Citation : 2021 Latest Caselaw 15124 Ker
Judgement Date : 20 July, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
TUESDAY, THE 20TH DAY OF JULY 2021/29TH ASHADHA, 1943
WP(C) NO. 2701 OF 2021
PETITIONERS:
1 SEETHI SAJAR @ SAJAR N.S., AGED 49 YEARS,
S/O LATE SEETHI, 16/1034 C SITHARA HOUSE,
THOPPUMPADI, THOPPUMPADI P.O.,
ERNAKULAM-682 005.
2 SEETHI KABEER @ S KABEER, AGED 53 YEARS,
S/O LATE SEETHI, 16/1034 C SITHARA HOUSE,
THOPPUMPADI, THOPPUMPADI P.O.,
ERNAKULAM-682 005.
BY ADVS.
BABU KARUKAPADATH
SMT.M.A.VAHEEDA BABU
SHRI.P.U.VINOD KUMAR
SMT.ARYA RAGHUNATH
SMT.VAISAKHI V.
SRI.T.M.MUHAMMED MUSTHAQ
SHRI.MOHAMED HISHAM P
RESPONDENTS:
1 CORPORATION OF KOCHI
ERNAKULAM-682 011,
REPRESENTED BY ITS SECRETARY
2 THE SECRETARY,
CORPORATION OF KOCHI,
ERNAKULAM-682 011.
3 THE VILLAGE OFFICER,
THOPPUMPADY VILLAGE OFFICE,
KAZHUTTUMUTTU, ERNAKULAM-682 005.
4 INDIAN OIL CORPORATION LTD,
PANAMPILLY AVENUE, PANAMPILLY NAGAR,
KOCHI-682 036, REPRESENTED BY
ITS TERRITORY MANAGER.
WP(C) No.2701/2021
:2 :
BY ADVS.
R1-R2 SRI.ARUN ANTONY
R3 GOVT.PLEADER SRI.MANU RAJ
R4 SRI.M.GOPIKRISHNAN NAMBIAR
R4 SRI.K.JOHN MATHAI
R4 SRI.JOSON MANAVALAN
R4 SRI.KURYAN THOMAS
R4 SRI.PAULOSE C. ABRAHAM
R4 SRI.RAJA KANNAN
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR
ADMISSION ON 20.07.2021, THE COURT ON THE SAME DAY
DELIVERED THE FOLLOWING:
WP(C) No.2701/2021
:3 :
JUDGMENT
~~~~~~~~~
Dated this the 20th day of July, 2021
The petitioners wanted to start an LPG Distribution
agency for which the 4th respondent issued Ext.P1 Letter of
Intent on 10.01.2019. The petitioners state that there were
two existing buildings in the land where they proposed to start
the business, as is evident from Ext.P5. The petitioners made
certain alterations to the existing building. The Assistant
Engineer of the 1st respondent-Kochi Corporation issued
Ext.P3 show-cause notice to the 1 st petitioner alleging that the
construction work now made is in violation of the Building
Rules. To Ext.P3 show-cause notice, the 1 st petitioner gave
Ext.P4 explanation. The petitioners also submitted Ext.P6
application for regularisation of the construction of the building
on 20.02.2020.
WP(C) No.2701/2021
2. As no action was taken on Ext.P6, the petitioners
approached this Court filing W.P.(C) No.24294/2020 and this
Court directed the 2nd respondent to consider Ext.P6
application submitted by the petitioners for regularisation of
the building. Respondents 1 and 2, however, rejected the
application submitted by the petitioners for regularisation of
construction, as per Ext.P11. The rejection as per Ext.P11 is
based on two factors. Firstly, it was stated that the petitioners'
building does not satisfy requisite access width. Secondly, the
building set back is not as required under the Kerala
Municipality Building Rules. It is challenging the said Ext.P11
order that the petitioners have approached this Court.
3. The learned counsel for the petitioners submitted
that the road has a width of 6.5 metres as per Ext.P16 Road
Register maintained by the Corporation themselves. This
Court has held in Ext.P12 judgment in W.A. No.249/2016 that
if originally a road has the requisite width, the subsequent
encroachment over the road made by the third parties cannot
be a reason for the Local Self Government to decline a WP(C) No.2701/2021
building permit for want of access width. The learned counsel
for the petitioners further pointed out that as per Ext.R1(e)
Site Inspection Report of the Executive Engineer, the gas
godown is situated in a small portion of the petitioners' leased
land and the shifting of boundary wall is in progress for getting
the required set back of 7.5 metres in the north side. The
petitioners would submit that as of now, the requisite set back
is available and their application for regularisation cannot be
rejected on that ground.
4. The learned Standing Counsel appearing for the
respondent-Corporation opposed the writ petition vehemently
and contended that access width is required taking into
account safety of the godown as well as the citizens residing
nearby. It is required for easy access for firefighting
measures. A gas godown indeed is a hazardous activity and
access width to the godown is very important. That
requirement cannot be watered down. According to the
learned Standing Counsel for the Corporation, the physical
availability of requisite access width is sine qua non for issuing WP(C) No.2701/2021
a building permit or for regularisation of an illegal construction.
5. The learned Standing Counsel for the Corporation
pointed out that the petitioners have not so far obtained Fire
NOC from the concerned Department and respondents 1 and
2 will not be able to entertain the application for regularisation
in the absence of Fire NOC issued by the competent authority.
For that reason also, the petitioners' application cannot be
considered. The learned Standing Counsel further pointed out
that at the time of inspection, admittedly there was no
sufficient set back for the godown building. Prescribed set
back is also a requirement under the Kerala Municipality
Building Rules and as long as sufficient set back is not made
available, the question of regularisation of the construction
does not arise. For the above reason, the writ petition is liable
to be dismissed, contended the learned Standing Counsel for
respondents 1 and 2.
6. Heard the learned counsel for the petitioners, the
learned Standing Counsel appearing for respondents 1 and 2,
the learned Government Pleader representing the 3 rd WP(C) No.2701/2021
respondent and the learned Standing Counsel for the 4 th
respondent-IOCL.
7. As regards the access width, a Division Bench of
this Court in Ext.P12 judgment in W.A. No.249/2016
considered the matter and held that if originally the road had
sufficient access width, the rejection of such access width due
to the subsequent encroachments cannot be a reason for
denying building permits. In paragraph 5 of Ext.P12 judgment,
a Division Bench of this Court held as follows:-
"5. Having considered, we find force in the submission. It is not denied that originally the road is shown to have a width of 8 metres. It appears that due to encroachments, the width of the road is reduced to less than 8 metres now. But that does not mean that right of a person to establish his industry which is conditioned upon an approach road of 8 metres can be denied. It would be something like saying that because the Panchayat has failed in its duty to keep the road free of encroachment, a person is denied his right to use his land in the manner he would like. For default of another, the right of a person cannot be frustrated."
The judgment of the Division Bench will squarely apply to the
case. If originally in the records of the Corporation the road
has the requisite access width, the Corporation will have to WP(C) No.2701/2021
accept the regularisation request. It will be the duty of the
Corporation to remove encroachments, if any, on the road and
maintain the width of the road as contained in their Registers.
According to the learned counsel for the petitioners,
subsequent to the amendment to Rule 28, the requisite
access width as on date is 6 metres. Ext.P16 would show that
the road in question has 6.5 metres width. Therefore,
respondents 1 and 2 are liable to reconsider that issue in the
light of Ext.P12 judgment.
8. As far as the issue of set back is concerned, the
Executive Engineer of the 1st respondent-Corporation has
found in Ext.R1(e) that the shifting of boundary wall is under
progress, for getting the required set back of 7.5 metres in the
north side. The learned counsel for the petitioners submits
that that shifting is completed and as on date, sufficient set
back space is made available.
9. In view of the above, this writ petition is disposed of
directing respondents 1 and 2 to reconsider Ext.P6 application
for regularisation in the light of Ext.P12 Division Bench WP(C) No.2701/2021
judgment of this Court and also taking into account Ext.R1(e)
Site Inspection Report of the Executive Engineer.
Respondents 1 and 2 shall cause inspection of the premises
for satisfying the set back before taking a decision in the
matter. The final order by the Corporation in this regard shall
be passed within a period of two months. To enable
respondents 1 and 2 to take an independent decision in the
matter afresh taking into consideration the subsequent
developments, Ext.P11 order is set aside.
If Ext.P1 Letter of Intent issued by the 4 th
respondent is still in force, the 4 th respondent shall maintain
status quo as regards Ext.P1 for a period of two months. The
learned Standing Counsel representing the 4 th respondent
pointed out that the petitioners have not so far obtained Fire
NOC. The petitioners undertake that Fire NOC will be
obtained and produced before the authorities as soon as it is
received.
Sd/-
N. NAGARESH, JUDGE
aks/22.07.2021 WP(C) No.2701/2021
APPENDIX OF WP(C) 2701/2021
PETITIONER'S EXHIBITS
EXHIBIT P1 A TRUE COPY OF THE LETTER OF INTENT DATED 10/01/2019 ISSUED BY THE IOC TO THE PETITIONER EXHIBIT P2 A TRUE COPY OF THE RECEIPT DATED 2.4.2019 RECEIVED ONLINE FROM THE 1ST RESPONDENT, EVIDENCING SUBMISSION OF APPLICATION SEEKING PERMIT FOR ROOF CHANGING EXHIBIT P3 A TRUE COPY OF THE SHOW CAUSE NOTICE DATED 7.9.2019 UNDER SECTION 406(10 OF THE KERALA MUNICIPALITY ACT, ISSUED TO THE 1ST PETITIONER FROM THE 1ST RESPONDENT CORPORATION EXHIBIT P4 A TRUE COPY OF THE WRITTEN EXPLANATION DATED NIL, SUBMITTED BY THE PETITIONERS AT THE TIME OF HEARING ON 28.11.2020 EXHIBIT P5 A TRUE COPY OF THE ASSESSMENT DETAILS WITH RESPECT TO THE BUILDING DATED 24/1/2020, ISSUED BY THE 1ST RESPONDENT CORPORATION.
EXHIBIT P6 A TRUE COPY OF THE RELEVANT PORTION OF
THE APPLICATION FOR BUILDING
PERMIT/REGULARIZATION 20.2.2020
SUBMITTED BY THE PETITIONERS BEFORE THE 1ST RESPONDENT CORPORATION EXHIBIT P7 A TRUE COPY OF THE SHOW CAUSE NOTICE DATED 1.10.2020 PROPOSING TO CANCEL THE LETTER OF INTENT ISSUED TO THE 1ST PETITIONER BY THE 4TH RESPONDENT IOC.
EXHIBIT P8 A TRUE COPY OF THE REQUEST DATED
14.10.2020 SUBMITTED BY THE 1ST
PETITIONER BEFORE THE 4TH RESPONDENT
IOC
EXHIBIT P9 A TRUE COPY OF THE NOC DATED 20.10.2020
ISSUED BY THE KERALA ZONE MANAGEMENT
AUTHORITY IN FAVOUR OF THE PETITIONERS WP(C) No.2701/2021
EXHIBIT P10 A TRUE COPY OF THE JUDGMENT DATED 23.11.2020 OF THIS HON'BLE COURT IN WPC NO 24294/2020 EXHIBIT P11 A TRUE COPY OF THE INTIMATION/ORDER DATED 8.1.2021 ISSUED BY THE 2ND RESPONDENT TO THE 1ST PETITIONER ON 29.1.2021 EXHIBIT P12 A TRUE COPY OF THE JUDGMENT DATED 31.10.2017 IN WA NO 249/2016 OF THIS HON'BL COURT EXHIBIT P13 A TRUE COPY OF THE JUDGMENT DATED 6.12.2017 IN WPC NO 38929/2015 OF THIS HON'BLE COURT
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!