Citation : 2021 Latest Caselaw 13873 Ker
Judgement Date : 6 July, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE C.T.RAVIKUMAR
&
THE HONOURABLE MR.JUSTICE MURALI PURUSHOTHAMAN
TUESDAY, THE 6TH DAY OF JULY 2021 / 15TH ASHADHA, 1943
DBP NO. 58 OF 2020
IN THE MATTER OF TRAVANCORE DEVASWOM BOARD - TDB
PROCEEDINGS INITIATED - REG.
------------
PETITIONER/S:
THE TRAVANCORE DEVASWOM BOARD
REPRESENTED BY ITS EXECUTIVE ENGINEER,
MAVELIKKARA
BY ADV G.BIJU
RESPONDENT/S:
THE DEPUTY DIRECTOR
LOCAL FUND AUDIT,
THIRUVANANTHAPURAM
BY ADV GOVERNMENT PLEADER,
SRI. T.K. ANANDAKRISHNAN
SRI. P.RAMACHANDRAN (AMICUS CURIE)
THIS DEVASWOM BOARD PETITION HAVING COME UP FOR
ADMISSION ON 06.07.2021, THE COURT ON THE SAME DAY
DELIVERED THE FOLLOWING:
-2-
DBP No.58 of 2020
JUDGMENT
Ravikumar, J.
TDB Report No.47 of 2020 of the learned Ombudsman for
Travancore and Cochin Devaswom Board in Petition No.21 of
2019 led to the registration of the above mentioned DBP. As per
petition No.21 of 2019 the Travancore Devaswom Board applied
for approval of the revised estimate as also sanction for payment
of final bill to the contractor for the work of construction of an
indoor stadium attached to Devaswom Board College, Parumala
in Thiruvalla Group. Obviously, earlier appropriate
sanction/approval was given for the original estimate of
Rs.65,80,000/-. The revised estimate is for Rs.71,45,335/-. The
estimate was prepared for the project based on SOR-2012. The
learned Ombudsman in the report sounded a caution with
respect to the care to be taken in future while preparing or while
filing the Maramath Petition seeking approval for estimate. It is
only apposite to extract paragraph 3 in this regard and it reads
DBP No.58 of 2020
thus:-
"3. Though there is only a marginal excess over the estimate already sanctioned, it is to be noticed that the admission by the Engineering Department that all the items and quantities were not properly taken into account, shows that while the Maramath Petition was filed, the estimate prepared was not correct. This shall not be repeated, as the preparation of the estimate for sanction by the Honourable High Court has to be after proper evaluation by the Engineering Department. More care shall be taken in this regard."
2. It would reveal that the Engineering Department
admitted that all the items and quantities were not properly
taken in to account before the Maramath petition was filed. It is
in the said circumstances that the learned Ombudsman had to
observe that the Engineering Department of the Devaswom shall
make a proper evaluation and the prepare the estimate before
moving the Maramath petition as any estimate prepared without
such evaluation is bound to be incorrect. We are in full
agreement with the said suggestion made by the learned
Ombudsman and in such circumstances, we order that the
Engineering Department of the TDB shall hereafter strictly
DBP No.58 of 2020
adhere to the suggestions made in paragraph 3 of the TDB Report
No.47 of 2020. That apart, in paragraph 4 of the report, it is
stated that the records would reveal that the soil test was done
only after preparation of the estimate and that it necessitated to
revise the estimate. Furthermore, it is stated that the nature of
the bricks for construction was to be changed at the time of
execution was also a reason for the increase in the estimated
cost. Taking note of the aforesaid aspects pointed out by the
learned Ombudsman in the report, this court directed the Chief
Engineer of the TDB to file an affidavit touching those aspects.
3. The very fact is that Petition No.21 of 2019 is a
consolidated one for approval of the revised estimate and
sanction for the payment of final bill to the contractor itself, is a
matter of concern and at any rate, it cannot be appreciated. The
learned Amicus Curie to the learned Ombudsman would submit
that in fact, such an application was filed about an year after the
completion of the construction. The TDB is expected to get
DBP No.58 of 2020
prepared the estimate for any particular project first and only on
approval of the estimate, in case it exceeds Rs.20 lakhs, that the
work could be commenced. True that in the case on hand for the
original estimate of Rs.65,80,000/- approval was obtained. But
then, we are at loss to understand as to how and under what
circumstances construction in excess of estimated amount was
permitted to be done. Above all, there is no justification in
moving an application for approval of the revised estimate much
after the completion of the construction. Taking note of the
observation of the learned Ombudsman in paragraph 4 of the
TDB report, we directed the Chief Engineer to file an affidavit
and in the affidavit filed in compliance with the said direction,
by way of an explanation, it is stated that the project in question
is one where the major portion of the fund is coming from the
University Grands Commission and in fact, UGC has allotted an
amount of Rs.40 lakhs for the said project. If the work of the
project was not commenced and completed in time, the fund
DBP No.58 of 2020
allotted by the UGC would have to be refunded with interest. It
is such circumstances that is assigned as a reason for preparing
the estimate before conducting the soil test. Furthermore, it is
stated that the work had commenced on 22.09.2015 and the soil
test was conducted on 20.12.2015, but before deciding the type of
foundation and the execution of the foundation work. After
stating so in paragraph 5, the Chief Engineer went on to state
thus: -
"As per the result of the soil test, it was recommended to provide stepped footings over metal cushioning instead of normal trapezoidal column footings. The foundation footing was done as per the recommendation of the structural analysis and hence the stability and safety of the structure are assured."
4. The project in question is an indoor stadium for a
college. In the order dated 05.03.2021 itself, taking note of that
fact, we made an observation as hereunder:
"When that be the work, we are at a loss to understand as to how the estimate could have been prepared and work could have been awarded without conducting soil test which was absolutely essential ad inevitable to assess and ascertain the stability of the site."
DBP No.58 of 2020
5. It is of common knowledge the nature of the
foundation to be laid would depend upon the nature of the soil.
Hence, an estimate without conducting the soil test, especially in
respect of a stadium, besides being inaccurate, can lead to
casualty in case of commencement of actual construction before
soil test. True that the affidavit dated 23.03.2021 filed by the
Chief Engineer TDB would now give the impression that though
the estimate was prepared before conducting the soil test the
actual work, including laying of foundation was commenced only
as per the recommendation for the structural analysis after the
soil test. We have no hesitation to hold that whatever be the
urgency or the concern of TDB in respect of any work of like
nature, preparation of estimate and actual commencement of the
work can only be after the conduct of the soil test. Only after
conducting the soil test suitability and feasibility of construction
of any structure in any given site can be decided. Ignoring
relevance and importance of soil test or taking it lightly cannot
DBP No.58 of 2020
be appreciated. It is only to be condemned. Preparing an
estimate and awarding contract before conducting the soil test
cannot be a matter that can be approved. We make it clear that
in case of occurrence of any such incident in future will be
viewed very seriously an needless to say that, in such eventuality
the persons responsible for such instances would have to be
proceeded with in accordance with law.
6. Reverting to the case on hand, as already noticed, the
affidavit would explain the circumstances as to why a revision of
the estimate became essential. As noticed by the learned
Ombudsman, there is no huge difference between the original
estimate and the revised estimate. Taking into consideration the
said aspect and also the circumstances that necessitated the
preparation of a revised estimate, we are inclined to allow the
application. We are also persuaded to allow this application in
view of the specific assurance given by the Chief Engineer that
the construction was actually commenced only after conducting
DBP No.58 of 2020
the soil test and in strict terms of the recommendations of the
structural analysis. Consequently, petition No.21 of 2019 will
stand allowed. If the account in respect of the project in question
was not already subjected for audit, after completion of work it
shall be subjected to audit, in accordance with law, expeditiously,
at any rate, within a period of one month.
DBP is ordered accordingly.
Sd/-
C.T.RAVIKUMAR Judge
sd/-
MURALI PURUSHOTHAMAN Judge
das
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!