Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Atlas Celestial Park Apartment ... vs Kerala State Electricity Board ...
2022 Latest Caselaw 11167 Ker

Citation : 2022 Latest Caselaw 11167 Ker
Judgement Date : 2 December, 2022

Kerala High Court
Atlas Celestial Park Apartment ... vs Kerala State Electricity Board ... on 2 December, 2022
          IN THE HIGH COURT OF KERALA AT ERNAKULAM
                          PRESENT
           THE HONOURABLE MR. JUSTICE AMIT RAWAL
FRIDAY, THE 2ND DAY OF DECEMBER 2022 / 11TH AGRAHAYANA, 1944
                  WP(C) NO. 10495 OF 2021
PETITIONER/S:

         ATLAS CELESTIAL PARK APARTMENT OWNERS ASSOCIATION,
         REG.NO.EKM/TC/885/2014, N.S.S.JUNCTION,
         NAYATHODE P.O., NEDUMBASSERY,
         ERNAKULAM, PIN - 683 572
         REPRESENTED BY ITS SECRETARY SHRI.SAJITH JOHN.
         BY ADVS.
         LAL K.JOSEPH
         SRI.P.MURALEEDHARAN (THURAVOOR)
         SMT.T.A.LUXY
         SHRI.SURESH SUKUMAR
         SRI.ANZIL SALIM
         SHRI.MANUEL K.M.
         SHRI.SETHU KRISHNA R.S.
         SHRI.CHACKO MATHEWS K.
         SMT.NOORUNISSA K.A.
RESPONDENT/S:


    1    KERALA STATE ELECTRICITY BOARD LTD.,
         VYDHYUDHIBHAVANAM, PATTOM,
         THIRUVANANTHAPURAM, PIN - 695 004
         REPRESENTED BY ITS SECRETARY.
    2    THE DEPUTY CHIEF ENGINEER
         KERALA STATE ELECTRICITY BOARD LTD.,
         ELECTRICAL CIRCLE, PERUMBAVOOR,
         PIN - 683 542.
    3    THE ASSISTANT ENGINEER
         KERALA STATE ELECTRICITY BOARD LTD., ELECTRICAL
         SECTION, KALADY, PIN - 683 574.
    4    THE CHIEF ELECTRICAL INSPECTOR
         OFFICE OF THE CHIEF ELECTRICAL INSPECTOR,
         HOUSING BOARD BUILDING, SHANTHI NAGAR,
         THIRUVANANTHAPURAM, PIN - 695 001.
 WP(C)s 10495 & 25548/2021

                                2


      5      ATLAS GOLD TOWNSHIPS(INDIA) PRIVATE LTD.
             NEAR FEDERAL BANK, VAPPALASSERRY P.O., ANGAMALY,
             ERNAKULAM, PIN - 683 572 REPRESENTED BY RESOLUTION
             PROFESSIONAL, JASIN JOSE.
             BY ADVS.
             SUDHEER GANESH KUMAR.R.
             B.PRAMOD


       THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON 02.12.2022, ALONG WITH WP(C).25548/2021, THE COURT ON
THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C)s 10495 & 25548/2021

                                       3




              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                    PRESENT
                THE HONOURABLE MR. JUSTICE AMIT RAWAL
FRIDAY, THE 2ND DAY OF DECEMBER 2022 / 11TH AGRAHAYANA, 1944
                            WP(C) NO. 25548 OF 2021
PETITIONER/S:

             ATLAS CELESTIAL PARK APARTMENT OWNERS ASSOCIATION,
             REG NO. EKM/TC/885/2014,
             N.S.S. JUNCTION, NAYATHODE P.O.,
             NEDUMBASSERY, ERNAKULAM 683 572,
             REPRESENTED BY ITS SECRETARY SHRI. SAJITH JOHN.
             BY ADVS.
             LAL K.JOSEPH
             P.MURALEEDHARAN (THURAVOOR)
             T.A.LUXY
             SURESH SUKUMAR
             ANZIL SALIM
             CHACKO MATHEWS K.
RESPONDENT/S:

      1      KERALA STATE ELECTRICITY BOARD LTD -
             VYDHYUDHIBHAVANAM, PATTOM,
             THIRUVANANTHAPURAM 695 004,
             REPRESENTED BY ITS SECRETARY.
      2      THE DEPUTY CHIEF ENGINEER,
             KERALA STATE ELECTRICITY BOARD LTD,
             ELECTRICAL CIRCLE, PERUMBAVOOR, 683 542.
      3      THE ASSISTANT ENGINEER,
             KERALA STATE ELECTRICITY BOARD LTD,
             ELECTRICAL SECTION, KALADY 683 574.
 WP(C)s 10495 & 25548/2021

                                        4


      4       THE CHIEF ELECTRICAL INSPECTOR,
              OFFICE OF THE CHIEF ELECTRICAL INSPECTOR,
              HOUSING BOARD BUILDING, SHANTHI NAGAR,
              THIRUVANANTHAPURAM 695 001.
      5       ATLAS GOLD TOWNSHIPS (INDIA) PRIVATE LTD,
              NEAR FEDERAL BANK , VAPPALLASSERRY P.O., ANGAMALY,
              ERNAKULAM 683 572, REPRESENTED BY RESOLUTION
              PROFESSIONAL JASIN JOSE.
       THIS     WRIT        PETITION   (CIVIL)   HAVING   COME   UP   FOR
ADMISSION ON 02.12.2022, ALONG WITH WP(C).10495/2021, THE
COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C)s 10495 & 25548/2021

                                     5




                    AMIT RAWAL, J.
             ------------------------------------
       WP(C) Nos.10495 and 25548 of 2021
            -------------------------------------
      Dated this the 2nd day of December, 2022


                            JUDGMENT

This judgment of mine shall dispose of two writ

petitions, namely WP(C) Nos.10495 and 25548 of 2021,

preferred by the very same petitioner. For the sake of

convenience, hereinafter, WP(C) No.10495/2021 will be

called as the first writ petition, and WP(C) No.25548/2021

as the second writ petition.

2. The reliefs sought for in the first writ petition are

as follows:

"i) Issue a Writ of Certiorari or any other appropriate Writ or Order quashing Ext-P5 communication dated 10/3/2021 to the extent it insists for the re submission of the Compliance Report & Completion Report by the 5th respondent, WP(C)s 10495 & 25548/2021

ii) Issue a Writ of Mandamus or any other appropriate Writ or Order directing the respondents 1 to 4 to accept the, Compliance Report & Completion Report for the temporary installation of 500KVA DG set submitted by the petitioners and such other applications which are deemed necessary to provide electric connections separately to the apartment owners in the residential complex of the petitioner and for effective implementation of Ext.P3 Scheme within a specific time frame.

iii) Issue a Writ of Mandamus or any other appropriate Writ or Order directing the respondents 1 to 4 not to insist for arrears of electricity charges from the petitioner for the purpose of granting electric connection to each apartment owners, while implementing Exhibt P3 Scheme.

iv) Declare that the petitioner is not liable to pay the arrears of electricity charges demanded against the 5th respondent in Ext P8."

Likewise, following are the reliefs sought for in the second

writ petition:

"i) Issue a Writ of Certiorari or any other appropriate writ or order quashing Ext.P10 and Ext.P11,

ii) Issue a Writ of Mandamus or any other appropriate Writ or Order directing the respondents 1 to 4 to implement Ext. P3 Scheme for grant of LT connections to the individual owners of the petitioner in view of Exts.

WP(C)s 10495 & 25548/2021

P2 and P4 within a specific time frame.

iii) Issue a Writ of Mandamus or any other appropriate Writ or Order directing the respondents 1 to 4 not to insist for arrears of electricity charges covered by Ext P10 and Ext P11 from the petitioner for the purpose of granting electric connection to each apartment owners, while implementing Exhibit P3 Scheme."

3. Insofar as the first and second prayers in the first

writ petition are concerned, they had been taken care of by

this Court by granting interim order dated 27.4.2021, which

reads as under:

"Admit.

The learned Government Pleader takes notice for R4. The learned Standing Counsel takes notice for R1 to R3. Issue notice to R5.

Since by Ext.P7, the 5th respondent has become incapable of making any application, petitioner, as a body of apartment owners are permitted to submit compliance report and completion report and all other applications on behalf of the 5th respondent. To enable the petitioner to do the above, Ext.P5 shall stand stayed until further orders."

WP(C)s 10495 & 25548/2021

As far as relief no.(iv) in the first writ petition is concerned,

which is for a declaration that the petitioner is not liable to

pay the arrears of electricity charges demanded against the

5th respondent in Ext.P8, the same has been put at rest for

the reason that by virtue of the judgment, produced as

Ext.P4 in the first writ petition, rendered by a Division Bench

of this Court in W.A.No.1673/2019 dated 29.1.2021, the

individual owners have been issued LT connections and have

also submitted a Bank Guarantee (produced as Ext.P14 in

the first writ petition) in terms of the provisions of sub-

Regulation (3) of Regulation 40 of the Electricity Supply

Code, 2014.

4. In the second writ petition, the prayer of the

petitioner is only for restraining the respondents from

demanding the arrears from them.

5. This case has a checkered history, which has been WP(C)s 10495 & 25548/2021

taken care of and noted extensively by a learned Single

Judge of this Court in Ext.P1 order dated 23.11.2017 in

WP(C) No.15370/2017 and a Division Bench of this Court in

Ext.P4 judgment dated 29.1.2021 in W.A.No.1817/2019 and

connected cases. The Division Bench considering the

predicament of the petitioner therein noted the following

observations:-

"19. In the instant case, none had applied seeking permission for a single point supply as contemplated under the provisions mentioned above. The original application, on the basis of which HT connection was initially granted, a copy of which was produced by the learned Standing Counsel, pursuant to the direction of this Court, shows that the application was made on 01.10.2015 for three buildings bearing Nos.XIV/188A1 for an area of 286.58 sq.m, Nos.XIV/188A2, for an area of 162.44 sq.m and building No. XIV/188A3 for an area of 15.03 sq.m. In the tariff category shown in the approval order, there are overwritings and erasures, that are visible even in the photocopy. On the basis of an application for three apartments in the apartment complex, HT connection is stated to have been given for the WP(C)s 10495 & 25548/2021

entire complex for all the apartments. It raises doubts on the manner in which such connections were provided. None of the individual apartment owners, other than the three building numbers mentioned earlier, had ever applied independently for the grant of HT connection to their respective apartments. In such circumstances, we are of the view that the initial grant of HT connection to the apartment complex constructed by the 4th respondent bearing the name 'Atlas Celestial Park' was not legally valid."

It is contended that the Bank Guarantee has been submitted

later on, for, the respondent-Electricity Board had been

insisting the petitioner for clearing of the arrears. Though

Bank Guarantee deemed to have been submitted under

protest strictly in compliance of the provisions of sub-

Regulation (3) of Regulation 40 of the Electricity Supply

Code, but the fact remains that during the interregnum,

Insolvency and Bankruptcy Code proceedings were initiated

against the builder, Atlas Gold Township (India) Private Ltd., WP(C)s 10495 & 25548/2021

and Resolution Professional has been appointed. In one of

the communications submitted by the petitioner to the

Resolution Professional, it surfaced that the KSEB had

preferred a claim in respect of the arrears of electricity of

the erstwhile Company.

6. It is discerned that once KSEB had taken steps for

recovery, arrears cannot be recovered from the petitioner.

Period of three years is to be reckoned from the date of

submission of the claim before the Resolution Professional.

Sub-Regulation (3) of Regulation 40 reads as under:

"40. Recovery of arrears relating to the previous consumer.-

xxx xxx xxx (3) If a purchaser or lessee or occupier of such premises requires a new connection, as the earlier connection given to the previous consumer in that premises has already been disconnected and dismantled on the ground of outstanding dues of the previous consumer, new connection shall not be denied to such purchaser or lessee or occupier of the premises provided he furnishes a deposit which shall be WP(C)s 10495 & 25548/2021

equal to the arrears of electricity charges and other liabilities if any, excluding interest thereon, till the licensee obtains from the appropriate legal forum an order on the recovery of arrears and other liabilities or till the licensee settles the arrears and liabilities with the previous consumer or till completion of three years whichever is less:

Provided that on obtaining order from the appropriate legal forum on the recovery of such arrears of electricity charges and other liabilities, or on settlement of the arrears and liabilities by the licensee with previous consumer or on completion of three years as aforesaid, the licensee shall release the entire amount of deposit furnished by such owner or lessee or occupier of the premises, along with interest at bank rate as on the date of furnishing such deposit."

On scrutiny of the aforementioned Regulation, it is evident

that once the licensee has taken steps to recover arrears,

the period of three years will have to be reckoned from the

date when the step is taken. After completion of three years

from the date on which the step has been taken, the

petitioner shall be entitled to seek release of the entire WP(C)s 10495 & 25548/2021

amount of the deposit, in view of the proviso to sub-

Regulation (3), which mandates the licensee to release the

entire amount of deposit furnished by the owner or occupier

of the premises along with interest as on the date of

submission of the claim before the Resolution Professional.

Therefore, the demand raised by the respondents for

claiming the arrears is not sustainable and is liable to be

quashed and, at best, to be kept in abeyance for a period of

three years.

7. It is then contended that during the pendency of

these writ petitions supervening facts occurred, which

necessitated the petitioner to prefer I.A. No.2/2022 in the

first writ petition reflecting furnishing of Ext.P14 Bank

Guarantee on 15.6.2022 and Ext.P16 demand notice dated

27.7.2022 and Ext.P17 reply dated 3.8.2022. The petitioner

submitted Ext.P15 application dated 24.2.2022 for renewal WP(C)s 10495 & 25548/2021

of the licence for working of the lift/escalator at the

premises and deposited a sum of Rs.13,230/- on 24.2.2021.

The respondents responded to the aforementioned request

vide Ext.P16 communication dated 27.7.2022 stating that a

sum of Rs.5,61,592/- is due as the arrears on account of the

periodical inspection of electrical installations at the

premises, which had not been remitted and called upon the

petitioner to remit the same into the Government Treasury

or through on-line under a specific head, failing which the

electric connection to the premises will be disconnected

without further notice. The petitioner responded to the

aforementioned communication vide Ext.P17 dated 3.8.2022

pointing out the facts that the builder company is non-

existent and is under liquidation process in NCLT; KSEB has

already filed a claim for the arrears before the NCLT; and

there is already an interim order passed in the first writ WP(C)s 10495 & 25548/2021

petition from which it was understood that the builder has

become incapacitated from making any application and

therefore, permission be granted to the petitioner to submit

the compliance report and application, if any, on behalf of

the builder. Despite that the respondents are insisting the

petitioner for remittance of periodical inspection charges. As

per the provisions of Regulation 43 of Central Electricity

Authority (Measures relating to Safety and Electricity

Supply) Regulations, 2010, the Electrical Inspector is

required to conduct an inspection to ensure that electric

supply line or apparatus of voltage exceeding 650 V are

placed in position, properly joined, duly completed and

examined and only thereafter if all the measures are in tact

for the purpose of safety and achievement of the provisions

of the Act, shall submit a report for commencement of the

supply. The said provision would not be applicable, for the WP(C)s 10495 & 25548/2021

reason that the HT connection with consumer Code 8/7135

was not issued to the petitioner-Association, but was in the

name of the builder-Company in respect of three flats, which

was disconnected and there is no challenge to the same;

whereas the members of the petitioner-Association have

been given separate LT connections, for which Bank

Guarantee has been submitted. Thus, for all intents and

purposes, the petitioner does not require, as per the

provisions of the Regulation aforementioned, inspection of

the Electrical Inspector. The said exercise is already over. It

is not a case of recommencement of the supply. In other

words, supplies were different. HT supply was only with

regard to three flats, whereas LT supply is for all the

individual flat owners.

8. On the other hand, Mr.Pramod, learned Standing

Counsel appearing on behalf of the KSEB, submitted that the WP(C)s 10495 & 25548/2021

predicament of the KSEB is writ large as there had been a

tussle between the association and the builder. The builder

had not submitted compliance report nor had strictly

complied with the provisions of Regulation 49, providing the

builder to construct the internal distribution network,

including the service line, transformer, switchgear etc., as

per the scheme approved. The scheme was approved. But

the builder made default in making the actual or minimum

consumption charges of HT connections. It was in that

circumstances, demand as per the provisions of Regulation

40 of the Kerala Electricity Supply Code, 2014 was raised.

LT consumers cannot seek waiver of the arrears of electricity

charges, which has become due from the premises from its

members while implementing Ext.P3 scheme. The HT

connection with consumer Code 8/7135 was dismantled

strictly in terms of the judgment in W.A.No.1673/2019 and WP(C)s 10495 & 25548/2021

connected cases for the purpose of regularisation of the

entire connections as per the Scheme (Ext.P3) approved by

the Electrical Inspector on 22.7.2015, by the individual

owners of the apartment. The arrears due on account of

dismantling of HT connection as on 29.6.2021 are

Rs.17,66,091/- along with interest as on 10.3.2021, which

pertains to defaulted charges payable by the consumers of

the apartment complex. In fact, the petitioner has stepped

into the shoes of the builder, nor is there any change of the

premises or the occupants. The security deposit of

Rs.11,59,300/- with the KSEB by the builder had already

been adjusted. Since the connections are actually

reconnection of the disconnected connections of the

premises, payment of all dues have to be paid by the

consumer. All these circumstances justify the demand.

Sri.Pramod also submitted that even though the arrears WP(C)s 10495 & 25548/2021

were due since long, no delay can be attributed to the KSEB

for raising the demand for the reason that owing to the

Covid pandemic and subsequent stay orders granted by

various courts, the demand was not raised.

9. In rebuttal, learned counsel appearing on behalf of

the petitioner submitted that even though the arrears are

with effect from 2015, but after adjusting the deposit, the

actual arrears are with effect from 2019. If at all the KSEB

has any grievance, they could have raised this point in Writ

Appeal, which came to be decided only on 29.1.2021.

10. I have heard the learned counsel for the parties.

11. From the operative part of the judgment of this

Court dated 29.1.2021 rendered in W.A.No.1673/2019 and

connected cases, direction was issued to the KSEB to

approve the Scheme which has actually been approved on

the basis of the report dated 22.7.2016 of the Chief WP(C)s 10495 & 25548/2021

Electrical Inspector. Petitioner has deposited the required

charges for energisation of the electric connections. The HT

connection issued in favour of the builder was dismantled.

Now, the question which arises is "whether the demand of

the KSEB for claiming the arrears from the petitioner is

justified or is in accordance with the provisions of the Act

and the Regulations". On perusal of the sub-Regulation (3)

of Regulation 40, it is clear that the licensee is empowered

to claim the arrears by resorting to a legal remedy and till

realisation of the same, while releasing the connection to the

other occupiers of the building, for protecting the interest, it

can always ask to furnish guarantee. The petitioner has

already submitted a Guarantee in terms of the

aforementioned Regulation. The contents of the e-mail

dated 8.11.2021 [Ext.P7(b) in the second writ petition]

reveals that the KSEB has already submitted a claim before WP(C)s 10495 & 25548/2021

the Resolution Professional appointed for managing the

affairs of the Company which is under insolvency

proceedings before the competent court. Thus, for all

intents and purposes, respondents have already taken the

steps to recover the arrears and the period of three years

shall be reckoned from the date on which such steps were

taken. Till such time, the interest of the KSEB is to be

protected. As per the proviso to the aforementioned sub-

Regulation (3), even in the absence of any settlement of the

liabilities, the licensee is mandatorily required to release the

Bank Guarantee after the expiry of the three years. Thus, in

my view, the demand of the arrears raised by the

respondents from the petitioner is not sustainable and

hereby ordered to be kept in abeyance till the expiry of the

three years, which is to be reckoned from the date of claim

before the Resolution Professional. WP(C)s 10495 & 25548/2021

12. As far as the claim with regard to energisation of

the lift is concerned, the same was operational at the time

when the LT connections were issued. An application for

renewal has already been submitted. But, the respondents

are again pressing for the arrears. In view of the findings

hereinabove, once the interest of the respondents has been

protected, they are directed to renew the licence for

energisation of the lift/escalator within a period of one

month, without asking for the report of the Electrical

Inspector as the provisions of Regulation 43 of the Central

Electricity Authority (Measures relating to Safety and

Electricity Supply) Regulations, 2010, do not envisage any

situation for the inspection of the Electrical Inspector being

not the case of re-energisation of the connection, as the

dismandling was of only HT connection, which still remains

disconnected. Regulation 43 is extracted hereinbelow: WP(C)s 10495 & 25548/2021

"43. Approval by Electrical Inspector. -

(1) Voltage above which electrical installations will be required to be inspected by the Electrical Inspector before commencement of supply or recommencement after shutdown for six months and above shall be as per the notification to be issued by the Appropriate Government, under clause (x) of sub-section (2) of section 176, and sub-section (1) of section 162 of the Act.

(2) Before making an application to the Electrical Inspector for permission to commence or recommence supply after an installation has been disconnected for six months and above at voltage exceeding 650 V to any person, the supplier shall ensure that electric supply lines or apparatus of voltage exceeding 650 V belonging to him are placed in position, properly joined and duly completed and examined and the supply of electricity shall not be commenced by the supplier for installations of voltage needing inspection under these regulations unless the provisions of regulations 12 to 29, 33 to 35, 44 to 51 and 55 to 77 have been complied with and the approval in writing of the Electrical Inspector has been obtained by him: Provided that the supplier may energise the aforesaid electric supply lines or apparatus for the purpose of tests specified in regulation 46.

(3) The owner of any installation of voltage exceeding 650 V shall, before making WP(C)s 10495 & 25548/2021

application to the Electrical Inspector for approval ofhis installation or additions thereto, test every circuit of voltage exceeding 650 V or additions thereto, other than an overhead line, and satisfy himself that they withstand the application of the testing voltage set out in sub-regulation (1) of regulation 46 and shall duly record the results of such tests and forward them to the Electrical Inspector:

Provided that an Electrical lnspector may direct such owner to carry out such tests as he deems necessary or accept the manufacturer's certified tests in respect of any particular apparatus in place of the tests required by this regulation.

(4) The owner of any installation of voltage exceeding 650 V who makes any addition or alteration to his installation shall not connect to the supply his apparatus or electric supply lines, comprising the said alterations or additions unless and until such alteration or addition has been approved in writing by the Electrical Inspector."

For renewal of the licence, the inspection of the Electrical

Inspector may be required. The Electrical Inspector, cannot,

in view of the Government Order dated 27.3.2019 insist for

the payment being the employee of the Government. KSEB WP(C)s 10495 & 25548/2021

will forward the request of the petitioner to the Electrical

Inspector for inspection of the area where the lift is installed

and submit status report. After submission of the report

within a period of 15 days from the communication sent by

the petitioner, within another 30 days, the respondents will

renew the licence for the lift by overcoming deficiency, if

any.

13. This Court is also takes note of the fact that any

compliance of the Scheme which remains pending be

completed as expeditiously as possible, subject to the

satisfaction of the Rules and Regulations.

The Writ Petitions are disposed of as above.

Sd/-

AMIT RAWAL JUDGE jg WP(C)s 10495 & 25548/2021

APPENDIX OF WP(C) 25548/2021

PETITIONER EXHIBITS Exhibit P1 TRUE COPY OF THE INTERIM ORDERS DATED 23/11/2017 IN WPC 15370/17.

Exhibit P1 (A) TRUE COPY OF THE INTERIM ORDERS DATED 7/12//2017 IN WPC 23730/2017.

Exhibit P1 (B) TRUE COPY OF THE INTERIM ORDERS DATED 16/1/2018 IN WPC 23730/2017.

Exhibit P1 (C) TRUE COPY OF THE INTERIM ORDERS DATED 5/2/2018 IN WPC 23730/2017.

Exhibit P1 (D) TRUE COPY OF THE INTERIM ORDERS DATED 5/7/2018 IN WPC 23730/2017.

Exhibit P2 TRUE COPY OF THE COMMON JUDGMENT DATED 20/2/2020 IN WPC NO 21563/18 PC 23739/17, WPC 15370/17.

Exhibit P3 TRUE COPY OF THE ELECTRICAL SCHEME APPROVED BY THE 4TH RESPONDENT ON 22.07.2015.

Exhibit P4 TRUE COPY OF THE JUDGMENT IN W.A. NOS.

1673 OF 2019 , 1743 OF 2019 1817 OF 2019 ALONG WITH ANOTHER W.A. 20 OF 2020.

Exhibit P5 TRUE COPY OF THE COMMUNICATION NO. B3-

34445/19/EIE DATED 10/3/2021 SIGNED BY THE ELECTRICAL INSPECTOR.

Exhibit P6 TRUE COPY OF THE COMPANY MASTER DATED OF M/S. ATLAS GOLD TOWN SHIP (INDIA) PVT. LTD.

Exhibit P7 TRUE COPY OF THE ORDER DATED 19.1.2019 PASSED BY NCLT IN TIBA/19/KOB/19.

Exhibit P7 (A) TRUE COPY OF THE ORDER DATED 30/7/2021 IN I.A/82/KOB/2020.

Exhibit P7 (B) TRUE COPY OF THE EMAIL DATED 8/11/201 ISSUED BY THE RESOLUTION PROFESSIONAL MR. JASIN.

Exhibit P8 TRUE COPY OF THE EMAIL DATED 8/11/2021 WP(C)s 10495 & 25548/2021

ISSUED COMMUNICATION NO. ECP/T4/HT/ATLAS GOLD/2021-22/17 DATED 05.04.2021.

Exhibit P9 TRUE COPY OF THE INTERIM ORDER DATED 27/5/2021 IN WPC NO. 10495/21.

Exhibit P10 TRUE COPY OF THE ORDER BEARING NO. B.O.

(FTD) NO. 822/2021 (D) (D &IT) /D-

2/GOVT. /SC/19-20/0019/2021-22 DATED 03/11/2021 ISSUED BY THE COMPANY SECRETARY (IN-CHARGE) BY THE ORDERS OF THE FULL TIME DIRECTORS OF THE KSEBL.

Exhibit P11 TRUE COPY OF THE ORDER DATED 09/11/2021 ISSUED BY THE 2ND RESPONDENT TO THE SECRETARY OF THE PETITIONER ASSOCIATION BEARING NO. ECP/T4/HT-ACP APARTMENT/2021-22/2765.

Exhibit P12 TRUE COPY OF THE REPLY LETTER ISSUED BY THE SECRETARY OF THE PETITIONER ASSOCIATION TO THE 2ND RESPONDENT DATED 08.03.2021.

Exhibit P13 TRUE COPY OF THE COMMUNICATION DATED 25/2/2021 ISSUED BY THE SPECIAL OFFICER, (REVENUE) UNDER THE IST RESPONDENT.

WP(C)s 10495 & 25548/2021

APPENDIX OF WP(C) 10495/2021

PETITIONER EXHIBITS EXHIBIT P1 TRUE COPY OF THE INTERIM ORDER DATED 23/11/2017 IN WPC 15370/17.

EXHIBIT P1A TRUE COPY OF THE INTERIM ORDER DATED 7/12/2017 IN WPC 23730/2017.

EXHIBIT P1B TRUE COPY OF THE INTERIM ORDER DATED 16/1/2018 IN WPC 23730/2017.

EXHIBIT P1C TRUE COPY OF THE INTERIM ORDER DATED 5/2/2018 IN WPC 23730/2017.

EXHIBIT P1D TRUE COPY OF THE INTERIM ORDER DATED 5/7/2018 IN WPC 23730/2017.

EXHIBIT P2 TRUE COPY OF THE COMMON JUDGMENT DATED 20/2/2020 IN WPC 23730/17.

EXHIBIT P3 TRUE COPY OF THE ELECTRICAL SCHEME APPROVED BY THE 4TH RESPONDENT ON 22/07/2015.

EXHIBIT P4 TRUE COPY OF THE COMMON JUDGMENT IN W.A.NOS.1673 OF 2019, 1743 OF 2019, 1817 OF 2019 ALONG WITH ANOTHER W.A.240 OF 2020.

EXHIBIT P5 TRUE COPY OF THE COMMUNICATION NO.B3-

34445/19/EIE DATED 10/3/2021 SIGNED BY THE ELECTRICAL INSPECTOR.

EXHIBIT P6 TRUE COPY OF THE COMPANY MASTER DATA OF M/S.ATLAS GOLD TOWNSHIP (INDIA) PVT.LTD. EXHIBIT P7 TRUE COPY OF THE ORDER DATED 19/11/2019 PASSED BY NCLT IN TIBA/19/KOB/19.

EXHIBIT P7A TRUE COPY OF THE ORDER DATED 30/7/2020 IN I.A./82/KOB/2020.

EXHIBIT P8 TRUE COPY OF THE COMMUNICATION NO.ECP/T4/HT/ATLAS GOLD/2021-22/17 DATED 05/04/2021.

EXHIBIT P9 TRUE COPY OF THE EMAILS DATED 5.5.2017 ADDRESSED TO R2 WP(C)s 10495 & 25548/2021

EXHIBIT P10 TRUE COPY OF EMAILS DATED 25.1.2021 ADDRESSED TO R2 EXHIBIT P11 TRUE COPY OF EMAILS DATED 10.2.2021 ADDRESSED TO R2 EXHIBIT P12 TRUE COPY OF LETTER DATED 8.3.2021 ADDRESSED TO R2.

EXHIBIT P13 TRUE COPY OF COMMUNICATION DATED 27.2.2021 Exhibit P14 THE TRUE COPY OF THE BANK GUARANTEE DATED 15.06.2022 AND TYPED COPY.

Exhibit P15 TRUE COPY OF THE RENEWAL APPLICATION DATED 24.02.2021.

Exhibit P16 THE TRUE COPY OF THE DEMAND NOTICE DATED 27/7/2022 ISSUED BY THE 4TH RESPONDENT ADDRESSED TO THE 5TH RESPONDENT AND TYPED COPY.

Exhibit P17 TRUE COPY OF THE REPLY DATED 03.08.2022 AND TYPED COPY.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter