Citation : 2021 Latest Caselaw 15688 Ker
Judgement Date : 30 July, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE DEVAN RAMACHANDRAN
FRIDAY, THE 30TH DAY OF JULY 2021 / 8TH SRAVANA, 1943
WP(C) NO. 17484 OF 2014
PETITIONER:
VIJAYAN.G.
OTTUVAZHICKAL HOUSE, KADANAD P.O., PALA, KOTTAYAM DISTRICT,
(RETIRED ASSISTANT ENGINEER, KERALA STATE ELECTRICITY BOARD,
110KV SUB STATION, PALA)
BY ADVS.
DR.K.P.SATHEESAN (SR.)
SRI.ANOOP.V.NAIR
SRI.M.R.JAYAPRASAD
SRI.P.MOHANDAS ERNAKULAM
SRI.SIDDHARTH KRISHNAN
SRI.S.VIBHEESHANAN
RESPONDENTS:
1 KERALA STATE ELECTRICITY BOARD LTD.
REPRESENTED BY THE CHAIRMAN AND MANAGING DIRECTOR, VYDYTHI
BHAVAN, PATTOM, THIRUVANANTHAPURAM - 695 004.
2 THE CHIEF ENGINEER (H.R.M)
KERALA STATE ELECTRICITY BOARD LTD., VYDYUTHI BHAVAN, PATTOM,
THIRUVANANTHAPURAM - 695 004.
3 THE DEPUTY CHIEF ENGINEER
KERALA STATE ELECTRICITY BOARD LTD., ELECTRICAL CIRCLE,
ALAPPUZHA - 688 001.
BY ADV SRI.K.S.ANIL, SC
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 30.07.2021,
THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C) NO. 17484 OF 2014
2
JUDGMENT
While the petitioner was working as an Assistant Engineer in
the services of 'Kerala State Electricity Board' (KSEB), he was
issued with Ext.P1 Memo of Charges, alleging that he had failed to
detect an 'erroneous connection' in respect of a consumer, under
the electrical section, Kidangara; and thereby caused monetary
loss to the Board.
2. The petitioner transpires to have answered the Memo of
Charges through Ext.P2, stating that he was not responsible for
any such misconduct and thus, praying that he be not proceeded
against.
3. However, the KSEB initiated a disciplinary enquiry
against him, which led to Ext.P4 report of the enquiry officer dated
10.12.2010, holding the petitioner not guilty of any of the charges,
finding that the error in the connection in question must have
happened after August 2004 and therefore, that the officials at the
time of installation of the new meter on 08.01.2001, cannot be
held responsible for the same.
4. The petitioner having been so exonerated, was
thereafter, issued with Ext.P5 order of the Disciplinary Authority,
namely, the Chief Engineer, (HRM) on 08.06.2012, notifying him WP(C) NO. 17484 OF 2014
that said Authority had disagreed with the views of the Enquiry
Authority, thus imposing a punishment of Rs.1,02,035/-, along with
interest thereon, to be recovered from his DCRG/pensionary
benefits. The petitioner asserts that Ext.P5 was issued without any
notice to him, but directing to show cause why the afore said
amount be not recovered from him, and that he, therefore,
preferred Ext.P6 reply to it. He alleges that without assessing any
of the contentions therein, Ext.P8 order was issued confirming
Ext.P5 and consequently, that he approached the competent
Appellate Authority, through an appeal, which was also, however,
dismissed through Ext.P10.
5. The petitioner, therefore, prays that Exts.P5, P8 and P10
be set aside and the KSEB be directed to disburse to him the
amount of Rs.1,13,508/-, which has been now withheld from his
retiral benefits, with interest.
6. I have heard Sri.Sudhin Kumar, learned counsel for the
petitioner and Sri.M.K.Thankappan, learned Standing Counsel
appearing for the KSEB.
7. Sri.M.K.Thankappan, countered the afore submissions
made on behalf of the petitioner, by arguing that Ext.P5 notice
was issued to the petitioner informing that the Disciplinary WP(C) NO. 17484 OF 2014
Authority had disagreed with the findings of the Enquiry Officer.
He added that, through the same, petitioner was asked to show
cause why an amount of Rs.1,02,035/-, along with interest, be not
recovered from him; and that based on the petitioner's explanation,
namely Ext.P6, Ext.P8 order was issued by the said Authority,
confirming the said proposal. He submitted that, as is evident from
Ext.P8, the case of the petitioner was thoroughly considered, but it
was found that he had committed supervisory lapses, in having
failed to detect the 'erroneous connection' of a particular
consumer, thereby, causing huge monetary loss to the Board. He,
thereafter, submitted that Ext.P10 order of the Chairman and
Managing Director of the KSEB was also issued after considering
all relevant aspects; and therefore, prayed that this writ petition
be dismissed.
8. When I consider the afore submissions and the materials
available on the records of this case, it is evident that the Enquiry
Authority found the petitioner to be not guilty at all. In fact, said
Authority has also, in Ext.P4 report referred to the evidence of
DW2 - a certain Sri.M.S.Xavier, to hold that the "malpractices in
the electric meter" in question must have happened between
December 2006 and August 2007; thus concluding that "error in WP(C) NO. 17484 OF 2014
potential connection might have happened only after 08-04". (sic).
9. It is also relevant that the Enquiry Officer has recorded
that the consumer was "prone to violation of Rules" and that
"silence regarding proper sealing of metre in the site mahazar
prepared on 04.09.2007 assumes added significance" (sic).
10. As I have said above, the Enquiry Officer, thereafter,
proceeded to honourably exonerate the petitioner, without any
liability.
11. However, the Disciplinary Authority then issued Ext.P5
proceedings, wherein, he recorded that "undersigned decided to
disagree with the findings of the enquiry officer" (sic) and
consequently that the "undersigned decided to apportion the
liability of Rs.6,61,683/- [Rs.12,49,854 (total liability) -
Rs.5,88,171/- (bill issued to the consumer)] in such a way that 25%
of the liability to be realized from the Assistant Engineer who
supervised the meter change on 08.01.2001 and balance 75% of
liability from all the officials responsible for the under-recording,
divided according to the period they dealt the consumer. (sic)
12. However, what is important at this juncture is that the
Disciplinary Authority did not issue any notice to the petitioner
before he proposed the punishment; but Ext.P5 was a post- WP(C) NO. 17484 OF 2014
decisional one, notifying him to show cause why the amounts
proposed be not recovered from him.
13. It is now well established in the annals of Administrative
Law that when the Disciplinary Authority decides to disagree with
the findings of the Enquiry Officer, the delinquent will have to be
specifically notified before a decision detrimental to him is taken.
14. However, in the case at hand, what has been done is
completely contrary, since the Disciplinary Authority took a
decision to the detriment of the petitioner and then asked him to
show cause why the amounts fixed be not recovered.
15. The records show that the petitioner, thereafter,
preferred Ext.P6 explanation to Ext.P5; but that the Disciplinary
Authority again reiterated what he stated in Ext.P5, through
Ext.P8, holding that petitioner is liable to repay the amounts as
proposed by him.
16. Pertinently, Ext.P8 makes it absolutely clear that what
was decided by the Disciplinary Authority consequent to Ext.P6
explanation was only as to whether punishment was required to be
imposed against the petitioner; rendering it limpid that his
decision regarding the guilt of the petitioner had been finalized
earlier.
WP(C) NO. 17484 OF 2014
17. That said, when the petitioner preferred statutory
appeal against the order of the Disciplinary Authority, it has been
rejected through Ext.P10, merely saying that, on a perusal of the
appeal petition and connected files, it has been found that the
petitioner is liable for the loss and that same has been fixed based
on the report of his Controlling Officer, which had been informed
to him by the Disciplinary Authority before finalizing his case.
18. As I have said above, Ext.P5 cannot find favour in law
because it is a post-decisional notice, after having found the
petitioner guilty of the charges - with the Disciplinary Authority
disagreeing with the Enquiry Authority. The said notice did not ask
the petitioner to show cause why the findings of the Enquiry
Officer be not disagreed with by the Disciplinary Authority, but
only to show cause why the amounts fixed as penalty be not
recovered from him.
19. At this time, it must also be borne in mind that the
Disciplinary Authority appears to have been guided by the fact that
large amounts of money had been lost to the Board on account of
the erroneous consumption record of a consumer, to an extent of
Rs.5,88,171/-.
20. However, it is conceded before me that the consumer WP(C) NO. 17484 OF 2014
had approached this Court by filing W.P.(C)No.26581/2009, in
which, certain amounts were directed to be paid as a condition for
obtaining interim order, which he did. It is further stated that said
writ petition was dismissed, through judgment dated 04.03.2014,
and consequently that said consumer became fully liable for the
amounts.
21. This being so, I fail to understand how the petitioner can
be held responsible for any loss to the KSEB; and, in any event of
the matter, the amount of Rs.5,88,171/- shown in Ext.P5 cannot be
now fastened on him because, admittedly, the consumer had
remitted some portion of it as per the interim direction of this
Court in W.P.(C)No.26581/2009 and may have paid off the balance
subsequent to the dismissal of the writ petition.
22. I, however, see that none of these aspects have been
considered in its proper perspective by the Appellate Authority, but
he has merely proceeded to grant imprimatur to Ext.P8 order of
the Disciplinary Authority, perhaps being guided by the fact that at
that time also, the consumer had not remitted the amounts noticed
to have been lost to the KSEB.
23. I am resultantly, of the firm view that the Appellate
Authority must reconsider the entire matter, particularly the WP(C) NO. 17484 OF 2014
contention of the petitioner that Ext.P5 has been issued without
any notice to him with respect to the finding of guilt by the
Disciplinary Authority and that no loss has now been caused to the
KSEB, consequent to the fact that W.P.(C)No.26581/2009 had been
dismissed.
In summation, this writ petition is allowed and Ext.P10 is set
aside; with a consequential direction to the Chairman and
Managing Director of the KSEB to reconsider the appeal preferred
by the petitioner, adverting to my observations above and taking
into account the recovery made from the consumer in question
consequent to the dismissal of W.P.(C)No.26581/2009, thus leading
to an appropriate order thereon and also after affording an
opportunity of being heard to the petitioner, as expeditiously as is
possible but not later than than three months from the date of
receipt of a copy of this judgment.
I make it clear that while the afore exercise is completed, the
Appellate Authority will consider each of the contentions of the
petitioner, including that he was not in charge of the Section,
while tampering of the meter happened; and will also specifically
assess the findings of the Enquiry Officer in the context of the
petitioner's assertions that he cannot be held responsible on WP(C) NO. 17484 OF 2014
account of the fact that tampering or error in the meter was found
to have happened after he left the office concerned.
At this time, Sri.Sudhin Kumar pointed out that, in Ext.P7, the
Electricity Ombudsman has recorded the statement of the KSEB
that in normal circumstances, their staff like Sub Engineers, Meter
Readers or Field Officers, who visit the premises of the consumer
could not have found out such abnormalities, since the seals of the
meter box were found intact. Certainly, this will also be kept in
mind by the Appellate Authority, while the afore directed exercise
is completed.
The above being so ordered, it goes without saying that,
depending upon the decision to be taken by the Appellate Authority
in terms of my directions above, the petitioner's balance retiral
benefits shall be paid to him, without any avoidable delay, but not
later than two months thereafter; failing which, it will carry
interest @ 8% per annum, from the date on which it became due
until it is actually paid.
This writ petition is thus ordered.
Sd/-
DEVAN RAMACHANDRAN JUDGE rp WP(C) NO. 17484 OF 2014
APPENDIX OF WP(C) 17484/2014
PETITIONER EXHIBITS
EXHIBIT P1 : TRUE COPY OF THE MEMO OF CHARGES ALONG WITH STATEMENT OF ALLEGATIONS GIVEN TO THE PETITIONER ON 04.02.2008
EXHIBIT P2 : TRUE COPY OF THE WRITTEN STATMENT OF DEFENCE FILED BY THE PETITINER BEFORE THE 3RD RESPONDENT DATED 13.05.2008
EXHIBIT P3 : TRUE COPY OF THE ORDER NO.EB3/DIS. ACTION/KIDANGARA/2007- 08/2298 DATED 17.10.2008 ISSUED BY THE 3RD RESPONDENT
EXHIBIT P4 : TRUE COPY OF THE ENQUIRY REPORT FILED BY THE ENQUIRY OFFICER DATED 10.12.2010
EXHIBIT P5 : TRUE COPY OF THE NOTICE NO.EBVS.4/7/2011/445 DATED 08.06.2012 ISSUED BY THE 2ND RESPONDENT
EXHIBIT P6 : TRUE COPY OF THE REPLY FILED BY THE PETITIONER DATED 18.07.2012
EXHIBIT P7 : TRUE COPY OF THE ORDER OF THE STATE ELECTRICITY OMBUDSMAN IN REPRESENTATION NO P 45/09 DATED 27.07.2009
EXHIBIT P8 : TRUE COPY OF THE ORDER NO.EBVS/4/7/2011/612 DATED 07.8.2012 ISSUED BY THE 2ND RESPONDENT
EXHIBIT P9 : TRUE COPY OF THE ORDER NO PA V/PPO/39463/705 DATED 22.03.2014 ISSUED BY THE 2ND RESPONDENT
EXHIBIT P10 : TRUE COPY OF THE ORDER NO.VIG./BIII/7478/2007/1421 DATED 10.06.2014 ISSUED BY THE FIRST RESPONDENT
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!