Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

P.V.S.Constuctions vs The State Of Kerala
2021 Latest Caselaw 10077 Ker

Citation : 2021 Latest Caselaw 10077 Ker
Judgement Date : 25 March, 2021

Kerala High Court
P.V.S.Constuctions vs The State Of Kerala on 25 March, 2021
WP(C).No.833 OF 2021(D)
                                  1

              IN THE HIGH COURT OF KERALA AT ERNAKULAM

                               PRESENT

                 THE HONOURABLE SMT. JUSTICE P.V.ASHA

      THURSDAY, THE 25TH DAY OF MARCH 2021 / 4TH CHAITHRA, 1943

                       WP(C).No.833 OF 2021(D)


PETITIONER/S:

                P.V.S.CONSTUCTIONS
                REPRESENTED BY ITS MANAGING PARTNER, P.V.SIVADAS,
                S/O.VASUDEVAN, AGED 49 YEARS, POOZHIKUNNUPARAMBIL,
                MELE KANDIYOOR, JELLIPPARA P.O., PALAKKAD-678 581

                BY ADVS.
                SRI.T.C.SURESH MENON
                SRI.P.S.APPU

RESPONDENT/S:

        1       THE STATE OF KERALA
                REPRESENTED BY THE SECRETARY TO GOVERNMENT, PUBLIC
                WORKS DEPARTMENT, SECRETARIAT, THIRUVANANTHAPURAM-
                695 001

        2       THE SUPERINTENDING ENGINEER,
                PUBLIC WORKS DEPARTMENT BUILDINGS, OFFICE OF THE
                SUPERINTENDING ENGINEER, PWD BUILDINGS, NORTH
                CIRCLE, KOZHIKODE-673 001

        3       THE ASSISTANT ENGINEER,
                PUBLIC WORKS DEPARTMENT, BUILDING SECTION NO.II,
                PALAKKAD-678 001

  *     4       THE CHIEF ENGINEER,
                PWD, THIRUVANANTHAPURAM

                IS SUO MOTU IMPLEADED AS ADDITIONAL R4 AS PER ORDER
                DATED 25.03.2021

OTHER PRESENT:

                SMT.PRINCY XAVIER, GP

     THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
25.03.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C).No.833 OF 2021(D)
                                                 2



                                        JUDGMENT

Dated this the 25th day of March 2021

The petitioner is an A Class contractor. Pursuant to Ext.P1

tender notification issued by the 2nd respondent inviting

tenders for construction of Laparoscopic Sterilization Operation

Theatre, Pay Ward and Parking facility, petitioner participated

in the same and quoted a sum of Rs.1,91,38,700/-. As per Ext.P2

letter the 2nd respondent informed the petitioner that the lowest

rate was quoted by him. However 2nd respondent informed the

petitioner that the rate quoted by him in respect of certain

items including item no.1.07 was higher and therefore petitioner

has to explain the reason for such higher rates. In answer to

the same petitioner as per Ext.P3 letter informed that he had

quoted only reasonable and prevailing rates. Thereafter Ext.P4

selection notice dated 30.07.2020 was issued to the petitioner,

based on which petitioner executed Ext.P7 agreement after

getting extension as per Ext.P6 order dated 27.08.2020 and on

payment of penalty of Rs.25,000/-. The complaint of the

petitioner is that subsequent to the execution of the agreement,

respondents effected deletion of one item covered by Ext.P8 at

serial No.1.07. Petitioner pointed out that the said deletion

was without any information to him and that he had quoted the

amount only after considering all the items covered by Ext.P8.

Immediately, thereupon the petitioner had submitted Ext.P9 WP(C).No.833 OF 2021(D)

letter pointing out that on deletion of item No.1.07 he will not

be able to execute the work and therefore he has to be permitted

to carry out the work including the work covered by item

No.1.07. The said request was not accepted and as per Ext.P10

letter dated 18.12.2020 petitioner was informed that the

Assistant Executive Engineer had reported that item No.1.07 was

not necessary and the materials on demolition of the said item

can be stored in a separate location. The petitioner was

directed to commence the work. The Writ Petition was filed at

that stage.

2. According to the respondents, the Engineer is to decide

which are the items to be included. It is stated that the

dispute raised by the petitioner is regarding item No.1.07 ie.

removing mortar from the bricks and clearing including stacking

with a lead of 50 meters, which was provided in the agreement

schedule for the purpose of recovering the reused dismantled

bricks and stacking the same for reuse. Item no.1.06 is for

demolishing brickwork manually/by mechanical means including

stacking of serviceable materials and disposal of unserviceable

materials within a lead of 50m as per the direction of the

Engineer in charge. It is stated that main item is 1.06 and the

item No.1.07 would become necessary only if the dismantled

material is good for reuse and viable depending upon the

logistics of handling the demolished material, quality of

demolished material etc. According to them, as per clause 30.6 WP(C).No.833 OF 2021(D)

of the bid document, the Engineer has to instruct the contractor

to vary quantities of the items or group of items and the

contractor shall carryout the variation as instructed by the

Engineer and the contractor cannot insist on the employer that

he would not carry out a particular item or that the particular

item is essential for completing the work. Clause 30.6 reads as

follows: .

"30.6 : Notwithstanding anything stated above in this clause, the Engineer shall have the full power to instruct the Contractor, in writing, during the execution of the Contract, to vary the quantities of the items or group of items. The Contractor shall carry out such variations and be bound by the same conditions, as though the said variations occurred in the Contract documents. However, the contract price shall be adjusted at the rates and the prices provided for the original quantities in the Contract."

Therefore, the respondents point out that the petitioner has to

carry out the work in accordance with the directions of the

Engineer irrespective of the bid submitted by him.

3. Eventhough petitioner has filed a reply affidavit

producing Ext.P11 dated 22.12.2015 pointing out that the very

contract itself is awarded to the petitioner by an incompetent

authority, it is seen that the said order relates to the

procedure for sanctioning tender excess, revised estimate, etc.

4. However, the petitioner's case is that the respondents

have committed fraud by insisting him to execute an agreement

even after clarifications were sought from him in Ext.P2

relating to the rate for item 1.07 and petitioner furnished his

reply in Ext.P3. The work is not yet commenced and the WP(C).No.833 OF 2021(D)

petitioner is not willing to carryout the work in accordance

with the said agreement in the absence of item at 1.07.

5. In the aforesaid circumstances, I am of the view that

the matter has to be considered by an authority superior to the

Superintending Engineer. Therefore, there shall be a direction

to the Chief Engineer to look into the matter and to take a

decision after affording an opportunity of hearing to the

petitioner within a period of six weeks. Hearing can be held

through electronic mode.

The Writ Petition is disposed of accordingly.

Sd/-

                                              P.V.ASHA

rkc                                                JUDGE
 WP(C).No.833 OF 2021(D)



                             APPENDIX
PETITIONER'S/S EXHIBITS:

EXHIBIT P1              TRUE   COPY   OF    THE   TENDER      NOTIFICATION
                        NO.PKD/2018/2371 DATED 25.5.2020

EXHIBIT P2              TRUE     COPY      OF     THE     COMMUNICATION
                        NO.DB6/BL/2018/2371, DATED 30.6.2020

EXHIBIT P3              TRUE COPY OF THE REPLY TO EXT.P2 SUBMITTED BY
                        THE PETITIONER DATED 15.7.2020

EXHIBIT P4              TRUE     COPY      OF     THE     COMMUNICATION
                        NO.DB6/BL/2018/2371,DATED 30.7.2020

EXHIBIT P5              TRUE COPY OF THE REQUEST LETTER SENT BY THE
                        PETITIONER TO THE 2ND RESPONDENT , DATED
                        18.8.2020

EXHIBIT P6              TRUE COPY OF THE ORDER NO.DB6/BL/2018/2371

PASSED BY THE 2ND RESPONDENT, DATED 27.8.2020

EXHIBIT P7 TRUE COPY OF THE CONFIRMATION LETTER NO.DB6/BL/2018/2371 SENT BY THE 2ND RESPONDENT, DATED 18.9.2020

EXHIBIT P8 TRUE COPY OF THE ACCEPTED AGREEMENT DATED 18.9.2020

EXHIBIT P9 TRUE COPY OF THE REQUEST MADE BY THE PETITIONER DATED 21.10.2020

EXHIBIT P10 TRUE COPY OF THE COMMUNICATION DATED 18.12.2020 ISSUED BY THE 2ND RESPONDENT

EXHIBIT P11 TRUE COPY OF THE CIRCULAR NO.29874/E2/2015PWD ISSUED BY THE 1ST RESPONDENT DT.22.12.2015

RESPONDENTS' EXHIBITS

ANNEXURE R2A TRUE COPY OF THE AGREEMENT SIGNED BY THE PETITIONER

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter