Citation : 2021 Latest Caselaw 1228 Ker
Judgement Date : 13 January, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
WEDNESDAY, THE 13TH DAY OF JANUARY 2021/23TH POUSHA, 1942
WP(C).No.6558 OF 2019(T)
PETITIONERS:
1 JOJO THOMAS, AGED 47, S/O. THOMAS,
CHAKINIYANKAL HOUSE, CHEPUKULAM P.O.,
UDUMBANNUR, THODUPUZHA, IDUKKI-685 581.
2 VINOD O. GOPINATH, AGED 42,
S/O. GOPINADHAN, OLIYANIKAL HOUSE,
CHEENIKUZHI P.O., IDUKKI-685 595.
BY ADV. SRI.G.SREEKUMAR (CHELUR)
RESPONDENTS:
1 THE STATE OF KERALA REP. BY
THE SECRETARY TO THE GOVERNMENT,
LOCAL SELF GOVERNMENT DEPARTMENT,
GOVERNMENT SECRETARIAT,
THIRUVANANTHAPURAM-695 001.
2 THE KERALA STATE RURAL ROADS DEVELOPMENT
AGENCY, REP. BY ITS MEMBER SECRETARY,
HAVING ADDRESS TC 28/855, CSI BUILDINGS,
PULIMOOD JUNCTION, THIRUVANANTHAPURAM-695 001.
3 THE SUPERINTENDING ENGINEER,
KERALA STATE RURAL ROAD DEVELOPMENT AGENCY,
HAVING ADDRESS TC 28/855, CIS BUILDINGS,
PULIMOOD JUNCTION, THIRUVANANTHAPURAM-695 001.
4 EXECUTIVE ENGINEER, PROGRAMME IMPLEMENTATION
UNIT (PIU), POVERTY ALLEVIATION UNIT, (PAU),
DISTRICT PANCHAYATH, PAINAVU, IDUKKI-685 608.
5 ACCREDITED ENGINEER/ASSISTANT ENGINEER,
PRIME MINISTER GRAMEENA SADAK YOGANA,(PMGSY),
ELAMDESOM BLOCK, PAINAVU, IDUKKI-685 603.
R1-R5 BY GOVERNMENT PLEADER SMT. DEEPA NARAYANAN
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON 13.01.2021, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
WP(C) No.6558/2019
:2 :
JUDGMENT
~~~~~~~~~
Dated this the 13th day of January, 2021
The petitioners, who are beneficiaries of
Peringasseri-Chepukulam road, are before this Court seeking
to direct the respondents to complete the procedure and
entrust the work and complete the same in a time bound
manner as far as the construction and maintenance of the
Peringasseri-Chepukulam road, in the interest of justice.
2. The petitioners would contend that on either side of
Peringasseri-Chepukulam road, there are about 150 families
residing. Such families have given land as free surrender for
development of the road. Surrender was made during the
year 2005 and agreement with the contractor was executed in
2009. In the meantime, some disputes arose between the
contractor and the Government and the construction was not
completed. Even as on date, there is no progress in the WP(C) No.6558/2019
construction.
3. The learned counsel for the petitioners would
submit that the beneficiaries of the road had given free
surrender of land incurring substantial loss of property. The
road is not completed because of the administrative lethargy.
The statutory and fundamental rights of the petitioners are
infringed and therefore interference of this Court invoking the
powers under Article 226 of the Constitution of India is
extremely necessary.
4. The learned Government Pleader filed a statement
and an additional statement in the writ petition. The statement
would show that pursuant to the contract, construction of
culverts, retaining walls and GSB and G2 layers were done
before 2011. However, certain disputes arose between the
contractor and the Government with regard to unit rate of
excavation of hard rock. The contractor filed W.P.(C)
No.13821/2012 before this Court. The litigation continued for
seven years. During this period, the Department could not
move further with the work. Due to the delay in execution of WP(C) No.6558/2019
work, the already executed road is completely damaged and
the work has to be restarted from the initial stage. The
statement would proceed to show that the amount required as
on date for construction of the Peringasseri-Chepukulam road
renovation would be ₹2,39,88,819/-.
5. The learned Government Pleader further pointed
out that the construction of this road was undertaken under
centrally sponsored PMGSY-I Scheme. The Government of
India has directed to complete all PMGSY-I works including
the work of Peringasseri-Chepukulam road before
31.12.2020. It was practically impossible for the Government
to rearrange and execute the work within the stipulated time
due to the litigation which was pending. Now that the period
of scheme is over, the funds from the Government of India are
unavailable.
6. In such circumstances, the Government will have to
reconsider the issue and arrange funds needed for the
construction of Peringasseri-Chepukulam road in State
Budget. This is a policy matter and this Court may not give WP(C) No.6558/2019
any positive direction to the Government, contended the
learned Government Pleader.
7. I have heard the learned counsel for the petitioner
and the learned Government Pleader.
8. It is not in dispute that the respondents had
undertaken the Peringasseri-Chepukulam road construction
work under the PMGSY-I Scheme. Though the work was
started as early in the hear 2011, due to a writ petition filed by
the contractor, the work could not be proceeded for about
seven years. The litigation went against the Government and
this Court directed the Government to pay full amount to the
contractor at the rate demanded by him. The judgment of this
Court considerably eroded the funds available for the
construction of the road. With the funds remaining after
complying with the judgment of this Court, the Government
could not have completed the road construction.
9. It is discernible from the pleadings that substantial
amount of funds are required for completion of road
construction. In such circumstances, this Court cannot pass WP(C) No.6558/2019
any positive direction in the matter. However, this Court hope
that since the Government is convinced about the requirement
of construction of Peringasseri-Chepukulam road and since
the citizens have already surrendered their land for
development of the road, due attention will be paid by the
respondents for resuming the work without much delay.
Writ petition is disposed of with the above
observations.
Sd/-
N. NAGARESH, JUDGE
aks/13.01.2021 WP(C) No.6558/2019
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 A TRUE COPY OF THE COMMUNICATION BY THE SUPERINTENDENT ENGINEER, KERALA STATE RURAL ROAD DEVELOPMENT AGENCY, THIRUVANANTHAPURAM DATED 12.3.09
EXHIBIT P2 A TRUE COPY OF THE NOTICE ISSUED AT THE BEHEST OF THE SUPERINTENDING ENGINEER, KSRRDA DATED 12.3.09
EXHIBIT P3 A TRUE COPY OF THE AGREEMENT ENTERED INTO WITH THE CONTRACTOR DATED 12.3.09
EXHIBIT P4 A TRUE COPY OF THE JUDGMENT BY THIS HON'BLE COURT WP(C) NO. 13821 OF 12 DATED 21.10.2015
EXHIBIT P5 A TRUE COPY OF THE REPRESENTATION SUBMITTED TO THE DEVELOPMENT AGENCY DATED NIL.
EXHIBIT P6 A TRUE COPY OF THE COMMUNICATION OF THE CHIEF ENGINEER, KSRRDA DATED 4.10.2018
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!