Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

T.K. Kesavan vs Kerala Police Housing And ...
2021 Latest Caselaw 4287 Ker

Citation : 2021 Latest Caselaw 4287 Ker
Judgement Date : 5 February, 2021

Kerala High Court
T.K. Kesavan vs Kerala Police Housing And ... on 5 February, 2021
         IN THE HIGH COURT OF KERALA AT ERNAKULAM

                            PRESENT

              THE HONOURABLE MR.JUSTICE N.NAGARESH

  FRIDAY, THE 05TH DAY OF FEBRUARY 2021/16TH MAGHA,1942

                     WP(C).No.8786 OF 2014


PETITIONER:

              T.K. KESAVAN,
              THALIYARA HOUSE, P.O.NIRAMARUDUR,
              TIRUR, MALAPPURAM DISTRICT-676 109.

              BY ADV. SRI.O.D.SIVADAS

RESPONDENTS:

     1        KERALA POLICE HOUSING AND CONSTRUCTION
              CORPORATION LIMITED,
              CHANDRASEKHARAN NAIR STADIUM,
              VIKAS BHAVAN P.O.,
              THIRUVANANTHAPURAM-695 033,
              REPRESENTED BY ITS MANAGING DIRECTOR.

     2        THE CHAIRMAN-CUM-MANAGING DIRECTOR,
              KERALA POLICE HOUSING AND CONSTRUCTION
              CORPORATION LIMITED,
              CHANDRASEKHARAN NAIR STADIUM,
              VIKAS BHAVAN P.O.,
              THIRUVANANTHAPURAM-695 033.

     3        THE SENIOR PROJECT ENGINEER,
              KERALA POLICE HOUSING AND CONSTRUCTION
              CORPORATION LIMITED,
              CHANDRASEKHARAN NAIR STADIUM,
              VIKAS BHAVAN P.O.,
              THIRUVANANTHAPURAM-695 033.

              BY ADV. SRI.C.K.GOVINDAN, SC
              BY ADV. SRI.V.J.JOSEPH, SC

     THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON 05.02.2021, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
 WP(C) No.8786/2014
                                   :2 :




                          JUDGMENT

~~~~~~~~~

Dated this the 5th day of February, 2021

The petitioner, a Building Contractor, has filed this

writ petition seeking the following reliefs:-

"i) Call for the records leading to the proceeding and quash Ext.P5 by issuing a writ of certiorari.

ii) Issue a writ of mandamus or any other appropriate writ, order or direction to the respondents to release the security deposit of one lakh rupees without any further delay.

iii) Declare that Ext.P5 order issued 2nd respondent imposing penalty for the delay in completing the work is illegal, arbitrary and without any authority."

2. The work of construction of Lower Subordinate

Quarters, Pandikkad, Malappuram was awarded by the

respondents to the petitioner as per Ext.P1 dated 09.01.2006.

An Agreement was executed on 11.07.2006. The agreed WP(C) No.8786/2014

contract amount was ₹65,13,600/-. The work site was handed

over to the petitioner on 14.08.2006. The work was agreed to

be completed within nine months.

3. The petitioner would submit that the original plan

was to construct two buildings with two floors each. However,

there was shortage of space to construct two buildings. The

respondents therefore required the petitioner to execute the

work as a primary structure with four floors, pending revision

of estimates. The change from the original plan caused

considerable delay, contended the petitioner.

4. When the site was handed over, it was noted that a

Three-Phase Electric Line was passing very close by the

proposed building, endangering the life of the workers. The

Project Engineer insisted that work can be started only after

shifting the electric line. The electric line was shifted only in

March, 2007.

5. The supply of laterite in the area was short and the

petitioner was forced to stop the works for weeks together.

The petitioner had to bring laterite from quarries situated WP(C) No.8786/2014

40 Km. away from the work site. Furthermore, there was

acute water scarcity in the area which forced the petitioner to

stop work frequently. Machine cut first quality bricks were

also not readily available. On account of the afore facts, there

occurred a delay of 14 months in completing the work.

6. The work was completed on 24.03.2010 and the

completion report was submitted by the Project Officer.

Taking into account the aforesaid facts and circumstances,

the final bill of the petitioner was settled and disbursed to the

petitioner on 28.04.2010. However, the security deposit of

₹1,00,000/- was retained for the defect liability period. The

respondents did not release the security deposit in spite of

Ext.P2 request made by the petitioner.

7. Surprisingly, the 2nd respondent issued Ext.P3

show-cause notice dated 25.06.2012 to the petitioner

proposing to impose a penalty of ₹32,17,622/- on account of

the delay in completion of work. The petitioner submitted

Ext.P4 objection dated 23.07.2012. However, the 2 nd

respondent issued Ext.P5 proceedings dated 12.11.2013 WP(C) No.8786/2014

imposing a penalty of ₹18,57,351/- for the delay in execution

of work. The petitioner challenges Ext.P5.

8. According to the petitioner, the delay occurred in

completion of the work is due to the fact that there was initially

a change of plan. Three-phase electric lines were to be

shifted by the KSEB before starting the construction work.

There was acute nonavailability of bricks which are extremely

necessary for the construction. The petitioner had to bring

laterite from far away quarries. And the scarcity of water also

hampered the work intermittently. The respondents were

aware of all these facts. There is no complaint against the

work of the petitioner. The respondents have settled the final

bill of the petitioner. In the circumstances, imposing such a

heavy penalty is highly arbitrary, illegal and unsustainable,

contended the counsel for the petitioner.

9. The Standing Counsel pointed out that the total

delay on the part of the petitioner in completing the work is

1130 days. The respondents condoned delay of 857 days.

However, there was no reason to condone the balance 273 WP(C) No.8786/2014

days delay. The compensation for delay was calculated on

the basis of Clause 2 of the Causes of Contract contained in

the tender document. Therefore, the respondents are

perfectly justified in quantifying and demanding the amount as

per Ext.P5.

10. I have heard the learned counsel for the petitioner

and the learned Standing Counsel appearing for the

respondents.

11. It is an admitted fact that the respondents directed

the petitioner to change the agreed plan for constructing the

building with two floors into one building with four floors. It is

also not disputed that a three-phase electrical line was

passing by the proposed building, making it unsafe to start

construction of the building without shifting the electric line by

the KSEB. Such shifting of the KSEB line also took

considerable time. The petitioner would submit that there

was shortage of machine cut bricks, lack of laterite and

scarcity of water, without which any construction work cannot

be proceeded smoothly.

WP(C) No.8786/2014

12. It is to be noted that the total consideration for the

agreed work was ₹65,13,600/- and the petitioner satisfactorily

completed the work, though there was a delay. The bills of

the petitioner were also settled. Apparently there was no

complaint as regards the work of the petitioner. Still, an

amount of ₹18,57,351/- has been imposed on the petitioner

towards compensation for delayed work. The said amount is

a substantial part of the total amount, more than 28%. Though

there may be a provision in the tender documents for claiming

compensation at specified rates, the respondents are bound

to consider the totality of the circumstances and levy or

demand just compensation.

13. If the petitioner has shown sufficient reasons for the

delay, imposition of fine or demand for compensation cannot

be mechanical. However, this Court is disabled from

examining the adequacy or proportionality of the

fine/compensation claimed due to non-availability of sufficient

data. In the said circumstances, this Court deem it

appropriate to direct the 2nd respondent to reconsider the WP(C) No.8786/2014

quantum of penalty imposed on the petitioner, taking into

account the entire circumstances which caused delay.

Accordingly, the writ petition is disposed of directing

the 2nd respondent to reconsider the quantum of

fine/compensation imposed on the petitioner, untrammelled by

any observations contained in Ext.P5 proceedings, within a

period of three months. The petitioner shall be granted an

opportunity of hearing before passing the final order.

Sd/-

N. NAGARESH, JUDGE

aks/08.02.2021 WP(C) No.8786/2014

APPENDIX PETITIONER'S EXHIBITS:

EXHIBIT P1 TRUE COPY OF THE LETTER DTD.9.1.2006.

EXHIBIT P2 TRUE COPY OF THE REQUEST SUBMITTED BY THE PETITIONER DTD.23.6.2012.

EXHIBIT P3           TRUE    COPY   OF   THE    PROCEEDINGS
                     DTD.25.6.2012.

EXHIBIT P4           TRUE COPY OF THE REPLY SUBMITTED BY
                     THE PETITIONER DTD.23.7.2012.

EXHIBIT P5           TRUE COPY OF THE PROCEEDINGS
                     DTD.12.11.2013 OF THE 2ND RESPONDENT.


SR
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter