Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

V.Ummer Haji vs State Of Kerala
2021 Latest Caselaw 7576 Ker

Citation : 2021 Latest Caselaw 7576 Ker
Judgement Date : 4 March, 2021

Kerala High Court
V.Ummer Haji vs State Of Kerala on 4 March, 2021
               IN THE HIGH COURT OF KERALA AT ERNAKULAM

                               PRESENT

                 THE HONOURABLE SMT. JUSTICE P.V.ASHA

    THURSDAY, THE 04TH DAY OF MARCH 2021 / 13TH PHALGUNA, 1942

                       WP(C).No.4783 OF 2021(W)


PETITIONER:

               V.UMMER HAJI
               AGED 67 YEARS
               VAZHAKANDY HOUSE, SULATHAN BATHERY,
               WAYANAD DISTRICT 673 592

               BY ADVS.
               SRI.JOMY GEORGE
               SRI.R.PADMARAJ
               SRI.M.J.BENNY
               SRI.DEEPAK MOHAN
               SMT. CHITRA N. DAS
               SHRI.RISHAB S.
               SHRI.GEORGE J MOOLAMKUNNAM

RESPONDENTS:

      1        STATE OF KERALA
               REPRESENTED BY CHIEF SECRETARY,
               GOVERNMENT SECRETARIAT,
               THIRUVANANTHAPURAM 695 001

      2        THE SECRETARY,
               PUBLIC WORKS DEPARTMENT,
               GOVERNMENT SECRETARIAT,
               THIRUVANANTHAPURAM 695 001

      3        THE SUPERINTENDING ENGINEER,
               PWD ROADS NORTH CIRCLE, PWD COMPLEX,
               MANANCHIRA, KOZHIKODE 673 001

      4        THE EXECUTIVE ENGINEER,
               PWD ROADS DIVISION, KALPATTA,
               WAYANAD DISTRICT 673 121


OTHER PRESENT:

               SMT.PRINCY XAVIER, GP

     THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
04.03.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C).No.4783 OF 2021(W)

                                   2




                        J U D G M E N T

Petitioner, who is a Contractor, has been

awarded the work of construction of Mambilichikadavu

Bridge in Vengapally Grama Panchayath in Wayanad

District. As per the selection notice petitioner was

directed to remit a sum of Rs.11,42,040/- towards

performance guarantee. Stating that amount is due

under various bills pending payment towards work

already executed by the petitioner, he submitted an

application on 11.02.2021 requesting for adjusting

the amount covered by the pending bills towards the

performance guarantee. As per Ext.P2 letter dated

12.02.2021, the 4th respondent-Executive Engineer

informed that a sum of Rs.3432900/- is outstanding

towards the pending bill in respect of another work

carried out by the petitioner which was completed on

06.03.2019. The 4th respondent recommended adjustment

of the amount towards performance guarantee as WP(C).No.4783 OF 2021(W)

against the said bill.

2. However as per Ext.P3 letter the 3 rd

respondent informed that adjustment can be made only

on production of indemnity certificate through EMLI

software.

3. Petitioner points out that in the case of

several contractors pending bills are already

adjusted manually on the basis of directions from

this Court since the EMLI software has not been

modified so far in tune with Ext.P4 Government

Order.

4. Learned Government Pleader also submitted

that the EMLI software is not modified so far.

5. Ext.P4 Government order has been issued as

early as on 23.06.2020. As per sub clause (v) of

Clause 3 of Ext.P4 order, amount due under audited

and passed bills of contractors would be accepted as

Performance Guarantee for new works being awarded,

only on the basis of indemnity certificate issued WP(C).No.4783 OF 2021(W)

online in EMLI application. Clause 4 provides for

effecting necessary modifications in EMLI to

facilitate the new system. Though the facility for

adjustment of the bills have been ordered by the

Government for the benefit of the contractors on

their request, suitable modifications are yet to be

effected in the software so as to enable the

contractors to enjoy the benefit of the order. The

petitioner cannot therefore be denied the benefit of

the same, in case petitioner satisfies all other

conditions in Ext.P4 order. This Court has in

several cases directed the respondents to carry out

the adjustment manually.

Therefore, there shall be a direction to the 3 rd

respondent to consider the request of the petitioner

for adjustment of the amount towards performance

guarantee from the admissible amount, if any under

the pending bill covered by Ext.P2 letter, in

accordance with Ext.P4 Government Order manually, WP(C).No.4783 OF 2021(W)

i.e., without insisting for indemnity certificate

through EMLI. This shall be done within a period of

'two weeks' from the date of receipt of a copy of

the judgment. Petitioner shall also be granted time

for execution of agreement by a further period of

'two weeks'.

The Writ Petition is disposed of accordingly.

Sd/-

P.V.ASHA, JUDGE AS WP(C).No.4783 OF 2021(W)

APPENDIX PETITIONER'S EXHIBITS:

EXHIBIT P1 TRUE COPY OF THE PROFORMA SHOWING THE PENDING BILL AMOUNT OF THE PETITIONER ISSUED BY THE 4TH RESPONDENT.

EXHIBIT P2 TRUE COPY OF THE LETTER NO.

A6/121/434/2020 DATED 12-0-2-2020 (WRONGLY DATED 12-02-2020 ) SENT BY THE 4TH RESPONDENT TO THE 3RD RESPONDENT

EXHIBIT P3 TRUE COPY OF THE LETTER DATED 16-02-

2021 ISSUED BY THE 3RD RESPONDENT REJECTING THE REQUEST OF THE PETITIONER.

EXHIBIT P4 TRUE COPY OF THE GOVERNMENT ORDER G.O(RT) NO. 3834/2020/FIN DATED 23- 06-2020

EXHIBIT P5 TRUE COPY OF THE JUDGMENT DATED 09-

11-2020 IN W.P(C) NO. 22048/2020 OF THIS HON'BLE COURT.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter