Citation : 2021 Latest Caselaw 848 Ker
Judgement Date : 11 January, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE ANIL K.NARENDRAN
MONDAY, THE 11TH DAY OF JANUARY 2021 / 21TH POUSHA, 1942
Con.Case(C).No.1818 OF 2020 IN WP(C). 6666/2017
PETITIONER/2ND & 3RD PETITIONERS:
1 M.G.MATHEW
AGED 58 YEARS
HIG-31, PANAMPILLY NAGAR, KOCHI-682 036
2 SUMA JACOB KORAH,
HIG- 32, PANAMPILLY NAGAR, KOCHI-682 036
BY ADVS.
SRI.P.DEEPAK
SRI.K.VIDYASAGAR
RESPONDENT/5TH RESPONDENT:
SHAREEN HAFEES
W/O. ABDUL WAHAB HAFEES, DOOR NO. TC 31/555, SHALIMAR
HOUSE, VELLAYAMBALAM,
THIRUVANANTHAPURAM-695 010, (RESIDING AT GARDEN
HEIGHTS, APART NO. 1, TC 4/1783-6, BELL HAVEN
GARDENS, KOWDIAR, THIRUVANANTHAPURAM-695 003
R1 BY ADV. SRI.K.I.MAYANKUTTY MATHER
R1 BY ADV. KUM.NARAYANI HARIKRISHNAN
OTHER PRESENT:
SMT DONA AUGUSTINE- ADVOCATE COMMISSIONER
THIS CONTEMPT OF COURT CASE (CIVIL) HAVING COME UP FOR
ADMISSION ON 11.01.2021, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
Con.Case(C).No.1818 OF 2020 IN WP(C). 6666/2017
2
JUDGMENT
The petitioners have filed this contempt case alleging violation
of Annexure-A1 order of this Court dated 25.07.2019 in W.P.(C)
No.6666 of 2017, whereby this Court granted an interim order
restraining the respondent herein, who is the 5 th respondent in that
writ petition, from proceeding further with the construction in the
land in question, on the strength of Ext.R5(k) building permit,
pending disposal of that writ petition. Paragraphs 13 to 15 of that
order reads thus:
"13. Having considered the pleadings and materials on record and also the submissions made by the learned counsel on both sides, this Court finds that, when the title of the 5 th respondent is in serious dispute, on account of the fact that the land originally owned by the 3 rd respondent, which is Public Trust, was sold on the strength of a resolution stated to have been passed on 08.05.2016, the 5th respondent cannot be permitted to carry out any further construction on the strength of Ext.R5(k) building permit dated 06.02.2019 granted by the Municipal Corporation.
14. In the result, there will be an interim order restraining the 5th respondent from proceeding further with the construction in the land in question, on the strength of Ext.R5(k) building permit, pending disposal of this writ petition.
15. The Secretary of the 2nd respondent GCDA shall file an Con.Case(C).No.1818 OF 2020 IN WP(C). 6666/2017
additional counter affidavit, explaining the facts and circumstances, with specific reference to Ext.R4(b) communication dated 16.01.2006."
2. The respondent has filed a reply affidavit dated
15.11.2020 in this contempt case.
3. On 18.11.2020, when this contempt case came up for
consideration, the learned counsel for the petitioner submitted that
an application shall be filed to depute an Advocate Commissioner to
conduct a local inspection.
4. On 23.11.2020, after considering the submission made
by the learned counsel on both sides, this Court appointed
Smt.Dona Augustine, a lawyer of this Court, as Advocate
Commissioner, to conduct inspection of the building in question,
with notice to the learned counsel for the petitioners and also to
the learned counsel for the respondent and submit a report before
this Court within two weeks, with specific reference to the matters
enumerated in the work memo to be filed by the learned counsel on
both sides. Pursuant to that order, the report of the Advocate
Commissioner is placed on record on 18.12.2020.
5. After the report of the Advocate Commissioner, the
respondent has filed a written objection/explanation, in the form of Con.Case(C).No.1818 OF 2020 IN WP(C). 6666/2017
an affidavit, on 04.01.2021. Paragraph 4 of that affidavit reads
thus:
"4. We are presently in Dubai since the last few months. I have verified with the caretaker and Project Engineer about the masonry covering of the pipe in the sunshade portion (as could be seen from Annexure C2) and could learn that the pipe was covered subsequent to the order of this Hon'ble Court. This was so done when the said pipe joint got broken/loosened due to the then heavy rains and when water started flowing into the basement floor where the electrical room is established. They had done the plastering over the pipe only to prevent the flooding of water into the basement floor and it was so done by the Project Engineer and the caretakers at their volition to cover the broken pipe with cement and brick pieces. They neither thought nor did intend such work as one tantamount to violation of the court order. They have done so only with the good intention and I came to know about the same (the said works) only after the filing of the contempt of court case. I unconditionally offer my apologies to the said acts of my caretakers and I am prepared to restore the anterior position of the pipe after removing the masonry work, which is only of a length of about two meters."
6. Heard the learned counsel for the petitioner, learned
counsel for the respondent and also the learned Advocate
Commissioner.
7. Having considered the submissions made by the learned Con.Case(C).No.1818 OF 2020 IN WP(C). 6666/2017
counsel on both sides, this Court finds that in view of the
unconditional apology tendered by the respondent, no further
proceedings need be taken in this contempt case, since the writ
petition is still pending consideration.
Therefore, this contempt case is closed recording the
unconditional apology made by the respondent.
Sd/-
ANIL K.NARENDRAN
JV JUDGE
Con.Case(C).No.1818 OF 2020 IN WP(C). 6666/2017
APPENDIX PETITIONER'S/S EXHIBITS:
ANNEXURE A1 TRUE COPY OF THE ORDER IN W.P.(C) NO.
6666/2017 DATED 25.07.2019 ON THE FILE OF THE HON'BLE HIGH COURT OF KERALA.
ANNEXURE A2 VIDEO RECORDINGS OF THE CONSTRUCTION ACTIVITIES BEING CARRIED OUT IN THE PLOT IN VIOLATION OF ANNEXURE A1 ORDER IN DVD FORMAT.
RESPONDENTS' EXHIBITS:
ANNEXURE B1 PHOTOGRAPHS OF THE BUILDING
ANNEXURE B1(A) PHOTOGRAPHS OF THE BUILDING
ANNEXURE B1(B) PHOTOGRAPHS OF THE BUILDING
ANNEXURE B1(C) PHOTOGRAPHS OF THE BUILDING
ANNEXURE B1(D) PHOTOGRAPHS OF THE BUILDING
ANNEXURE B1(E) PHOTOGRAPHS OF THE BUILDING
ANNEXURE B1(F) PHOTOGRAPHS OF THE BUILDING
ANNEXURE B1(G) PHOTOGRAPHS OF THE BUILDING
ANNEXURE B1(H) PHOTOGRAPHS OF THE BUILDING
ANNEXURE C1 A TRUE COPY OF THE NOTICE DATED 01.12.2020
ANNEXURE C2 TRUE COPY OF THE PHOTOGRAPH OF HTE WORK REFERRED IN ANNEXURE A2
ANNEXURE C3 TRUE COPY OF HTE PHOTOGRAPH SHOWING HTE ENTRANCE TO THE SITE
ANNEXURE C4 COMPACT DISK WITH VIDEOGRAPHS RECORDED DURING INSPECTION
ANNEXURE C5 TRUE COPY OF THE ELECTRICITY BILLS PROVIDED BY THE RESPONDENT Con.Case(C).No.1818 OF 2020 IN WP(C). 6666/2017
ANNEXURE C6 TRUE COPY OF THE PHOTORGRAPH
ANNEXURE C7 TRUE COPY OF THE PHOTOGRAPHS PROVIDED BY THE RESPONDENT
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!