Citation : 2021 Latest Caselaw 18725 Ker
Judgement Date : 9 September, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE DEVAN RAMACHANDRAN
THURSDAY, THE 9TH DAY OF SEPTEMBER 2021 / 18TH BHADRA, 1943
WP(C) NO. 28853 OF 2020
PETITIONER:
M.K.RADHA, AGED 71 YEARS, W/O.LATE M.I.KESEAVAN,
MODENPLACKAL HOUSE, METHOTTY, KOOVAKANDAM P.O.,
IDUKKI DISTRICT-685 588.
BY ADVS.
S.NIDHEESH
SMT.JISHY P.S.
SHRI.DHANIL KUMAR.
RESPONDENTS:
1 TAHASILDAR (LR), THODUPUZHA TALUK,
IDUKKI DISTRICT-685 584.
2 TALUK SURVEYOR, THODUPUZHA TALUK,
IDUKKI DISTRICT-685 584.
3 DISTRICT SURVEY SUPERINTENDENT,
IDUKKI DISTRICT-685 566.
4 DIVISIONAL FOREST OFFICER,
KOTHAMANGALAM, IDUKKI DISTRICT-686 666.
5 DISTRICT TRIBAL WELFARE OFFICER,
PROJECT OFFICE, ITDP, IDUKKI, THODUPUZHA P.O.,
IDUKKI DISTRICT-685 584.
6 DISTRICT COLLECTOR, IDUKKI DISTRICT,
PIN-685 603.
SHRI.T.P.SAJAN - SPL GP
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
09.09.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WPC 28853/20
2
JUDGMENT
The petitioner says that she is the widow of
late M.I.Kesavan and that both of them belong to a
Scheduled Tribe community by name "Mala Arayan".
The petitioner says that she and her husband
possessed property in the Tribal Settlement Area
and that this is evident from Exts.P1 and P2. She
says that, however, since the property has not
been properly surveyed or demarcated, she is
finding it difficult to put it to profitable use;
and therefore, that she preferred Ext.P3
application before the 1st respondent - Tahsildar
(LR), seeking that necessary action for such
purpose be initiated without any delay. The
petitioner says that, however, her application has
not been considered by the 1st respondent, thus
constraining her to approach this Court through
this writ petition.
2. I have heard Shri.Dhanil Kumar, learned WPC 28853/20
counsel for the petitioner and Shri.T.P.Sajan,
learned Special Government Pleader appearing for
the respondents.
3. Interestingly, Shri.T.P.Sajan conceded that
no action on Ext.P3 has been yet completed; but
added that the 1st respondent - Tahsildar has
already instructed the Taluk Surveyor to initiate
appropriate action. He then submitted that on a
preliminary enquiry, it has been found that there
is a road through the petitioner's property and
thus prayed that this Court allow the Tahsildar to
take the same into account, while completing the
proceedings based on Ext.P3.
4. In reply, Sri.Dhanil Kumar - learned
counsel for the petitioner, submitted that the
afore assertion of Sri.T.P.Sajan is not merely
untenable but also baseless. He submitted that
since Ext.P1 clearly shows that petitioner has
been given permission to occupy forest land under WPC 28853/20
the provisions of the applicable law, no road
could have been constructed therein and that if
there is any such, it can only be construed that
same has been constructed in complete
contravention of law.
5. When I consider the afore rival submissions, it cannot be disputed that the petitioner has a right to have the property
covered by Exts.P1 and P2 properly surveyed and
demarcated. In fact, this is even conceded by
Sri.T.P.Sajan. Hence, the only other question is
whether there is a road through the property and
whether the petitioner had agreed to the
construction of such. This is a question of fact,
which will have to be considered by the competent
Authority in terms of law and this Court cannot
speak affirmatively on it, while acting under
Article 226 of the Constitution of India.
In the afore circumstances, I direct the 2nd
respondent to complete the survey of the property WPC 28853/20
of the petitioner covered by Exts.P1 and P2, after
following due procedure, as expeditiously as is
possible, but not later than three months from the
date of receipt of a copy of this judgment.
Once the survey is completed and the sketch is
prepared by the Taluk Surveyor, he will present it
before the 1st respondent-Tahsildar, who will
complete the proceedings thereon; during which he
will verify if there is a road through the
property in question and if no, it has been
constructed with the permission of the petitioner.
Needless to say, if the road has been
constructed without the permission of the
petitioner, then the 1st respondent-Tahsildar will
also specifically consider whether same should be
allowed to continue, particularly under the ambit
of the Scheduled Tribes and Other Traditional
Forest Dwellers (Recognition of Forest Rights)
Rules, 2007 and then take necessary consequential
action as is required in law.
WPC 28853/20
While completing the afore exercise, the 1 st
respondent-Tahsildar will hear the petitioner, the
competent official of the Forest Department, the
authorised officer of the Panchayat, as also any
other interested person, as he may deem fit.
This writ petition is thus ordered.
Sd/-
MC/RR DEVAN RAMACHANDRAN
JUDGE
WPC 28853/20
APPENDIX OF WP(C) 28853/2020
PETITIONER EXHIBITS
EXHIBIT P1 TRUE COPY OF THE TITLE FOR FOREST LAND
UNDER OCCUPATION DATED 11.08.2011.
EXHIBIT P2 TRUE COPY OF SURVEY MAP DATED NIL.
EXHIBIT P3 TRUE COPY OF THE APPLICATION BEFORE THE 1ST RESPONDENT DATED 17.12.2020.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!