Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Perumalil Granite ... vs The General Manager
2021 Latest Caselaw 6881 Ker

Citation : 2021 Latest Caselaw 6881 Ker
Judgement Date : 26 February, 2021

Kerala High Court
M/S.Perumalil Granite ... vs The General Manager on 26 February, 2021
WP(C).No.2137 OF 2021(N)
                                     1

            IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                  PRESENT

                 THE HONOURABLE SMT. JUSTICE P.V.ASHA

   FRIDAY, THE 26TH DAY OF FEBRUARY 2021 / 7TH PHALGUNA, 1942

                       WP(C).No.2137 OF 2021(N)


PETITIONER/S:

                M/S.PERUMALIL GRANITE CONSTRUCTIONS
                ARUNNOOTTIMANGALAM POST, KOTTAYAM DISTRICT-686604,
                REPRESENTED BY ITS PROPRIETOR ALEX P.CYRIAC, AGED
                52 YEARS, S/O.LATE P.C.CYRIAC, PERUMALIL HOUSE,
                ARUNNOOTTIMANGALAM, KOTTAYAM.

                BY ADVS.
                S.SHANAVAS KHAN
                SMT.S.INDU

RESPONDENT/S:

      1         THE GENERAL MANAGER, SOUTHERN RAILWAY HEAD QUARTERS
                OFFICE, PARK TOWN, CHENNAI-600003.

      2         THE CHIEF ADMINISTRATIVE OFFICER (CONSTRUCTION),
                SOUTHERN RAILWAY HEAD QUARTERS OFFICE, PARK TOWN,
                EGMORE, CHENNAI-600003, IN CHARGE OF CHIEF
                ADMINISTRATIVE OFFICER (CONSTRUCTION), SOUTHERN
                RAILWAY, ERNAKULAM.

      3         THE DEPUTY CHIEF ENGINEER-I (CONSTRUCTION),
                SOUTHERN RAILWAY, ERNAKULAM, ERNAKULAM, KOCHI-
                682016.

      4         THE CHIEF ENGINEER (CONSTRUCTION) SOUTH,
                SOUTHERN RAILWAY, ERNAKULAM, KOCHI-682016.

                R1-4 BY SRI.P.L.VENU KUMAR, SC, RAILWAYS

     THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
26.02.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C).No.2137 OF 2021(N)
                                         2




                                  JUDGMENT

Dated this the 26th day of February 2021

The petitioner is a railway contractor, who was awarded the

work of "Ernakulam Kottayam Section: Proposed Construction of

Road Over Bridge in lieu of LC No.30 at Km 52/600-700 as 1 x

25.00m Span Composite Girder Super Structure between Ettumanoor

and Kottayam Station (Karthas) and Epoxy Phinolic IPN Coating

for bridge no. 353,332,286 and ROB in lieu of LC No.30", based

on which Ext.P2 agreement was executed on 10.02.2020. Petitioner

submits that he has completed all the work except the launching

of girder. The learned counsel for the petitioner pointed out

that for the purpose of launching girder, sanction is required

from the Commissioner of Railway Safety, as per Section 23 of

Railway Act, 1989 and Chapter 7 of Railways (Opening for Public

Garage for Passengers) Rule 2000. The complaint of the

petitioner is that the respondents are not taking any action for

getting permission from the Commissioner of Railway Safety. The

petitioner has therefore submitted Ext.P3 representation before

the 3rd respondent to expedite the proceedings. The petitioner

pointed out that the period of agreement was only up to

20.08.2020 and that even though the work except the launching of

girder was completed well before that, the agreement was WP(C).No.2137 OF 2021(N)

extended till 31.03.2021 at the request of the 3rd respondent.

2. The learned Standing Counsel for Railways submits that

Commissioner of Railway Safety, Bangalore who is to accord

sanction for launching girder is under another Ministry. It is

stated that the launching of girder is to be carried out with

acute care and caution as it has to be done in live track

ensuring the safety and security of the passengers and all

concerned and therefore the petitioner cannot insist that

permission has to be granted immediately.

3. Learned counsel for the petitioner points out that

tender itself provided for launching of the girder. The tender

was invited on 19.10.2019. Therefore respondents cannot be heard

to contend that sanction would be given in due course or that

petitioner has to wait and has to keep the agreement extended

indefinitely.

4. As rightly pointed out by the learned counsel for the

petitioner, the notice inviting tender issued in 2019 itself

would show that the work tendered was inclusive of the launching

of girder. The respondents who are very well aware of the nature

of the work for which safety measures are required, should have

therefore ascertained the convenience of the CRS.

5. Though sanction from the Commissioner of Railway Safety

is a condition precedent for starting the work in the live

track and it is necessary to ensure the safety and security of

the stake holders petitioner cannot be asked to wait WP(C).No.2137 OF 2021(N)

indefinitely. It is stated that all other works are over by

20.08.2020.

However the learned Standing Counsel submits that the

petitioner has to submit revised specifications in respect of

each girder in the prescribed format as per the latest circular

issued by the Railways. It is stated that as the petitioner had

submitted it in the pre-revised specifications the same has been

returned and therefore petitioner has to resubmit the same in

the prescribed form. The learned counsel for the petitioner

submits that the same would be submitted in the prescribed

format within a period of one week. On receipt of the same the

3rd respondent shall take expeditious action for getting sanction

from the Commissioner of Railway Safety so as to enable the

petitioner to complete the work if possible before the date of

expiry of the agreement on 31.03.2021 itself and at any rate

within a period of two months from the date of receipt of a copy

of the judgment.

The Writ Petition is disposed of accordingly.

Sd/-

                                                    P.V.ASHA

rkc                                                     JUDGE
 WP(C).No.2137 OF 2021(N)




                           APPENDIX
PETITIONER'S/S EXHIBITS:

EXHIBIT P1           TRUE COPY OF THE LETTER OF ACCEPTANCE DATED
                     21.11.2019 ISSUED BY THE 3RD RESPONDENT.

EXHIBIT P2           TRUE COPY OF THE RELEVANT PAGE OF AGREEMENT
                     NO.02/DCE/ERS/2020 DATED 10.02.2020.

EXHIBIT P3           TRUE COPY OF THE LETTER DATED 09.09.2020

ISSUED BY PETITIONER TO THE 3RD RESPONDENT.

EXHIBIT P4 TRUE COPY OF THE LETTER DATED 27.10.2020 ISSUED BY THE PETITIONER TO 3RD RESPONDENT.

EXHIBIT P5 TRUE COPY OF THE LETTER DATED 04.01.2021 ISSUED TO THE SECOND RESPONDENT.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter