Citation : 2022 Latest Caselaw 4598 Ker
Judgement Date : 22 April, 2022
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
FRIDAY, THE 22ND DAY OF APRIL 2022 / 2ND VAISAKHA, 1944
WP(C) NO. 23116 OF 2021
PETITIONER:
ANWAR.P
AGED 43 YEARS
S/O.MOOSA, PWD CONTRACTOR,
PATTASSERI HOUSE, VALIYORA.P.O,
MALAPPURAM DISTRICT-676304.
BY ADVS.
PUSHPARAJAN KODOTH
K.JAYESH MOHANKUMAR
VANDANA MENON
VIMAL VIJAY
RESPONDENTS:
1 CALICUT UNIVERSITY
REPRESENTED BY THE REGISTRAR,
THENHIPPALAM, MALAPPURAM DISTRICT-673635.
2 THE EXECUTIVE ENGINEER (CIVIL),
ENGINEERING DEPARTMENT, UNIVERSITY OF CALICUT,
THENHIPPALAM, MALAPPURAM DISTRICT-673635.
3 ASSISTANT EXECUTIVE ENGINEER(CIVIL),
ENGINEERING DEPARTMENT, UNIVERSITY OF CALICUT,
THENHIPPALAM, MALAPPURAM DISTRICT-673635.
4 THE ASSISTANT ENGINEER(CIVIL),
ENGINEERING DEPARTMENT, UNIVERSITY OF CALICUT,
THENHIPPALAM, MALAPPURAM DISTRICT-673635.
BY ADV SRI.P.C.SASIDHARAN, SC, CALICUT
UNIVERSITY
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR
ADMISSION ON 22.04.2022, THE COURT ON THE SAME DAY
DELIVERED THE FOLLOWING:
W.P.(C) No.23116/2021
:2:
N. NAGARESH, J.
`````````````````````````````````````````````````````````````
W.P.(C) No.23116 of 2021
`````````````````````````````````````````````````````````````
Dated this the 22nd day of April, 2022
JUDGMENT
~~~~~~~~~
Petitioner, who is an A Class Contractor
undertaking works for PWD, has approached this Court
seeking to quash Exts.P8 and P11 and to direct respondents
1 and 2 to disburse the security deposit to the petitioner by
executing Ext.P3 agreement. The petitioner has also sought
for certain incidental reliefs.
2. The petitioner was awarded with the work of
Construction of Ring Road connecting newly constructed Life
Science and Mathematics Department by the University of
Calicut. Ext.P3 agreement was executed on 27.02.2020.
The estimate amount was ₹23,35,925.67. The petitioner
states that though Ext.P2 agreement was executed and work W.P.(C) No.23116/2021
had to be completed within six months, the respondents did
not handover the work site to the petitioner. The petitioner
submitted Ext.P5 representation dated 09.03.2020, Ext.P6
representation dated 19.03.2020 and Ext.P7 registered letter
dated 13.07.2021 to the respondents. In spite of the
representations and letters, work site was not handed over.
3. To the surprise of the petitioner, the respondents
passed Ext.P8 order dated 22.07.2021 directing the
petitioner to start work within three days failing which the
security deposit was to be forfeited and the contract was to
be cancelled at the risk and cost of the petitioner. The
petitioner states that the said order was passed without
considering Exts.P6 and P7 representations. To Ext.P8, the
petitioner sent Ext.P9 representation dated 10.08.2021
pointing out that the site has not been handed over to the
petitioner in spite of his request.
4. The respondents, however, passed Ext.P11 order
dated 10.09.2021 cancelling Ext.P3 agreement at the risk
and cost of the petitioner. An amount of ₹1,16,800/- by way W.P.(C) No.23116/2021
of security deposit was forfeited. The petitioner states that
Ext.P11 order is against Clause 22 of Ext.P2 and paragraphs
14.3, 14.4, 14.5 and 2102.1 of the Kerala Public Works
Department Manual.
5. The learned counsel for the petitioner argued that
Exts.P8 and P11 were passed without hearing the petitioner,
in violation of the principles of natural justice. The
respondents have not complied with Clause 22 of Ext.P2 and
paragraphs 14.3, 14.4, 14.5 and 2102.1 of the PWD Manual.
6. The respondents failed to handover the site. The
petitioner had submitted Exts.P5 and P6 representations
requiring to handover the same. No action was taken
thereon. Now, the contract has been terminated at the risk
and cost of the petitioner. For no fault of the petitioner, he is
being penalised, contended the counsel for the petitioner.
7. The 1st respondent-University resisted the writ
petition. The 1st respondent stated that Ext.P5 and P6 are
fraudulent documents which were never received by the
University. The site was handed over to the petitioner within W.P.(C) No.23116/2021
time in terms of the agreement. The site was available free
of any hindrance or encumbrance, since it is only a road
within the University. The petitioner did not turn up to execute
the work.
8. The Standing Counsel for the respondents further
argued that as per paragraph 2116.1 of the Kerala PWD
Manual, the Agreement Authority has the power to cancel the
contract and arrange the work otherwise, in the event of
default by the contractor. The damages and penalties and
can be recovered from the contractor.
9. I have heard the counsel for the petitioner and the
Standing Counsel for the respondents.
10. The case put forward by the petitioner is that as
per paragraph 14.3 of the PWD Manual, the contractor has
to take over charge of the site by signing the
acknowledgment form and commence the work within ten
days from the date of execution of agreement. As per
paragraph 2102.1, after executing the agreement, the
contractor or the authorised agent shall take over the site W.P.(C) No.23116/2021
from the Assistant Engineer within ten days and commence
the work immediately. If the contractor does not turn up, the
acknowledgment form for handing over of the site duly
signed by the Assistant Engineer shall be sent to the
contractor through registered post and it shall be deemed
that the contractor has taken over the site from the date of
posting. In the case of the petitioner, no such
communication has been sent to the petitioner through
registered post. Therefore, termination of the work with risk
and cost of the petitioner is illegal and unsustainable.
11. Admittedly, the petitioner had executed Ext.P3
agreement on 27.02.2020. Thereafter, no work was carried
out. The petitioner claims that he has sent Exts.P5 and P6
representations 09.03.2020 to the Executive Engineer. The
respondents would dispute this. According to the
respondents, the Executive Engineer has not received
Exts.P5 and P6 representations and those are concocted
documents.
W.P.(C) No.23116/2021
12. The petitioner states that he had sent Ext.P7 letter
by registered post. However, the postal acknowledgment
receipt and the delivery slip of Ext.P7 letter issued by the
postal authorities, copies of which were made available to
the Court, would show that Ext.P7 registered letter was
delivered to the Executive Engineer only on 26.07.2021, after
the Executive Engineer directed the petitioner to start the
work within three days, as per Ext.P8.
13. It has to be further noted that the petitioner has
not submitted any application for extension of time to
complete the work, before the expiry of the agreement
period. As per paragraph 2112 of the PWD Manual, even if
the failure of the contractor to complete the work on the
stipulated date is due to any departmental delays, the
contractor has to apply for extension of time through the
Assistant Engineer before the expiry of the period of
completion. The petitioner has not submitted such an
application.
W.P.(C) No.23116/2021
In the facts and circumstances of the case, this
Court is not inclined to interfere with the impugned orders at
Ext.P8 and P11 passed by the respondents. The writ petition
fails and it is accordingly dismissed.
Sd/-
N. NAGARESH, JUDGE aks/18.04.2022 W.P.(C) No.23116/2021
APPENDIX OF WP(C) 23116/2021
PETITIONER'S EXHIBITS
Exhibit P1 TRUE COPY OF REGISTRATION GIVEN TO THE PETITIONER BY THE SUPERINTENDENT ENGINEER, PWD BUILDINGS, NORTH CIRCLE, KOZHIKODE-673001, DATED 12.10.2012 AS AN A CLASS CONTRACTOR.
Exhibit P2 TRUE COPY OF NOTICE INVITING TENDER
FOR THE CONSTRUCTION OF RING ROAD
CONNECTING NEWLY CONSTRUCTED LIFE
SCIENCE AND MATHEMATICS DEPARTMENTS ISSUED BY THE 2ND RESPONDENT DATED 17.02.2020 (36 PAGES) Exhibit P3 TRUE COPY OF AGREEMENT NO.72/2019-20 EXECUTED BY THE PETITIONER AND THE RESPONDENTS DATED 27.02.2020 (5 PAGES) Exhibit P4 TRUE COPY OF APPENDIX 2100 A REFERRED IN PARA 2102.1 OF THE KERALA PUBLIC WORKS DEPARTMENT MANUAL.
Exhibit P5 TRUE COPY OF REPRESENTATION SUBMITTED BY THE PETITIONER TO 2ND RESPONDENT DT.09.03.2020.
Exhibit P6 TRUE COPY OF REPRESENTATION SUBMITTED BY THE PETITIONER TO 2ND RESPONDENT DT.19.03.2020.
Exhibit P7 TRUE COPY OF REGISTERED LETTER SENT BY PETITIONER TO THE 2ND RESPONDENT DT.13.07.2021.
Exhibit P8 TRUE COPY OF THE ORDER PASSED BY THE 2ND RESPONDENT DATED 22.07.2021.
Exhibit P9 TRUE COPY OF THE REPRESENTATION SUBMITTED BY THE PETITIONER TO THE 2ND RESPONDENT DATED 10.08.2021.
Exhibit P10 TRUE COPY OF THE POSTAL ACKNOWLEDGEMENT ISSUED BY THE POSTAL DEPARTMENT DATED 11.08.2021.
Exhibit P11 TRUE COPY OF THE ORDER ISSUED BY THE 2ND RESPONDENT DATED 10.09.2021.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!