Citation : 2021 Latest Caselaw 21581 Ker
Judgement Date : 2 November, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
TUESDAY, THE 2ND DAY OF NOVEMBER 2021/11TH KARTHIKA, 1943
WP(C) NO. 19955 OF 2021
PETITIONER:
K.J. SIMON, KALATHARAYIL HOUSE,
PADANADU, CHENGANNUR, PIN-689 506.
BY ADV NEETHU SOMAN
RESPONDENTS:
1 STATE OF KERALA REPRESENTED BY
THE SECRETARY TO GOVERNMENT,
IRRIGATION DEPARTMENT,
KERALA SECRETARIAT,
THIRUVANANTHAPURAM, PIN-695 001.
2 THE DISTRICT COLLECTOR,
COLLECTORATE, PATHANAMTHITTA,
KERALA, PIN-689 645.
3 THE ASSISTANT EXECUTIVE ENGINEER,
IRRIGATION SUB-DIVISION,
PATHANAMTHITTA, PIN-689 641.
ADDL.4 THE REVENUE DIVISIONAL OFFICER,
REVENUE DIVISIONAL OFFICE,
M.G.ROAD, PARASS LA,
ADOOR, KERALA 691 523.
(ADDITIONAL R4 IS IMPLEADED AS PER ORDER DATED
02.11.2021 IN I.A.NO.1/2021)
SRI.CYRIAC KURIAN SPL.G.P. (IRRIGATION)
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION
ON 02.11.2021, ALONG WITH WP(C).20000/2021, THE COURT ON THE
SAME DAY DELIVERED THE FOLLOWING:
WP(C)Nos.19955/2021 & 20000/2021
2
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
TUESDAY,THE 2ND DAY OF NOVEMBER 2021/11TH KARTHIKA,1943
WP(C) NO. 20000 OF 2021
PETITIONER:
V.G.RAJU, AGED 60 YEARS,
S/O. V.M. GOPALAKRISHNAN,
'A' CLASS CONTRACTOR IN IRRIGATION
DEPARTMENT, PIROVOM, VILANJOOPARMPIL
HOUSE, PERINGARA P.O., THIRUVALLA,
PATHANAMTHITTA DISTRICT 689 108.
BY ADV NEETHU SOMAN
RESPONDENTS:
1 STATE OF KERALA REPRESENTED BY
THE SECRETARY TO GOVERNMENT,
IRRIGATION DEPARTMENT, SECRETARIAT,
TRIVANDRUM 695 001.
2 THE DISTRICT COLLECTOR, COLLECTORATE,
PATHANAMTHITTA, KERALA 689 645.
3 THE ASSISTANT EXECUTIVE ENGINEER,
IRRIGATION SUB- DIVISION,
KOZHENCHERRY, PATHANAMTHITTA 689 641.
ADDL.4 THE REVENUE DIVISIONAL OFFICER,
REVENUE DIVISIONAL OFFICE, M.G.ROAD,
PARASS LA, ADOOR, KERALA PIN 691 523.
(ADDITIONAL R4 IS IMPLEADED AS PER ORDER DATED
02.11.2021 IN I.A.NO.1/2021)
BY SRI.CYRIAC KURIAN (SPL.G.P. IRRIGATION)
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR
ADMISSION ON 02.11.2021, ALONG WITH WP(C).19955/2021,
THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C)Nos.19955/2021 & 20000/2021
3
JUDGMENT
Dated this the 2nd day of November, 2021
The petitioners in both these writ petitions are
Contractors who entered into an agreement with the
respondents for upgradation and maintenance of irrigation
of canals, rivers etc. The petitioners would submit that in
respect of the petitioner in WP(C)No.19955/2021, an
amount of `14,62,214/- (Rupees Fourteen lakhs sixty two
thousand two hundred and fourteen only) is due and inspite
of the submission, the bill is not processed and amount not
paid.
2. As regards the petitioner in WP(C)No.
20000/2021, the petitioner would state that an amount of
`24,15,824/- (Rupees Twenty four lakhs fifteen thousand
eight hundred and twenty four only) is due to the petitioner
and the amount is not paid so far. The work was completed WP(C)Nos.19955/2021 & 20000/2021
promptly without any substantial delay and the amounts due
to the petitioners cannot be withheld, contended the learned
counsel for the petitioners.
3. The learned Special Government Pleader for
Irrigation submitted that the bills submitted by the petitioners
are processed. Now the additional 4 th respondent has to
scrutinise the bill and countersign the same and it has to be
forwarded to the District Collector. Once the District
Collector receives the bill duly signed by the additional 4 th
respondent, then the amount payable to the petitioners can
be paid without further delay.
4. I have heard the learned counsel for the
petitioners and the learned Special Government Pleader
representing the respondent.
5. The satisfactory completion of work undertaken
by the petitioners is not in dispute. The fact that the
petitioners have raised their bills is admitted. In such WP(C)Nos.19955/2021 & 20000/2021
circumstances, this Court is of the opinion that the payment
of amounts to the petitioners cannot be delayed further for
unconceivable reasons.
In the circumstances, the writ petition is disposed of
directing the additional 4th respondent to scrutinise and
countersign the bills preferred by the petitioners within a
period of 30 days. The District Collector shall process the
bill and make payment to the petitioners within a further
period of two months therefrom, if the petitioners are
otherwise eligible.
Sd/-
N. NAGARESH JUDGE ncd/05.11.2021 WP(C)Nos.19955/2021 & 20000/2021
APPENDIX OF WP(C) 19955/2021
PETITIONER'S EXHIBITS
Exhibit P1 A TRUE COPY OF THE B CATEGORY REGISTRATION CERTIFICATE ISSUED BY THE SUPERINTENDING ENGINEER, DEVELOPMENT CIRCLE KUTTANDU CHENGANNUR, KERALA, TO THE PETITIONER.
Exhibit P2 A TRUE COPY OF THE LETTER OF ACCEPTANCE FOR REMOVAL OF SILT AND OTHER WASTE MATERIALS FROM ACHENKOVIL RIVER AT VARIOUS KADAVUS THUMPAMON PANCHAYATH ISSUED BY THE ASSISTANT EXECUTIVE ENGINEER IRRIGATION SUB DIVISION PATHANAMTHITTA DATED 5.6.2020. Exhibit P3 A TRUE COPY OF THE LETTER OF ACCEPTANCE FOR THE REMOVAL OF ACCUMULATED SILT IN ACHENKOVIL RIVER NEAR PANTHAPLAVIL KADAVUS IN KULANADA PANCHAYATH ISSUED BY THE ASSISTANT EXECUTIVE ENGINEER IRRIGATION SUB DIVISION PATHANAMTHITTA DATED 4.6.2020.
Exhibit P4 A TRUE COPY OF THE LETTER OF ACCEPTANCE FOR THE REMOVAL OF SILT AND OTHER WASTE MATERIALS IN THE BANKS OF ACHENKOVIL RIVER AT MATHOORBHGAM IN CHENNERKKARA PANCHAYATH.
Exhibit P5 A TRUE COPY OF LETTER OF COMMENCEMENT ISSUED BY THE ASSISTANT EXECUTIVE ENGINEER 33/AEE/2020-21 DATED 10.6.2020. Exhibit P6 A TRUE COPY OF LETTER OF COMMENCEMENT ISSUED BY THE ASSISTANT EXECUTIVE ENGINEER 27/AEE/2020-21 DATED 10.6.2020. Exhibit P7 A TRUE COPY OF LETTER OF COMMENCEMENT ISSUED BY THE ASSISTANT EXECUTIVE ENGINEER 26/AEE/2020-21 DATED 10.6.2020. Exhibit P8 A TRUE COPY OF THE CONTRACT AGREEMENT ENTERED INTO BETWEEN THE PETITIONER AND THE ASSISTANT EXECUTIVE ENGINEER (6/AEE/2020-21) ON 26.6.2020. WP(C)Nos.19955/2021 & 20000/2021
Exhibit P9 A TRUE COPY OF THE CONTRACT AGREEMENT ENTERED INTO BETWEEN THE PETITIONER AND THE ASSISTANT EXECUTIVE ENGINEER (7/AEE/2020-21) ON 26.6.2020. Exhibit P10 A TRUE COPY OF THE CONTRACT AGREEMENT ENTERED INTO BETWEEN THE PETITIONER AND THE ASSISTANT EXECUTIVE ENGINEER (8/AEE/2020-21) ON 26.6.2020. Exhibit P11 A TRUE COPY OF THE COMPLETION CERTIFICATE UNDER THE AGREEMENT 06/AEE/2020-21 ON 13.7.2020.
Exhibit P12 A TRUE COPY OF THE COMPLETION CERTIFICATE ON UNDER THE AGREEMENT NO.07/AEE/2020-21 ON 10.7.2020. Exhibit P13 A TRUE COPY OF THE COMPLETION CERTIFICATE UNDER THE AGREEMENT NO.08/AEE/2020-21 ON 3.7.2020. Exhibit P14 A TRUE COPY OF FINAL BILL OF THE TOTAL VALUE EXECUTED UNDER THE AGREEMENT NO.06/AEE/2020-21.
Exhibit P15 A TRUE COPY OF FINAL BILL OF THE TOTAL VALUE EXECUTED UNDER THE AGREEMENT NO.07/AEE/2020-21.
Exhibit P16 A TRUE COPY OF FINAL BILL OF THE TOTAL VALUE EXECUTED UNDER THE AGREEMENT NO.08/AEE/2020-21.
WP(C)Nos.19955/2021 & 20000/2021
APPENDIX OF WP(C) 20000/2021
PETITIONER'S EXHIBITS
Exhibit P1 A TRUE COPY OF THE A CATEGORY REGISTRATION CERTIFICATE ISSUED BY THE SUPERINTENDING ENGINEER, PROJECT CIRCLE PIRAVOM KERALA, TO THE PETITIONER DATED 04.02.2020.
Exhibit P2 A TRUE COPY OF THE LETTER OF ACCEPTANCE FOR THE REMOVAL OF SILT AND OTHERS WASTE MATERIALS DEPOSIT IN THE BANKS OF RIVER JAWAN KADVU TO ANJILIMOOTIL KADAVU IN ARAMULA PANCHAYATH ISSUED BY ASSISTANT EXECUTIVE ENGINEER IRRIGATION SUB DIVISION PATHANAMTHITTA DATED 04.06.2020.
Exhibit P3 A TRUE COPY OF THE LETTER OF ACCEPTANCE FOR THE REMOVAL OF SILT AND OTHER WASTER MATERIALS DEPOSITED IN THE BANKS OF RIVER VAZHAUVELI KADAVU OF ACHANKOVIL RIVER IN KULANADA PANCHAYAT ISSUED BY ASSISTANT EXECUTIVE ENGINEER IRRIGATION SUB DIVISION PATHANAMTHITTA DATED 04.06.2020.
Exhibit P4 A TRUE COPY OF THE LETTER TO
COMMENCEMENT ISSUED BY THE 3RD
RESPONDENT DATED 10/06/2020 TENDER NO. 34/AEE/2020-21.
Exhibit P5 A TRUE COPY OF LETTER TO COMMENCEMENT ISSUED BY THE 3RD RESPONDENT DATED 10/08/2020 TENDER NO. 31/AEE/2020-21. Exhibit P6 A TRUE COPY OF THE CONTRACT AGREEMENT NO. 4/AEE/2020-21 ENTERED BETWEEN PETITION AND THE ASSISTANT EXECUTIVE ENGINEER, IRRIGATION DEPARTMENT DATED 23.06.2020.
Exhibit P7 A TRUE COPY OF THE CONTRACT AGREEMENT NO. 5/EE/2020-21 ENTERED BETWEEN PETITION AND THE ASSISTANT EXECUTIVE ENGINEER IRRIGATION DEPARTMENT DATED 23/06/21020.
WP(C)Nos.19955/2021 & 20000/2021
Exhibit P8 A TRUE COPY OF COMPLETION CERTIFICATE ISSUED BY THE ASSISTANT EXECUTIVE ENGINEER ON 23/07/2021 FOR THE AGREEMENT REF NO. 04/AEE/2020-21 Exhibit P9 A TRUE COPY OF COMPLETION CERTIFICATE ISSUED BY HE ASSISTANT EXECUTIVE ENGINEER ON 23/07/2021 UNDER THE AGREEMENT REF NO. 05/AEE/2020-21. Exhibit P10 A TRUE COPY OF FINAL BILL OF THE AGREEMENT REF NO. 4/AEE/2020-21 SIGNED BY THE ASSISTANT EXECUTIVE ENGINEER IRRIGATION SUB DIVISION, PATHANAMTHITTA DATED 03/02/2021 MEASUREMENT BOOK NO. 174/2020.
Exhibit P11 A TRUE COPY OF FINAL BILL OF THE AGREEMENT REF NO. 4/AEE/2020-21 SIGNED BY THE ASSISTANT EXECUTIVE ENGINEER, SUB DIVISION PATHANAMTHITTA DATED 03/02/2020 MEASUREMENT BOOK NO. 165/2020.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!