd respondent tried to invoke Bank

Guarantee, the petitioner filed injunction Suit. The 2 nd

respondent arbitrarily invoked Bank Guarantee.

3. The petitioner issued Ext.P3 letter dated

11.08.2021 to the 2nd respondent seeking payment of Bills to

the tune of ₹1,58,35,448/- due to the petitioner. The 2 nd

respondent, in response, directed the petitioner to complete

all pending works within 30 days, as per Ext.P4 letter dated

26.08.2021. The petitioner submitted Ext.P5 reply dated

28.08.2021 pointing out that the work order was amended on

three occasions and the 2nd respondent has not adhered to

the contractual obligation of diminishing Bank Guarantee. W.P.(C) No.28448/2021

The design of the partition was changed 14 to 16 times and it

is humanly impossible to complete the work even in 90 days.

By Ext.P6 letter dated 28.08.2021, the petitioner reminded

the 2nd respondent about the pending bills.

4. To the dismay of the petitioner, the 2 nd

respondent terminated all the three work orders as per

Exts.P7 to P9 dated 28.09.2021. The petitioner submitted

Exts.P10 to 12 replies dated 29.09.2021 to Exts.P7 to P9

cancellations. The petitioner also requested for a joint

measurement as to the work completed by the petitioner and

requested for return of tools, as per Ext.P13 letter dated

10.11.2021. The request of the petitioner fell in deaf ears.

Hence, the petitioner is before this Court.

5. The 2nd respondent filed a Statement and

contested the writ petition. The 2nd respondent stated that the

petitioner though entered into three agreements, did not

show any progress in terms of the work order. The

respondents have been issuing letters one after another to

the petitioner requiring to complete the works as scheduled. W.P.(C) No.28448/2021

The entire modernisation work of the 2 nd respondent-

Company was unduly delayed. Negotiations were held with

the petitioner. A joint meeting was convened on 12.06.2019.

The petitioner agreed to complete all works on or before

31.07.2019. Even thereafter, the works were not proceeding.

Further discussions with the petitioner were held on

09.11.2019. The petitioner was granted extended time to

complete the works. The petitioner as per Annexure-R2(e)

agreed to complete the works by 27.02.2020.

6. The petitioner still did not honour its commitment.

The delay on the part of the petitioner in executing the works

would result in payment of liquidated damages to the States

with whom the 2nd respondent entered into agreements for

supply of medicines. In the circumstances, the 2 nd

respondent had no other option than to terminate the

contracts. Time is the essence of all the three contracts. The

agreement provided that if there is a dispute between the

petitioner and the 2nd respondent, it should be resolved

through arbitration proceedings. O.S. No.1275 of 2019 filed W.P.(C) No.28448/2021

by the petitioner before the Junior Civil Judge, City Civil

Court, Hyderabad was dismissed as per Annexure-R2(f).

O.S. No.2174 of 2019 filed by the petitioner was closed as

per Annexure-R2(g) as the issue was referred to Arbitrator.

7. The 2nd respondent has already revoked the Bank

Guarantee and has terminated the agreements. The works

were re-tendered. The contention of the petitioner that

measurement was not taken in its presence does not merit

any consideration. The measurement was taken in the

presence of the representatives of the petitioner-Company.

The 2nd respondent is entitled to recover the loss incurred

from the petitioner. The petitioner cannot invoke this Court's

writ jurisdiction for redressal of disputes of a commercial

nature.

8. The learned counsel for the petitioner submitted

that in view of the judgment of the Apex Court in Union of

India and others v. Tantia Constructions Private Limited

[(2011) 5 SCC 697], alternative remedy is not an absolute

bar to invoke the jurisdiction of this Court. Arbitration is only W.P.(C) No.28448/2021

one alternate remedy as per the agreement. The petitioner

had assured the 2nd respondent that work will be completed

in all respects and plant handed over to the 2 nd respondent

on or before 27.02.2020, provided the 2 nd respondent clears

all the 22 points mentioned in the e-mail dated 18.11.2019

forwarded by the petitioner.

9. The counsel for the petitioner pointed out that the

measurements noted by the respondents in Ext.R2(k) are not

visible and is not countersigned by the petitioner. Entire joint

measurements have not been taken. Joint measurements of

a large number of works, have not been done. The

termination of the contracts is highly arbitrary. As per the

terms of contract, Agreement Authority shall give 15 days

notice of termination in writing to the Contractor, which has

not been done by the 2nd respondent. The drawings given by

the 2nd respondent were incomplete, which is the major

reason for the delay.

10. I have heard the counsel for the petitioner, the

Special Government Pleader (Industries) for the 1 st W.P.(C) No.28448/2021

respondent and the Standing Counsel for the 2 nd

respondent.

11. Three contracts were entered into by the petitioner

and work orders were issued on 11.11.2017, 30.12.2017 and

12.11.2018. The first two works were to be completed within

90 days and the 3rd one within 30 days. The petitioner did not

carry out the work with promptitude. A joint meeting was

convened by the 2nd respondent on 12.06.2019. By the time,

more than 18 months had elapsed. In this meeting, the

petitioner agreed to complete all the works before

31.07.2019. Annexure-R2(d) minutes of the meeting would

disclose that the petitioner had not raised any technical

issues which would hamper the completion of work. The

issue of drawings is not seen raised by the petitioner in the

meeting. The only concern expressed appears to be in

respect of payment of Bills.

12. The petitioner did not complete the work by

31.07.2019. Again, another meeting was held on

09.11.2019. By Annexure-R2(e), the petitioner again agreed W.P.(C) No.28448/2021

to complete the work by 27.02.2020. It is the specific case of

the 2nd respondent that it had cleared all the 22 points as

mentioned in the petitioner's e-mail dated 18.11.2019. Yet,

the work was not completed even by 27.02.2020. The

inordinate delay on the part of the petitioner delayed the

modernisation plans of the 2nd respondent and consequential

financial losses were incurred.

13. The agreements provided for arbitration

proceedings for resolution of any disputes arising from the

agreements. The petitioner, however, filed O.S.

No.1275/2019 in the Court of the Junior Civil Judge, City Civil

Court, Hyderabad during the extended period of contract,

which was withdrawn on 30.07.2019. In another O.S.

No.2174/2019 filed before the Court of the Junior Civil Judge,

the said court referred the dispute for arbitration as per

Annexure-R2(g) order.

14. The 2nd respondent has already terminated the

contracts and has invoked Bank Guarantee. The works have

been already retendered.

W.P.(C) No.28448/2021

15. The grounds urged by the petitioner challenging

termination of contracts are all disputed questions of facts

which cannot be decided by this Court, in exercise of the

powers conferred under Article 226 of the Constitution of

India. The agreements executed by the petitioner provide for

arbitration for resolution of disputes arising out of the

contract. The counsel for the petitioner urged that even if the

petitioner is to be relegated to arbitration proceedings, this

Court may order a joint inspection in respect of the works

completed by the petitioner in pursuance of the agreements.

The 2nd respondent disputed the said claim also stating the

measurements of works done by the petitioner have already

been taken in the presence of the officials of the petitioner-

company.

16. In the facts and circumstances of the case, this

Court find that the petitioner has to resort to arbitration or

other civil proceedings for redressal of grievances and a writ

petition is not maintainable, in the facts of the case. W.P.(C) No.28448/2021

The writ petition fails and it is consequently

dismissed.

Sd/-

N. NAGARESH, JUDGE aks/28.01.2022 W.P.(C) No.28448/2021

APPENDIX OF WP(C) 28448/2021

PETITIONER'S EXHIBITS

Exhibit P1 TRUE COPY OF ORDER IN IA NO.223/2019 IN OS NO.1275/2019 DATED 06.06.2019 PASSED BY THE HON'BLE XXI JUNIOR CIVIL JUDGE, HYDERABAD Exhibit P2 TRUE COPY OF ORDER IN IA NO.510/2019 IN OS NO.2174/2019 DATED 19.09.2019 PASSED BY THE HON'BLE XXI JUNIOR CIVIL JUDGE, HYDERABAD Exhibit P3 TRUE COPY OF LETTER DATED 11.08.2021 ISSUED BY THE PETITIONER TO THE RESPONDENT NO.2 REGARDING NON PAYMENT OF AN AMOUNT OF RS 1,58,35,448/-

Exhibit P4 TRUE COPY OF RESPONDENT NO.2 ISSUED LETTER DATED 26.08.2021 TO PETITIONER WHEREIN 30 DAYS WERE PROVIDED TO COMPLETE ALL THE PENDING WORKS Exhibit P5 TRUE COPY OF REPLY LETTER DATED 28.08.2021 ISSUED BY THE PETITIONER TO THE LETTER DATED 26.08.2021 Exhibit P6 TRUE COPY OF LETTER DATED 28.08.2021 ISSUED BY THE PETITIONER WHEREIN IT WAS CATEGORICALLY STATE THAT THE DESIGN FOR THE PETITIONERS WERE CHANGED 14 TO 16 TIMES Exhibit P7 TRUE COPY OF LETTER DATED 28.09.2021 ISSUED BY RESPONDENT NO.2 TERMINATING WORK ORDER DATED 19.02.2018 Exhibit P8 TRUE COPY OF LETTER DATED 28.09.2021 ISSUED BY RESPONDENT NO.2 TERMINATING WORK ORDER DATED 30.12.2017 Exhibit P9 TRUE COPY OF LETTER DATED 28.09.2021 ISSUED BY RESPONDENT NO.2TERMINATING WORK ORDER DATED 10.01.2018 Exhibit P10 TRUE COPY OF THE SAID CANCELLATION OF WORK ORDER DATED 30.12.2017 WAS REPLIED BY THE PETITIONER BY VIRTUE OF LETTER DATED 29.09.2021 W.P.(C) No.28448/2021

Exhibit P11 TRUE COPY OF THE SAID CANCELLATION OF WORK ORDER DATED 10.01.2018 WAS REPLIED BY THE PETITIONER BY VIRTUE OF LETTER DATED 29.09.2021 Exhibit P12 TRUE COPY OF THE SAID CANCELLATION OF WORK ORDER DATED 19.02.2018 WAS REPLIED BY THE PETITIONER BY VIRTUE OF LETTER DATED 29.09.2021 Exhibit P13 TRUE COPY OF LETTER DATED 10.11.2021 ISSUED BY PETITIONER FOR REQUESTING FOR COMBINED MEASUREMENTS FOR ALL THE JOBS ALONG WITH RETURNING OF TOOLS AND TACKLES TO THE RESPONDENT NO.2 Exhibit P14 TRUE COPY OF TENDER FOR SUPPLY INSTALLATION TESTING COMMISSIONING & VALIDATION OF HVAC WORKS AS PER GMP STANDARD FOR NON-BETA LACTAM PROJECT VIDE TENDER REFERENCE NUMBER KSDP/PRJ/NB/HVAC/10/21-22/124 DATED 07.12.2021 AT 01.43 PM Exhibit P15 TRUE COPY OF TENDER FOR SUPPLY INSTALLATION TESTING AND COMMISSIONING OF CLEAN ROOM PANNEL WORKS USING PCGI PANELS AS PER GMP STANDARD FOR NON-

                        BETA   LACTAM    PROJECT    VIDE  TENDER
                        REFERENCE                         NUMBER

KSDP/PRJ/NB/PCGI/09/2021-22/123 DATED 07.12.2021 AT 01.48 PM Exhibit P16 TRUE COPY OF TENDER FOR SUPPLY INSTALLATION TESTING COMMISSIONING AND VALIDATION OF HVAC SYSTEM AS PER GMP STANDARD FOR BETA LACTAM BLISTER PACKING PROJECT VIDE TENDER REFERENCE NUMBER KSDP/PRJ/BETA/11/21-22/125 DATED 07.12.2021 AT 01.45 PM

RESPONDENT EXHIBITS

Exhibit R2(a) COPY OF WORK ORDER DT 11.11.2017 Exhibit R2(b) COPY OF WORK ORDER DT 30.12.2017 BY 2ND RESPONDENT Exhibit R2(c) COPY OF WORK ORDER DT 12.11.2018 Exhibit R2(d) COPY OF MINUTES OF MEETING WITH THE PETITIONER ON 12.6.2019 W.P.(C) No.28448/2021

Exhibit R2(e) COPY OF AGREEMENT REGARDING COMPLETION OF WORKS DT 28.11.2019 Exhibit R2(f) COPY OF ORDER OF JUNIOR CIVIL JUDGE, CITY CIVIL COURT, HYDERABAD.

Exhibit R2(g)           COPY OF ORDER OF JUNIOR CIVIL JUDGE,
                        CITY   CIVIL     COURT,     HYDERABAD    IN
                        IA.581/2019
Exhibit R2(h)           COPY OF EMAIL DT 31.5.2021.
Exhibit R2(I)           TRUE   COPY     OF    THE   LETTER    DATED

03/10/2019 ADDRESSED TO THE PETITIONER REGARDING INFORMING OF THE ACT Exhibit R2(J) TRUE COPY OF THE HVAC WORK FOR NON BETALCTUM PLANT MEASURED BY THE 2ND RESPONDENT Exhibit R2(K) TRUE COPY OF THE MEASUREMENT IN RELATION TO PCGI PANEL OF NON BETALACTUM PROJECT WAS MADE ON 09/03/2021 Exhibit R2(L) TRUE COPY OF THE JOINT MEASUREMENT MADE ON 25/03/2021 Exhibit R2(M) TRUE COPY OF THE ACKNOWLEDGEMENT MADE BY THE PETITIONER REGARDING THE JOINT MEASUREMENT DATED 05/07/2021 Exhibit R2(N) TRUE COPY OF THE TENDER DETAILS CONTAINING THE DRAWINGS DATA SHEET AND SPECIFICATION

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter