Thursday, 14, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Anish Markose vs The State Of Kerala
2021 Latest Caselaw 22342 Ker

Citation : 2021 Latest Caselaw 22342 Ker
Judgement Date : 9 November, 2021

Kerala High Court
Anish Markose vs The State Of Kerala on 9 November, 2021
         IN THE HIGH COURT OF KERALA AT ERNAKULAM
                            PRESENT
              THE HONOURABLE MR.JUSTICE N.NAGARESH
TUESDAY, THE 9TH DAY OF NOVEMBER 2021 / 18TH KARTHIKA, 1943
                    WP(C) NO. 17381 OF 2021
PETITIONER:

         ANISH MARKOSE,
         AGED 40 YEARS,
         S/O MARKOSE, OMBALAYIL HOUSE,
         KOLENCHERRY, ERNAKULAM DISTRICT-682311,
         AUTHORIZED SIGNATORY OF ANTECH-PRL(JV)
         (A JOINT VENTURE ASSOCIATION ANTECH CONSTRUCTION
         COMPANY AND PRL PROJECT AND INFRASTRUCTURE LTD.),
         OMBALAYIL, KOLENCHERRY, ERNAKULAM.

         BY ADVS.
         SRI.SAJEEV KUMAR K.GOPAL
         SRI.ASWATHY BABU


RESPONDENTS:

    1    THE STATE OF KERALA,
         REPRESENTED BY THE CHIEF SECRETARY TO THE
         GOVERNMENT,
         GOVERNMENT SECRETARIAT,
         THIRUVANANTHAPURAM-695001.

    2    THE SECRETARY TO THE GOVERNMENT,
         PUBLIC WORKS DEPARTMENT, GOVERNMENT SECRETARIAT,
         THIRUVANANTHAPURAM-695001.

    3    THE KERALA STATE TRANSPORT PROJECT,
         TC 11/339, SREEBALA BUILDING,
         KESTON ROAD, NANDANCODE, KOWDIAR.P.O,
         THIRUVANANTHAPURAM-695003,
         REPRESENTED BY THE PROJECT DIRECTOR.

    4    THE CHIEF ENGINEER,
         KERALA STATE TRANSPORT PROJECT,
         TC 11/ 339, SREEBALA BUILDING KESTON ROAD,
         NANDANCODE, KOWDIAR.P.O,
         THIRUVANANTHAPURAM-695003.
 WP(C) No.17381/2021
                            :2 :


     5     THE PROJECT DIRECTOR
           KERALA STATE TRANSPORT PROJECT, TC 11/339,
           SREEBALA BUILDING, KESTON ROAD,
           NANDANCODE, KOWDIAR.P.O, THIRUVANANTHAPURAM-
           695003.
     6     M/S MARY MATHA INFRASTRUCTURE PVT.LTD,
           MARY MATHA SQUARE, ARAKUZHA ROAD,
           MUVATTUPUZHA.P.O, ERNAKULAM DISTRICT-686661.

           BY ADVS.
           P.SHANES METHAR FOR R6
           SRI.K.V.MANOJKUMAR, SR. GOVT. PLEADER

     THIS WRIT PETITION (CIVIL) HAVING COME UP            FOR
ADMISSION ON 09.11.2021, THE COURT ON THE SAME            DAY
DELIVERED THE FOLLOWING:
 WP(C) No.17381/2021
                                :3 :




                          JUDGMENT

~~~~~~~~~

Dated this the 9th day of November, 2021

The petitioner, who is authorised signatory of

ANTECH-PRL(JV), Ernakulam, has approached this Court

seeking to direct respondents 2 to 5 to forthwith publish the

pre-qualification evaluation of the bidders with respect to the

work, namely Rehabilitation and Upgradation of Vadayar -

Chanthapalam - Mulakkulam Road and Vadayar

Kallattippalam - Muttuchira Road in Kottayam District vide Bid

No.KSTP/KFW/RKI/PKG-IV/Work/Rd-2 forthwith. The

petitioner has also sought to direct the respondents not to

award the said work to the 6 th respondent who is not

pre-qualified for the work.

2. The 3rd respondent-Kerala State Transport Project

invited bid for the work of Rehabilitation and Upgradation of

Vadayar - Chanthapalam - Mulakkulam Road and Vadayar

Kallattippalam - Muttuchira Road in Kottayam District vide Bid WP(C) No.17381/2021

No.KSTP/KFW/RKI/PKG-IV/Work/Rd-2, for a length of 22.476

Km. The petitioner satisfied Clause 4.2(b) of Ext.P2 which are

the qualification and evaluation criteria. The 6 th respondent

does not have the required experience under Clause 4.2(b),

contended the petitioner. The 6 th respondent has not

produced any documents along with their tender, in proof of

their experience.

3. When the financial bid was opened, the 6 th

respondent was found to be in L1 position and the petitioner

was L2. The petitioner submits that the 6 th respondent does

not have requisite experience and respondents 3 to 5 have

not provided the pre-qualification documents in the

e-procurement portal.

4. The petitioner submitted Ext.P4 representation to

upload the pre-qualification evaluation of bidders. The

petitioner again represented to the 2 nd respondent as per

Ext.P5 pointing out that pre-qualification documents were not

made available, that the 6th respondent does not have the

pre-qualification and requesting not to award work to the 6 th WP(C) No.17381/2021

respondent. Apprehending that the work will be awarded to

the 6th respondent in spite of want of qualification and

experience, the petitioner has filed this writ petition.

5. The 4th respondent filed a statement in the writ

petition. The 4th respondent stated that the 6 th respondent is a

single entity and the qualification on requirement of a single

entity is specified in Clause 4.2(b). For establishing

experience, the bidder can demonstrate their arrangement to

deploy specialised agency with sufficient machinery or they

can submit an undertaking to procure own machinery for the

purpose of carrying out the work. As per the technical

evaluation, the 6th respondent was found qualified and well

experienced.

6. The 4th respondent stated that the evaluation of

bidders was done by M/s.Louis Berger which is the German

Bank approved project management consultancy. The

technical evaluation report was forwarded to the German

Bank, which was approved by the Bank as per

Annexure-R4(h).

WP(C) No.17381/2021

7. The 6th respondent filed a counter affidavit. The 6 th

respondent stated that they are qualified and successful

bidders and are entitled to award of the work. The 6 th

respondent satisfies all eligibility criteria prescribed for the

work.

8. After perusing the pleadings and hearing the

arguments, it appears that the grievance raised by the

petitioner is relating to Clause 4.2(b) of Ext.P2 bidding

document which provides the requirement as to construction

experience in key activities. The allegation is that the 6 th

respondent does not satisfy the experience required of single

entity bidders. Clause 4.2(b) to the extent it is applicable to

single entity bidders is as follows:-

No. Subject Requirement Single Entity

2 works of INR 48.75 Crores (Forty Eight Crores Seventy Five Lakhs only) or 3 works of INR 39 Crores (Thirty Nine Crores only) WP(C) No.17381/2021

4.2(b) Construction For the above or any other Must meet Experience contracts completed and under requirements. For in key implementation as prime contractor, items 6 and 7, activities joint venture member, management alternatively, the contractor or subcontractor on or bidder shall after the first day of the year during demonstrate their the period stipulated in 4.2(a) arrangement to above, a minimum construction deploy specialised experience in the following key agency with activities successfully completed: sufficient

1. Bituminous Concrete: 800 cum machinery or to per year submit an

2. Dense Bituminous Macadam: undertaking to 950 cum per year procure own

3. Wet Mix Macadam: 400 cum per machinery for the year purpose for

4. Granular Sub-base 12400 per carrying out PQC year and DLC and

5. Minor Bridge: At least 1 No. 10 m engage span per year experienced

6. PQC M 40 grade 14750 cum per technicians in the year relevant field.

7. DLC: 7700 cum per year

8. RCC: 11300 cum per year

The allegation of the petitioner is that the 6 th respondent does

not satisfy the requisite experience enumerated at Item Nos.4,

6 and 7.

9. The learned counsel for the petitioner argued that

the 6th respondent does not have the requisite 12400 cubic

metres per year experience of Granular Sub-base, 14750

cubic metres per year experience in PQC M 40 grade and

7700 cubic metres per year experience in DLC. Clause 4.2(b) WP(C) No.17381/2021

contains "must meet requirements" and therefore there cannot

be any relaxation. The project is of ₹111 Crores and it cannot

be given to any entity which does not have requisite

experience. The learned counsel for the petitioner further

argued that there is a vigilance report connected with identical

work bid by the 6th respondent and the vigilance report clearly

indicates that there are no documents to show that the 6 th

respondent satisfies the requisite experience. The vigilance

report also has found fault with other authorities who have

approved the bid submitted by the 6 th respondent. The

learned counsel for the petitioner further pointed out that in

spite of the findings in the vigilance report and substantial

allegation made in the writ petition, neither the 4 th respondent

nor the 6th respondent has produced even a scrap of paper

before this Court to prove their credentials.

10. The learned Senior Government Pleader resisted

the writ petition and stated that the selection was done as per

an evaluation report which found the 6 th respondent as

competent to undertake the work. The work in question is an WP(C) No.17381/2021

external aided project funded by German Bank. The 6 th

respondent has undergone through a multi layer scrutiny and

was found to be qualified. As far as publication of documents

relating to experience, a party participating in a bid has no

right to demand that all the documents should be uploaded in

public domain.

11. The learned Senior Counsel assisted by the

counsel for the 6th respondent submitted that the 6 th

respondent has passed stringent scrutiny in the matter of

qualification and experience. The scrutiny was made by

agencies who have technical knowledge in the field

concerned. The courts should show a lot of restraint in the

matter of interference in contractual matters and that too when

technical issues are involved. The authority who issues the

tender is the best judge to determine the qualification and

experience of bidders. The courts should not interfere in such

matters unless it is established that the decision taken by the

authorities are manifestly arbitrary. The learned Senior

Counsel further pointed out that the petitioner has no prayer in WP(C) No.17381/2021

the writ petition to award the work to him. The intention of the

petitioner is only to thwart the ongoing tendering process and

force the authorities to make a re-tender of the same work.

The work has to be completed in a time bound manner, within

18 months. Three months have already lapsed. In the

circumstances of the case, the writ petition should be

dismissed.

12. I have heard the learned counsel for the petitioner,

the learned Government Pleader representing respondents 1

to 5 and the learned Senior Counsel assisted by the counsel

for the 6th respondent.

13. The allegation of the petitioner is that the 6 th

respondent does not satisfy the experience conditions relating

to the following areas:-

              (i)     Item No.4 Granular Sub-base 12400
                      cubic metre per year

              (ii)    Item No.6 PQC M 40 Grade: 14750
                      cubic metre per year

(iii) Item No.7 DLC : 7700 cubic metre per year WP(C) No.17381/2021

Clause 4.2(b) of Ext.P2 would show that for Item Nos.6 and 7,

alternatively, the bidder can demonstrate their arrangement to

deploy specialised agency with sufficient machinery or can

submit an undertaking to procure own machinery for the

purpose for carrying out PQC and DLC and engage

experienced technicians in the relevant field. Such an

alternate requirement/option has been given to single entities.

The 6th respondent is a single entity. Ext.P2 bidding document

itself gives a relaxed option to single entities. If they do not

have the requisite experience in PQC and DLC, they can get

the work done deploying specialised agency with sufficient

machinery. Such single entities, alternatively, can submit an

undertaking to procure own machinery for the purpose of

carrying out PQC and DLC and engage experienced

technicians in the relevant field.

14. When Ext.P2 bidding document for procurement of

the works itself gives such options to the single entity bidders,

the petitioner cannot be heard to contend that those are "must

meet requirements" and the construction experience should WP(C) No.17381/2021

be satisfied by single entity themselves. The 6 th respondent

has given their undertaking as contemplated under Clause

4.2(b) along with their bid. Therefore, the argument of the

petitioner based on Item No.6 and 7 of Clause 4.2(b) of Ext.P2

is only to be rejected.

15. As regards Item No.4, it requires experience in

Granular Sub-base of a quantity of 12400 cubic metres per

year. The 6th respondent has stated that they have executed

more than 12400 cubic metres in a year, together as a prime

contractor and a sub contractor, of Granular Sub-base during

the relevant period. The 6th respondent would further submit

that Wet Mix Macadam (WMM) work means and includes

laying and compacting clean, crushed, graded, aggregate and

granular material pre-mixed with water, to a dense mass on a

required GSD layer. Therefore, technically, the experience in

Item No.4 is always taken together with Item No.3. The 6 th

respondent has executed 85704.63 cubic metres of Item No.3

work.

WP(C) No.17381/2021

16. The 4th respondent has produced Ext.R4(b) which

is the technical evaluation report. With regard to requirement

of Granular Sub-base, as against the requirement of 12400

cubic metres per year, the 6th respondent has compliance of

15818 cubic metres, in the year 2019-'20. As far as the

petitioner is concerned, the petitioner has compliance of

30022 cubic metres, which is the average quantity of five

years. Therefore, going by the technical evaluation report, the

6th respondent satisfies the requirement under Item No.4 of

Clause 4.2(b).

17. In this regard, it has to be kept in mind that the

project is an external aided project. The bids and the

technical qualifications of the bidders have undergone a three

stage scrutiny. One by M/s.Louis Berger who are the

technical experts appointed by the German Bank. The 3 rd

respondent-Kerala State Transport Project has also

scrutinised and verified the qualifications. Thereafter, the

German Bank has also considered the qualifications and has

arrived at Ext.R4(b) report, after a thorough scrutiny and WP(C) No.17381/2021

evaluation. When the authority which tendered the work and

the technical experts well-versed in the field have found that

the 6th respondent satisfies the requisite experience, it would

be inappropriate for this Court to come to a conclusion to the

contrary, unless of course, there are compelling

circumstances.

18. The Hon'ble Apex Court has held in the judgment in

Silppi Constructions Contractors v. Union of India and

another [(2020) 16 SCC 489] that the Courts should exercise

a lot of restraints while exercising their powers of judicial

review in contractual or commercial matters. The courts must

realise their limitations and the havoc which needless

interference in commercial matters can cause. In contracts

involving technical issues, the courts should be even more

reluctant because most Judges do not have the necessary

expertise to adjudicate upon technical issues beyond their

domain. The courts should give way to the opinion of experts

unless the decision is totally arbitrary or unreasonable. The

courts should not use a magnifying glass to scan tenders and WP(C) No.17381/2021

make every small mistakes appear like a big blunder. The

courts must give "fair play in the joints" to Government and

Public Sector Undertakings in matters of contract.

19. The learned counsel for the petitioner pointed out

that vigilance wing of Pubic Works Department has made an

enquiry into the Nemmara Nelliampathy Road tender under

the Re-Build Kerala Project undertaken by the KSTP and

came to a conclusion that there is no document submitted by

the 6th respondent in proof of any work done legally, executing

any agreements with the Government and that the PMC

Consultants and KSTP Officials who drafted the technical

evaluation report could not explain the same. Therefore,

when there is a vigilance report against respondents 3 to 6

doubting the technical qualification of the 6 th respondent, the

present work involving ₹111 Crores cannot be awarded to the

6th respondent.

20. It has to be noted that the report is drafted by a

vigilance enquiry team in respect of another work. As regards

the present work, as stated above, the tendering authority and WP(C) No.17381/2021

the technical experts have scrutinised the records and found

that the 6th respondent satisfies the eligibility conditions. As

held by the Hon'ble Apex Court, the authority which floats the

contracts or tender and has authored the tender documents is

the best Judge as to how the document have to be

interpreted. The courts will only interfere to prevent

arbitrariness, irrationality, bias, malafides or perversity.

Therefore, it will be improper to interfere with the tendering

process on the basis of a preliminary report made by the

vigilance officers of the Public Works Department in respect of

another work.

For all the afore reasons, the writ petition is devoid

of any merit and is liable to be dismissed. The writ petition is

accordingly dismissed.

Sd/-

N. NAGARESH, JUDGE

aks/06.11.2021 WP(C) No.17381/2021

APPENDIX OF WP(C) 17381/2021

PETITIONER'S EXHIBITS:

Exhibit P1 TRUE COPY OF THE POWER OF ATTORNEY FOR LEAD MEMBER OF THE JOINT VENTURE Exhibit P2 TRUE COPY OF SECION III, QUALIFICATION AND EVALUATION CRITERIA OF BIDDING DOCUMENT FOR PROCUREMENT OF WORK.

Exhibit P3 TRUE COPY OF THE TENDER SUMMARY REPORT DATED 14.08.2021 FROM THE E-TENDERING SYSTEM, GOVERNMENT OF KERALA.

Exhibit P4 TRUE COPY OF THE REPRESENTATION DATED 28.07.2021 SUBMITTED BY ANTECH-PRL(JV) THROUGH ITS AUTHORIZED SIGNATORY.

Exhibit P5            TRUE   COPY   OF   THE   REPRESENTATION
                      SUBMITTED M/S ANTECH PRL(JV) THROUGH
                      ITS    AUTHORIZED    SIGNATORY    DATED

24.08.2021 BEFORE THE 2ND RESPONDENT.

RESPONDENTS' EXHIBITS:

Exhibit R6(a) TRUE COPY OF THE RELEVANT PAGES OF THE SECTION II. QUALIFICATION AND BID DATA SHEET.

Exhibit R6(b) TRUE COPY OF THE RELEVANT PAGE (CORRIGENDUM - 5) OF THE WORK REHABILITATION AND UP GRADATION OF MOOKKANNUR - EZHATTUMUGHAM ROAD AND BLACHIPPARA - PALLISSERY ROAD (LENGTH 19.950 KM) IN ERNAKULAM DISTRICT (KSTP/KFW/RKI PKG-III/WORK/RD-I).

Exhibit R6(c)         TRUE COPY OF THE RELEVANT PAGE (SECTION
                      III - EVALUATION AND QUALIFICATION
                      CRITERIA,    CLAUSE    4.2(b)    FOR   WORK
                      REHABILITATION    AND   UP    GADATION   OF

VADAYAR CHANDAPPALAM MULAKKULAM ROAD AND VADAYAR KALLATTIPPALAM MUTTUCHIRA ROAD (LEMGTH OF 22.476 KM) IN KOTTAYAM DISTRICT.

ANNEXURE-R4(a)        THE RELEVANT PAGE SHOWING CLASUE 4.2(b)
 WP(C) No.17381/2021



ANNEXURE-R4(b)        COPY OF THE EVALUATION DONE BY THE
                      GERMMAN    BANK     APPROVED    PROJECT
                      MANAGEMENT     CONSULTANCY    M/S.LOUIS
                      BERGER.
ANNEXURE-R4(c)        TRUE COPY OF THE APPROVAL OF THE GERMAN
                      BANK DATED 03.05.2021
ANNEXURE-R4(d)        TRUE COPY OF THE EVALUATION.
ANNEXURE-R4(e)        TRUE COPY OF THE APPROVAL OF THE GERMAN
                      BANK DATED 27.05.2021
ANNEXURE-R4(f)        TRUE COPY OF CLAUSE 2.5.2.
ANNEXURE-R4(g)        TRUE COPY OF THE LETTER ISSUED TO NIC

KERALA STATE CENTRE (e-TENDER PORTAL) ANNEXURE-R4(h) TRUE COPY OF THE FINAL APPROVAL GIVEN BY THE GERMAN BANK DATED 28.06.2021.

SR

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter