Citation : 2021 Latest Caselaw 19712 Ker
Judgement Date : 17 September, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE BECHU KURIAN THOMAS
FRIDAY, THE 17TH DAY OF SEPTEMBER 2021 / 26TH BHADRA, 1943
OP (DRT) NO. 110 OF 2021
AGAINST THE ORDER/JUDGMENT IN OA 1/2001 OF DEBT RECOVERY TRIBUNAL,
ERNAKULAM, ERNAKULAM
PETITIONER/1ST CERTIFICATE DEBTOR :
CHAYA INDUSTRIES LTD
HAVING ITS REGISTERED OFFICE AT NEW INDUSTRIAL DEVELOPMENT
AREA, KANJIKODE, PALAKKAD 678 621, KERALA,
REP.BY ITS MANAGING DIRECTOR,
MR. THIRUNAVUKKARASU RAGUNATHAN.
BY ADV P.JINISH PAUL
RESPONDENTS/CERTIFICATE HOLDER & CERTIFICATE DEBTORS 2&3:
1 RECOVERY OFFICER, DEBT RECOVERY TRIBUNAL-1
PANAMBILLY NAGAR, ERNAKULAM 682 036
2 STRESSED ASSETS STABILIZATION FUND
5TH FLOOR, IDBI TOWER, WTC COMPLEX, CUFFE PARADE,
MUMBAI 400 005, REP.BY ITS DEPUTY GENERAL MANAGER.
3 T.RAGUNATHAN, 17, EAST ROAD,
C.I.T. NAGAR WEST, CHENNAI 600 035
4 T.MANOHAR, 17, EAST ROAD,
C.I.T. NAGAR WEST, CHENNAI 600 035
5 YESSEM STEEL PRODUCTS (KANJIKODE) PVT LTD.
KELATH PARAMBIL, KARAKAD P.O.,
KONDURKARA, KALLADIPATTA VIA, PALAKKAD 679 313.
REP.BY ITS MANAGING DIRECTOR.
THIS OP (DEBT RECOVERY TRIBUNAL) HAVING COME UP FOR ADMISSION ON 17.09.2021,
THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
OP (DRT) NO. 110 OF 2021
2
BECHU KURIAN THOMAS, J
===========================
O.P(DRT) No.110 of 2021
---------------------------------
Dated this the 17 th day of September, 2021
JUDGMENT
The learned counsel for the petitioner submitted that
the petition has become infructuous.
2. Accordingly, the original petition is dismissed as
infructuous.
Sd/-
BECHU KURIAN THOMAS, JUDGE AMV/18/09//2021
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!