Citation : 2021 Latest Caselaw 4280 Ker
Judgement Date : 5 February, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
FRIDAY, THE 05TH DAY OF FEBRUARY 2021 / 16TH MAGHA,1942
WP(C).No.34083 OF 2018(I)
PETITIONER:
T.S.SARASAN,
AGED 62 YEARS,
S/O SANKARAN, P.W.D CONTRACTOR,
THOTTINKARA VEEDU, THAVALAM P.O.,
PAKKULAM, PIN-688589
BY ADVS.
SRI.A.T.ANILKUMAR
SMT.V.SHYLAJA
RESPONDENTS:
1 KERALA POLICE HOUSING AND CONSTRUCTION
CORPORATION LTD.,
REP. BY ITS MANAGING DIRECTOR,
CHANDRASEKHARAN NAIR STADIUM,
PALAYAM, VIKAS BHAVAN P O,
THIRUVANANTHAPURAM, PIN-695033.
2 THE MANAGING DIRECTOR,
KERALA POLICE HOUSING AND CONSTRUCTION
CORPORATION LTD.,
CHANDRASEKHARAN NAIR STADIUM,
PALAYAM, VIKASBHAVAN P.O.,
THIRUVANANTHAPURAM, PIN-695033.
3 THE FINANCE MANAGER,
KERALA POLICE HOUSING AND CONSTRUCTION
CORPORATION LTD.,
CHANDRASEKHARAN NAIR STADIUM,
PALAYAM, VIKAS BHAVAN P.O.,
THIRUVANANTHAPURAM, PIN-695033.
R1-3 BY ADV. SRI.C.K.GOVINDAN, SC
R1-3 BY ADV. SRI.L.P.ARAVINDAKSHAN
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON 05.02.2021, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
WP(C) No.34083/2018
:2 :
JUDGMENT
~~~~~~~~~
Dated this the 5th day of February, 2021
The petitioner, who is a licensed PWD Contractor,
was awarded with Ext.P1 work related to construction of
barrack block for India Reserve Battalion at Thrissur. The
work had to be completed within ten months from the date of
handing over of the site. Agreement was executed on
06.04.2011. The petitioner successfully completed the work
on 11.04.2016 and handed over the constructed building to
the respondents.
2. The petitioner would submit that the delay in
executing the work was not solely attributable to the petitioner.
During the construction work, all his part bills were therefore
honoured by the respondents. After completion of the
construction, the respondents issued Ext.P2 letter directing
the petitioner to show-cause why penalty should not be
imposed for delay in completion of the work. WP(C) No.34083/2018
3. The petitioner submitted a detailed reply to Ext.P2
and requested the respondents to condone the delay in
completion of the work. The petitioner requested the
respondents to exempt the petitioner from imposition of
penalty. However, the respondents, as per Ext.P3 letter,
upheld their demand. The petitioner would submit that the
respondents have computed the penalty at 23,71,863/-.
Against the said penalty, the final bill amount of ₹9,12,652/-
and retention money of ₹9 lakhs have been withheld from the
petitioner. There is a further order to recover ₹1,06,210/-.
4. The learned counsel for the petitioner would argue
that the time was not the essence of the contract. The delay
in completion of the work was not exclusively attributable to
the petitioner. If time was the essence of the contract, the
respondents ought to have terminated the contract after the
stipulated ten months' period. On the other hand, the
petitioner was not only permitted to continue with the work but
also the part bills submitted by the petitioner were honoured
by the respondents.
WP(C) No.34083/2018
5. The learned counsel for the petitioner would submit
that the petitioner had submitted a complaint before the
Secretary to the Government against the penalty and
requested to reconsider the illegal retention of the money.
The request was forwarded to the 1 st respondent-Kerala
Police Housing and Construction Corporation Limited. The
Secretary to the 1st respondent, by letter dated 27.06.2018,
informed the petitioner that 210 days delay was condoned
from the total 1427 days delay in completion of the work. The
counsel for the petitioner would urge that since time is not the
essence of the contract and the petitioner has completed the
work successfully to the satisfaction of the respondents,
though belatedly, no such extreme penalty can be imposed.
The respondents are therefore liable to be compelled to pay
the final bill amount withheld from the petitioner as also the
retention money due to the petitioner.
6. The respondents filed counter affidavit in the writ
petition and resisted the prayers of the petitioner. The learned
Standing Counsel appearing for respondents 1 to 3 would WP(C) No.34083/2018
submit that the petitioner's work was prolonged and there was
a huge and unexplained delay in completion of work. The
agreement was executed in April, 2011. The work ought to
have been completed within ten months. However, the
petitioner took more than five years to complete the work,
causing substantial loss to the respondents. Clause 2 of the
agreement made specific provisions for compensation for
delay. The respondents have calculated the
compensation/penalty strictly on the basis of the agreement
and as per the extent instructions.
7. As per the specific provision for the first extension,
1% of the total amount subject to a minimum of ₹1,000/- and
maximum of ₹50,000/- is liable to be realised. In the case of
the petitioner, the first 1% amount comes to ₹2,27,062/- and
same is limited to ₹50,000/-. For the second extension, 2% of
the total amount subject to a minimum of ₹2,000/- and
maximum of ₹1 lakh is leviable. This amount was limited to ₹1
lakh. The maximum time extension that can be given for a
work shall be limited to half of the TOC, i.e., five months. The WP(C) No.34083/2018
work was completed only on 11.04.2016. It was under such
circumstances that the respondents imposed ₹25,31,060/-
penalty on the petitioner.
8. Heard learned counsel for the petitioner and
learned Standing Counsel appearing for the respondents.
There is no dispute that the agreement was executed on
06.04.2011 and the agreement mandated that the work should
be completed within ten months. The work was, however,
completed after a very long delay of five years only. The
learned counsel for the petitioner would put forth many
reasons for the delay and contend that the delay was not
caused due to the fault of the petitioner. However, this is a
disputed question of fact. This Court cannot adjudicate in a
writ petition under Article 226 of the Constitution whether the
delay was caused due to the fault of the petitioner or was it
attributable to the respondents.
9. As long as the contract provides for levy of penalty
and since the petitioner has signed the agreement with open
eyes, the petitioner cannot now turn around and contend that WP(C) No.34083/2018
no penalty is leviable from the petitioner. True, the time may
not be of essence of the contract. However, the agreement
executed by the petitioner provided for levy of
penalty/compensation for delayed completion of work. The
fact that part bills were promptly honoured cannot be a ground
to urge that the respondents have impliedly condoned the
delay. The counter affidavit filed by the respondents would
show that the levy of penalty/compensation was strictly in
accordance with the agreement and extant instructions.
In such circumstances, this Court does not find any
reason to interfere with the matter. The writ petition is
therefore dismissed. However, it is made clear that the
petitioner will be at liberty to approach appropriate court of law
to establish that the delay was not caused due to any fault on
his part and to challenge the penalty imposed on that ground.
Sd/-
N. NAGARESH, JUDGE
aks/05.02.2021 WP(C) No.34083/2018
APPENDIX PETITIONER'S EXHIBITS:
EXHIBIT P1 TRUE COPY OF THE CONTRACT ENTERED BETWEEN THE PETITIONER AND RESPONDENTS IN RESPECT OF THE CONSTRUCTION OF BARRACK BLOCK FOR INDIA RESERVE BATTALION.
EXHIBIT P2 TRUE COPY OF THE SHOW CAUSE LETTER DATED 6.6.2016.
EXHIBIT P3 TRUE COPY OF THE LETTER DATED 30.10.2017 IMPOSING PENALTY.
EXHIBIT P4 TRUE COPY FO THE LETTER DATED 27.6.2018.
EXHIBIT P5 TRUE COPY OF THE LETTER ADJUSTING FINAL BILL AMOUNT OF EXHIBIT P1 WORK WITH ANOTHER WORK.
RESPONDENTS' EXHIBITS:
EXHIBIT R2(a) TRUE COPY OF THE LETTER DATED 26-05-
2012 ISSUED TO PETITIONER BY THE PROJECT ENGINEER.
EXHIBIT R2(b) TRUE COPY OF THE MEMO DATED 05-06-2012 ISSUED TO PETITIONER BY THE CHIEF ENGINEER.
EXHIBIT R2(c) TRUE COPY OF THE LETTER DATED 26-04-
2013 ISSUED TO PETITIONER BY THE PROJECT ENGINEER.
EXHIBIT R2(d) TRUE COPY OF THE MEMO DATED 22-05-2013 ISSUED TO PETITIONER BY THE CHIEF ENGINEER.
EXHIBIT R2(e) TRUE COPY OF THE LETTER DATED 17-07-
2012 ISSUED TO PETITIONER BY THE CHIEF ENGINEER.
WP(C) No.34083/2018
EXHIBIT R2(f) TRUE COPY OF THE LETTER DATED 11-12-
2013 ISSUED TO PETITIONER BY THE PROJECT ENGINEER.
EXHIBIT R2(g) TRUE COPY OF THE LETTER DATED 06-08-
2014 ISSUED TO PETITIONER BY THE ASSISTANT EXECUTIVE ENGINEER.
EXHIBIT R2(h) TRUE COPY OF THE LETTER DATED 20-09-
2014 ISSUED TO PETITIONER BY THE PROJECT ENGINEER.
EXHIBIT R2(i) TRUE COPY OF THE TERMINATION NOTICE
12-11-2014 ISSUED TO PETITIONER BY
SECOND RESPONDENT.
EXHIBIT R2(j) TRUE COPY OF THE PROCEEDINGS OF
MANAGING DIRECTOR, SECOND RESPONDENT DATED 20-09-2016.
SR
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!