Citation : 2021 Latest Caselaw 22452 Ker
Judgement Date : 9 November, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE BECHU KURIAN THOMAS
TUESDAY, THE 9TH DAY OF NOVEMBER 2021 / 18TH KARTHIKA, 1943
WP(C) NO. 20526 OF 2021
PETITIONER :
CHICAGO CONSTRUCTIONS INTERNATIONAL (P) LTD.,
CHITHIRA LANE, KOCHAR ROAD,
SASTHAMANGALAM, THIRUVANANTHAPURAM-695010,
REPRESENTED BY ITS MANAGING DIRECTOR, MOHANAKUMAR.S.
BY ADVS.
K.P.PRADEEP
HAREESH M.R.
RASMI NAIR T.
T.T.BIJU
T.THASMI
M.J.ANOOPA
SWATHI GUPTHA
RESPONDENTS :
1 STATE OF KERALA
REPRESENTED BY THE SECRETARY TO GOVERNMENT,
DEPARTMENT TAXES,
GOVERNMENT SECRETARIAT,
THIRUVANANTHAPURAM-695001.
2 KERALA WATER AUTHORITY,
JALABHAVAN, VELLAYAMBALAM,
THIRUVANANTHAPURAM-695033,
REPRESENTED BY ITS MANAGING DIRECTOR.
3 MANAGING DIRECTOR,
KERALA WATER AUTHORITY,JALABHAVAN,
VELLAYAMBALAM,
THIRUVANANTHAPURAM-695033.
BY SENIOR GOVT.PLEADER SRI.JUSTIN JACOB
BY ADV.BENJAMIN PAUL, SC
BY ADV BIJILY JOSEPH
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
09.11.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C) NO. 20526 OF 2021
2
BECHU KURIAN THOMAS, J.
=-=-=-=-=-=-=-=-=-=-=-=-=-=
W.P.(C) No.20526 of 2021
=-=-=-=-=-=-=-=-=-=-=-=-=-=
Dated this the 9th day of November, 2021
JUDGMENT
Petitioner is a works contractor, who had executed
contract works for the Kerala Water Authority during the period
2015-16 and 2016-17. The claims of the contractors for refund of
GST paid by them after coming into force of the Goods and Service
Tax Act, 2017 were considered by the Kerala Water Authority and by
a General Circular No.2/2017 dated 10.02.2017, the Kerala Water
Authority decided to grant the benefit of GST paid by the contractors
on production of proof of receipt of payment.
2. Petitioner claims to have paid the GST, due on the
works carried out by them on behalf of the Water Authority and has
sought refund. Ext.P7 application was filed by them along with proof
of payment of GST and have claimed the amounts due to them.
However, according to the petitioner, no decision has been taken by
the respondents in spite of repeated reminders.
3. Having regard to the circumstances, there will be a
direction to respondents 2 and 3 to consider Ext.P7 application filed WP(C) NO. 20526 OF 2021
by the petitioner and pass appropriate orders, as expeditiously as
possible, at any rate, within a period of one month from the date of
receipt of a copy of this judgment. If the petitioner is found eligible
to be refunded the GST paid by them, the respondents 2 and 3 shall
make the payment so due, within an outer period of two months
from the date of such decision.
The writ petition is disposed of as above.
Sd/-
BECHU KURIAN THOMAS, JUDGE RKM WP(C) NO. 20526 OF 2021
APPENDIX OF WP(C) 20526/2021
PETITIONER'S EXHIBITS :
Exhibit P1 TRUE COPY OF THE WORK ORDER NO PHC/D3-
9722/13/CIVIL/NVOL.2 DATED 01-10-2015 ISSUED BY THE KERALA WATER AUTHORITY
Exhibit P1(A) TRUE COPY OF THE RELEVANT PAGES OF THE AGREEMENT DATED 17-10-2015 EXECUTED BY THE PETITIONER WITH KERALA WATER AUTHORITY
Exhibit P2 TRUE COPY OF THE SELECTION NOTICE NO.PHC D3-4506/14 DATED 09.07.2015 ISSUED BY THE SUPERINTENDING ENGINEERING, KERALA WATER AUTHORITY
Exhibit P2(A) TRUE COPY OF THE SELECTION NOTICE NO.PHC/D2/968 (A)/2014-15 DATED 30-07-2015 ISSUED BY THE SUPERINTENDING ENGINEERING, KERALA WATER AUTHORITY
Exhibit P2(B) TRUE COPY OF THE SELECTION NOTICE NO.PHC/D3-3940/14 DATED 26-09-2015 ISSUED BY THE SUPERINTENDING ENGINEERING, KERALA WATER AUTHORITY
Exhibit P2(C) TRUE COPY OF THE SELECTION NOTICE NO.PHC/D2/968(B)/2014 DATED 30.09.2015 ISSUED BY THE SUPERINTENDING ENGINEERING, KERALA WATER AUTHORITY.
Exhibit P2(D) TRUE COPY OF THE WORK ORDER NO.KWA/PHC/TSR/D3-4609/14 DATED 29-02-2016 ISSUED BY THE SUPERINTENDING ENGINEERING, KERALA WATER AUTHORITY
Exhibit P2(E) TRUE COPY OF THE WORK ORDER NO.KWA/PHC/ALP/D1-1530/15 DATED 03.03.2016 ISUSED BY THE SUPERINTENDING ENGINEERING, KERALA WATER AUTHORITY WP(C) NO. 20526 OF 2021
Exhibit P2(F) TRUE COPY OF THE WORK ORDER SE/PHC/TVLA/DB/1135/2016 DATED 24-09-2016 ISSUED BY THE SUPERINTENDING ENGINEER, KERALA WATER AUTHORITY
Exhibit P2(G) TRUE COPY OF THE WORK ORDER NO.KWA/PHC/PKD/2014/15 DATED 14.08.2017 ISSUED BY THE SUPERINTENDING ENGINEERING, KERALA WATER AUTHORITY
Exhibit P3 TRUE COPY OF THE RELEVANT PAGES OF THE AGREEMENT NO 7/2015-16/SE/PHC/ALP DATED 3-3-2016
Exhibit P4 TRUE COPY OF THE GO(P)NO.2/2018/PWD DATED 27-01-2018
Exhibit P5 TRUE COPY OF THE JUDGMENT DATED 17-12-2019 IN WP(C)NO.23298 OF 2019
Exhibit P6 TRUE COPY OF THE ORDER NO.KWA/HO/FM/MABARD/F2-200/2018 DATED 13-03-2020 ISSUED BY THE JOINT MANAGING DIRECTOR, KERALA WATER AUTHORITY
Exhibit P7 TRUE COPY OF THE COMPUTATION STATEMENT OF WORKS CONTRACT INCOME SUBMITTED TO THE 2ND RESPONDENT BY THE PETITIONER.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!