Saturday, 09, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Ajit Associates ... vs State Of Kerala
2021 Latest Caselaw 12266 Ker

Citation : 2021 Latest Caselaw 12266 Ker
Judgement Date : 26 April, 2021

Kerala High Court
M/S.Ajit Associates ... vs State Of Kerala on 26 April, 2021
         IN THE HIGH COURT OF KERALA AT ERNAKULAM

                            PRESENT

              THE HONOURABLE MR.JUSTICE N.NAGARESH

 MONDAY, THE 26TH DAY OF APRIL 2021 / 6TH VAISAKHA, 1943

                   WP(C).No.23006 OF 2019(A)


PETITIONER:

              M/s.AJIT ASSOCIATES ARCHITECTURAL
              CONSULTANTS PVT. LTD.,
              HAVING ITS OFFICE AT 3RD FLOOR,
              PUTHOORAN PLAZA, KPCC JUNCTION,
              M.G. ROAD, ERNAKULAM, KOCHI -682011,
              REPRESENTED BY ITS MANAGING DIRECTOR
              MR.(AR.) B.R. AJIT.

              BY ADVS.
              SRI.BABU KARUKAPADATH
              SMT.M.A.VAHEEDA BABU
              SHRI.P.U.VINOD KUMAR
              SRI.AVINASH P RAVEENDRAN
              SMT.ARYA RAGHUNATH
              SMT.ANJALY N.S.

RESPONDENTS:

     1        STATE OF KERALA,
              REPRESENTED BY ITS PRINCIPAL SECRETARY,
              DEPARTMENT OF PORTS, GOVERNMENT SECRETARIAT,
              THIRUVANANTHAPURAM-695001.

     2        DIRECTOR OF PORTS,
              GOVERNMENT OF KERALA, VELIYATHURA,
              VALLAKKADAVU, THIRUVANANTHAPURAM-695008.

     3        THE KERALA MARITIME SOCIETY,
              NEENDAKARA, KOLLAM-691582,
              REPRESENTED BY ITS SPECIAL OFFICER.

     4        M/S. SOUTH INDIAN CONSTRUCTIONS,
              VAVVAKKAVU P.O., KOLLAM-690528.
 WP(C) Nos.23006/2019 &15489/2020
                                   :2 :


ADDL.   5     KERALA MARITIME BOARD,
              REPRESENTED BY ITS CHIEF OPERATING OFFICER,
              VALIYATHURA, VALLAKADAVU P.O.,
              THIRUVANANTHAPURAM - 695008

              ADDL.R5 IS IMPLEADED AS PER ORDER DATED
              10.10.2019 IN IA No.1/2019.

              R4 BY ADV. SRI.JOHNSON GOMEZ
              R4 BY ADV. SRI.C.UNNIKRISHNAN (KOLLAM)
              R4 BY ADV. SMT.A.V.INDIRA
              R4 BY ADV. SRI.S.BIJU (KIZHAKKANELA)
              R4 BY ADV. SMT. JANE MARIA TOMY
              R4 BY ADV. SMT.UTHARA A.S
              R4 BY ADV. SMT.KARISHMA JOJO
              R4 BY ADV. SHRI.GAJENDRA SINGH RAJPUROHIT
              R4 BY ADV. SMT.GAYATHRI V NAIR
              R4 BY ADV. SMT.LIYA ELZA ALEX
              R4 BY ADV. SRI.D.JAYAKRISHNAN
              R5 BY ADV. K.P.SUDHEER
              R6 BY ADV. SRI.K.B.PRADEEP
              R6 BY ADV. SHRI.HARISANKAR R
              R6 BY ADV. SHRI.SREERAJ M.D.
              R1-2 BY GOVERNMENT PLEADER K.V MANOJ KUMAR

     THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON 26-04-2021, ALONG WITH WP(C).15489/2020(I), THE COURT
ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C) Nos.23006/2019 &15489/2020
                                   :3 :


           IN THE HIGH COURT OF KERALA AT ERNAKULAM

                               PRESENT

             THE HONOURABLE MR.JUSTICE N.NAGARESH

 MONDAY, THE 26TH DAY OF APRIL 2021 / 6TH VAISAKHA, 1943

                    WP(C).No.15489 OF 2020(I)


PETITIONER:

              SOUTH INDIAN CONSTRUCTIONS PVT. LTD.,
              VAVVAKKAVU P.O.,
              KARUNAGAPALLY REPRESENTED BY ITS CHAIRMAN AND
              MANAGING DIRECTOR,
              MR.R. VINOD KUMAR, AGED 47 YEARS,
              S/O. RAGHAVAN,
              RESIDING AT KOCHUPARAYATTU,
              VAVVAKKAVU, KARUNAGAPALLY, KOLLAM.

              BY ADVS.
              SRI.C.UNNIKRISHNAN (KOLLAM)
              SMT.A.V.INDIRA
              SHRI.ANANDA PADMANABHAN
              SMT.LIYA ELZA ALEX

RESPONDENTS:

       1      STATE OF KERALA,
              REPRESENTED BY ITS PRINCIPAL SECRETARY,
              DEPARTMENT OF PORTS,
              GOVERNMENT SECRETARIAT,
              THIRUVANANTHAPURAM 695 001.

       2      DIRECTOR OF PORTS,
              GOVERNMENT OF KERALA,
              THIRUVANANTHAPURAM 695 002.

       3      THE KERALA MARITIME BOARD,
              VALIYATHURA, VALAKAKADAVU,
              THIRUVANANTHAPURAM 695 008,
              REPRESENTED BY ITS CHIEF EXECUTIVE OFFICER.
 WP(C) Nos.23006/2019 &15489/2020
                                   :4 :


       4      M/S. AJITH ASSOCIATES,
              ARCHITECTURAL CONSULTANTS PVT.LTD.,
              HAVING ITS OFFICE AT 3RD FLOOR,
              PUTHOORAN PLAZA, KPCC JUNCTION,
              M.G. ROAD, ERNAKULAM, PIN-682 001,
              REPRESENTED BY ITS DIRECTOR MR. AJIT.

              R3   BY GOVERNMENT PLEADER SRI.K.V.MANOJKUMAR
              R4   BY ADV. SRI.BABU KARUKAPADATH
              R4   BY ADV. SMT.M.A.VAHEEDA BABU
              R4   BY ADV. SRI.P.U.VINOD KUMAR
              R4   BY ADV. SMT.ARYA RAGHUNATH
              R4   BY ADV. SMT.VAISAKHI V.
              R4   BY ADV. SRI.T.M.MUHAMMED MUSTHAQ
              BY   ADV. SRI.K.P.SUDHEER

     THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON 26-04-2021, ALONG WITH WP(C).23006/2019(A), THE COURT
ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C) Nos.23006/2019 &15489/2020
                                   :5 :




                         JUDGMENT

~~~~~~~~~

Dated this the 26th day of April, 2021

The petitioner in WP(C) No.23006 of 2019 is a

Company engaged in the activities of Architects, Designers

and as Project Managers and Supervisors of such activities.

The petitioner seeks to direct respondents 1 to 3 not to

release any more amounts to the 4 th respondent without

considering the points of objections raised by the petitioner in

Exts.P6 to P9. The 4th respondent in WP(C) No.23006/2019,

is the petitioner in WP(C) No.15489 of 2020. In W.P.(C)

No.15489 of 2020, the 4th respondent-petitioner seeks to

command respondents 1 to 3 to release `2,72,98,311/-

illegally withheld from him along with interest at the rate of

18% per annum from various bills of effecting deductions, with

future interest.

WP(C) Nos.23006/2019 &15489/2020

2. As both these writ petitions relate to one contract

work and to payments pursuant to the contract, they are heard

together and being disposed of by a common judgment. The

parties in these writ petitions are referred to in this judgment,

as they are arrayed in WP(C) No.23006/2019.

3. The Government of Kerala approved the

appointment of petitioner as an Architect for construction of

the campuses of the 3rd respondent-Kerala Maritime Institute

at Neendakara. The petitioner entered into an agreement

dated 03.07.2010 with the 3 rd respondent. The petitioner

would contend that for construction of a library with ground

plus one floor and an academic block with a ground +2 floors,

only shallow foundation/footing design was necessary.

However, the 4th respondent insisted for a pile foundation.

According to the petitioner, actually the piling drawings were

meant only for the hostel block which was of 8 floors.

4. The petitioner would state that when the bills

submitted by the 4th respondent was scrutinised and

examined, it was noticed that the amounts already paid were WP(C) Nos.23006/2019 &15489/2020

in excess by `2.9 Crore. Noticing this excess payment by

respondents 2 and 3 to the 4 th respondent-contractor and also

noticing certain anomalies, the petitioner sent a letter dated

09.02.2019 to the 2nd and 3rd respondents requesting to

withhold further payments to the 4th respondent. According to

the petitioner, a sum of `9.906 Crores was to be recovered

from the 4th respondent under various heads.

5. In spite of the objections of the petitioner the

officials attached to the office of the 2 nd and 3rd respondents

continued to insist for payment of undeserving amount to the

4th respondent-contractor. A meeting in the presence of the

Minister for Sports was held on 02.08.2019. The Managing

Director of the petitioner was laid up and could not attend the

meeting. In the meeting, certain unfounded allegations were

raised against the petitioner. The petitioner sent a letter dated

03.08.2019 to the Minister for Sports, pointing out corruption

in the matter of payment of amounts to the 4 th respondent-

contractor. However, respondents 1 to 3 are trying to close

the contract with the 4 th respondent, discharging the 4 th WP(C) Nos.23006/2019 &15489/2020

respondent from further contractual liability and to pay him

further amount without effecting recovery of excess amount

already paid. In the circumstances, the petitioner seeks to

direct respondents 1 to 3 to realise the excess amount paid to

the 4th respondent in violation of the advice and instructions

given by the petitioner in Exts.P6 to P9.

6. In the writ petition filed by the 4th respondent, the 4th

respondent stated that the 4 th respondent participated in the

tender for construction floated by the Director of Ports, the 2 nd

respondent, and as the bid of the 4 th respondent being lowest,

the tender was awarded to the 4 th respondent. The petitioner

was appointed as the Project Management Consultant of the

Project. The petitioner being the Consultant, had prepared

the bid document and specifications for construction of

Institute buildings. The petitioner issued drawings and the 4 th

respondent commenced construction accordingly.

7. The petitioner-Consultant had issued pile

foundation drawings for all the structures initially, but it was

changed to shallow foundation for two main structures during WP(C) Nos.23006/2019 &15489/2020

May, 2013. When the petitioner supplied pile foundation

drawings, the petitioner prescribed that piling need to be done

only up to a depth of 22 m. The petitioner made such

prescription after conducting a soil test through M/s.LAN-Dec

Engineers, Cochin, its soil testing agency. When the 4th

respondent proceeded with piling work, they could not find

any hard strata even after 22 m. They were instructed to

further deepen the pile and they could not find hard strata

even at a depth of 50 m. This was confirmed by another soil

testing agency "CGL-GEO INFOMATICS".

8. Thereafter, the petitioner changed their pile

foundation drawings in respect of two main structures within

two months and prescribed isolated footing foundation. The

4th respondent had completed works amounting to `33.3

Crores. An amount of `3.3 Crores was withheld as retention

money. Another `2.73 Crores was withheld without any

reason. The 4th respondent submitted a letter dated

24.11.2016 seeking to release the said amount. The 2 nd

respondent Port Director also requested the Government to WP(C) Nos.23006/2019 &15489/2020

release the payment to the 4th respondent as per Ext.P3 dated

30.11.2016. The 4th respondent made a series of

communications / representations to respondents 1 and 2.

9. The Director of Ports wrote Ext.P5 letter to the

Secretary to Government pointing out that the bill due to the

4th respondent is pending with the petitioner-consultant and

the petitioner has not recommended payment because the

Department has not paid consultancy fee to the petitioner.

The petitioner recommended payment of 22 nd RA Bill of the

petitioner for `1,45,25,983/- with statutory recovery of

`21,78,998/-, but at the same time petitioner also

recommended recovery of `9.688 Crore from 4th respondent.

The Director of Ports stated that on examination of

recommendation of the petitioner, it was noted that the

recoveries from the 4th respondent were proposed in a

revenging manner.

10. The 4th respondent stated that more than 90% of

works have been completed by them before October, 2018

and work could not be further proceeded with due to non- WP(C) Nos.23006/2019 &15489/2020

co-operation of the petitioner. Therefore, it would be only just

and proper to release the retention amount to the 4 th

respondent as the work has reached a halt for the last two

years for no fault of the 4th respondent.

11. During the pendency of the writ petition, the Kerala

Maritime Board was impleaded as additional 5 th respondent,

since due to Sections 10 and 11 of the Kerala Maritime Board

Act, 2017, the assets and functions of the 3 rd respondent-

Kerala Maritime Society was vested with the Kerala Maritime

Board. As per the direction of this Court, the petitioner sought

to implead the Training Coordinator of the Kerala Maritime

Institute as additional 6th respondent.

12. The Chief Executive Officer of the 5 th respondent-

Kerala Maritime Board filed a counter affidavit in WP(C)

No.15489/2020. The 5th respondent stated that the petitioner

is expected to carry out joint measurement along with the

contractor's engineer and to verify and certify measurements

before recommending bills submitted by the 4th respondent-

contractor. Now the Director of Ports is disabled to take WP(C) Nos.23006/2019 &15489/2020

measurement of the work carried out with respect to RAB-22

due to non-co-operation of the petitioner. The Director of

Ports is unable to terminate the agreement between the

petitioner and the Kerala Maritime Society due to the

pendency of WP(C) No.23006/2019. The 5 th respondent

stated that there are sufficient reasons to terminate the

agreement with the petitioner, due to inadequacy of service by

the petitioner with regard to timely completion of

designs/drawing/other documents enabling smooth and timely

completion of the project and quality supervision over the

work.

13. The 5th respondent stated that as per the total value

of work approved by the petitioner in respect of running

account bills RAB-6 to RAB-13, the amount payable to the 4 th

respondent after statutory deductions comes to

`2,72,98,311/-. This amount is not paid due to lack of

authorisation from the Government. The Director of Ports has

retained 10% of the amount towards retention money as per

the agreement conditions. The retention money thus withheld WP(C) Nos.23006/2019 &15489/2020

amounts to `3,29,65,792/- and it can be paid only along with

the final bill. The petitioner has breached the condition as to

providing architectural services and they stopped their service

from 22.12.2018 onwards by withdrawing their site engineer.

14. The 5th respondent stated that the 4th respondent

contractor has executed work in excess of the scheduled

quantity. Such excess work was necessitated as a result of

violation of conditions of agreement by the petitioner whereby

the petitioner has made deviation, alteration, addition to the

approved drawings without the knowledge and prior written

consent of the Society. The structural changes made by the

petitioner were not brought to the notice of the 3 rd respondent

for approval. The petitioner did not submit revised estimates

with deviation statements for approval.

15. The 5th respondent stated that the construction

work was stalled during the implementation of the project due

to inconsistency of issued working drawings and the drawings

submitted by the petitioner after the new soil testing report.

The non-cooperation of the petitioner after receiving 70% of WP(C) Nos.23006/2019 &15489/2020

consultancy fee forced the 3 rd respondent to deduct the extra

amount of expenditure incurred for soil testing. The petitioner

also raised a new claim for consultation fee, contended the 5 th

respondent.

16. The additional 6th respondent in WP(C)

No.23006/2019 filed a detailed counter affidavit. The

additional 6th respondent stated that the following clauses

described in paragraphs (a) to (e) of the said agreement were

breached by petitioner:

"(a) As per clause 1.01 of the Agreement, Architect shall provide services pertaining to the plan, design, estimate preparation and supervision of the said project. Clause 1.06 and 1.07 says that after the written approval of the sketch of the architect shall prepare the detailed drawings along with schedules of specifications and schedule of quantities. The Architect shall also furnish detailed estimate on the specification and schedule of rate adopted by the State PWD in the region.

(b) Clause 1.11 stipulates that the Architect shall prepare and submit complete working drawings and details sufficient to commence the work at the site for the proper execution during the construction.

(c) Clause 1.12 states that the Consultant shall visit the site of work as and when necessary to clarify any decision or WP(C) Nos.23006/2019 &15489/2020

interpretation of the drawings and specifications. They shall attend conferences and meetings as and when required till the completion of the project.

(d) Clause 1.13 insists that the Architect shall not make any deviation, alteration, addition to or omission to the approved drawings without the knowledge and prior written consent of the Society, the Society reserves the right to omit or postpone any works or part thereof at its discretion.

(e) As per clause 2.01, the Architect shall submit to the Society all the necessary sketch plans/designs, draft tender documents with in the period stipulated by the society. They shall carry of the works in all respects as required by the society and within the stipulated time. Time shall be construed as the essence of the agreement."

The above clauses described in paragraphs (a) to (e) are

1.01, 1.02, 1.11, 1.12 & 2.01 of the agreement dated

03.07.2010 which are violated by the petitioner. These

breaches were duly reported to the Government under letter

No.C2-289/2011/DP(1) dt.28/05/2019 by Director of Ports and

Special Officer of Kerala Maritime Society (2 nd & 3rd

respondent), contended the additional 6th respondent.

17. I have heard the learned counsel for the petitioner,

the learned Government Pleader appearing for respondents 1 WP(C) Nos.23006/2019 &15489/2020

and 2, the counsel appearing for the 4 th respondent, the

Standing Counsel appearing for the additional 5 th respondent

and the counsel appearing for the additional 6 th respondent.

18. From the pleadings, it is evident that the

Government of Kerala accepted the tender for the

construction of Kerala Maritime Institute at Neendakara as per

G.O. dated 07.01.2013. As per the Scheme, 11 components

were included for construction, which are as follows:

"1. Library Block

2. Hostel Block

3. Canteen Block

4. Academic Block

5. Electrical Room and Substation

6. Auditorium

7. Security Cabin

8. Swimming Pool

9. Road and Drain

10. Compound wall and Parade Ground

11. UG sump, Pump House STP"

The petitioner was the Project Management Consultant (PMC)

and the 4th respondent was the Contractor with whom the 3 rd

respondent-Kerala Maritime Society entered into agreements.

19. According to the petitioner, a Library with Ground

+1 Floor and an Academic Block with Ground +2 Floors were WP(C) Nos.23006/2019 &15489/2020

proposed to be constructed in non-mining areas, but in fact

mining activities were going on at the sites. After careful

study, the petitioner found that only shallow foundation/

footing design is required, which would also reduce cost and

hence petitioner proposed shallow foundations. According to

the petitioner, the 4th respondent and the additional 6 th

respondent did not accept the proposal. The mining activity

was at the instance of the additional 6 th respondent and was

intended to give piling work to the 4 th respondent as it was

more gainful for the latter. The petitioner submitted Ext.P6

letter dated 05.04.2016 to the 3 rd respondent pointing out the

facts. When Running Bills RAB 1 to RAB 22 of the 4 th

respondent were examined it was found that the 4 th

respondent already received excess amounts. Hence Ext.P7

letter dated 09.02.2019 was sent to respondents 2 and 3

pointing out that `9.906 Crores was to be recovered from the

4th respondent. The petitioner has further alleged that the 4 th

respondent did not start the construction part of auditorium

but started work at a non-excavation area, which resulted in WP(C) Nos.23006/2019 &15489/2020

additional cost. Therefore the intention of the 4 th respondent

is malafide and the bills cannot be settled without deducting

undue excess amount paid to the 4th respondent.

20. But, the pleadings would reveal that when initially

tenders were issued shallow foundation alone was mentioned,

but after the Government handed over the area for mining

work, an addendum notification was issued including in it

piling work. Exts.R4(d) and Ext. R4(e) pile foundation

drawings were issued by the petitioner itself, to the 4 th

respondent. The drawings were prepared based on a soil

investigation report prepared by M/s.LAN-Dec Engineers,

Cochin, an agency arranged by the petitioner. On the basis of

the said report, piling work was suggested and that too only

up to 24m depth. The 4th respondent could not find hard

strata at 24m depth. The petitioner was required to continue

with piling and hard strata could be touched only at a depth of

58-60 m. The petitioner again engaged another soil testing

agency M/s.CGL-GEO Infomatics who confirmed the hard

strata only at that depth. The piling at a depth of 58-60m WP(C) Nos.23006/2019 &15489/2020

caused additional expenditure not originally provided for. This

extra cost was as a result of the petitioner engaging a sub

standard agency for soil testing. Thereafter, the pile

foundation drawings in respect of two main structures were

changed to that of the isolated footing foundation.

21. It has been revealed that the first soil test result by

M/s.LAN-Dec, Cochin was received on 08.08.2012. The

petitioner issued pile foundation drawing of 18-21 m for

Library block on 06.03.2013. The piling work was stopped on

20.03.2013 as the 4th respondent could not find hard strata

even at a depth of 50m. A notice was issued to the petitioner

in this regard on 21.03.2013. The Structural Engineer of the

petitioner who visited the site on 21.03.2013 admitted that the

soil test report is incorrect. On 01.04.2013, the petitioner

issued Ext.R6(Q) letter requiring detailed soil investigation.

These facts would show that the initial soil investigation

conducted at the instance of the petitioner was faulty and the

fault has resulted in substantial delay in work and extra costs. WP(C) Nos.23006/2019 &15489/2020

22. Another allegation of the petitioner is that the 4 th

respondent did not start construction work of the auditorium.

The 4th respondent has stated that the petitioner has so far

not handed over drawing of auditorium to the petitioner.

Furthermore, in the special meeting on the construction,

convened on 25.06.2014 by the Director of Ports, it was

decided to keep in abeyance the construction of the

auditorium and compound wall. This is evident from Ext.R4(b)

minutes. Therefore, the petitioner cannot blame the delay on

the 4th respondent.

23. The prayer of the petitioner is not to make any

more payments to the 4 th respondent without considering the

objections of the petitioner. As discussed and found herein

above, the delay in construction and escalation of cost of

construction is not attributable to the 4 th respondent. As

regards alleged excess payment made to the 4 th respondent,

the Director of Ports has considered the issue in detail in

Ext.P5 and observed that the petitioner has suggested to

recover amounts from the 4 th respondent in a revengeful WP(C) Nos.23006/2019 &15489/2020

manner, for not getting paid their consultancy fee. In the facts

of the case, this Court finds no reason to disregard or

disbelieve the conclusions of the Director of Ports contained

in Ext.P5. WP(C) No.23006/2019 filed by the petitioner is

therefore liable to be dismissed.

24. As regards the prayers of the petitioner in WP(C)

No.15489/2020 to release the amounts due to him under the

contract, the 3rd respondent in their counter affidavit in WP(C)

No.15489/2020, has stated that the Director of Ports is totally

unable to make the measurements of the work carried out by

the 4th respondent without the service of the petitioner since

the petitioner is expected to carry out joint measurement

along with the Engineer of the 4 th respondent to verify and

certify such measurements before recommending the bills

submitted by the 4th respondent for payment. Due to the

pendency of WP(C) No.23006/2019, the Director of Ports is

unable to terminate the agreement with the petitioner. It is not

in dispute that the petitioner has denied their service from

22.12.2018, by withdrawing their Site Engineer. In the WP(C) Nos.23006/2019 &15489/2020

circumstances, necessary orders need to be passed directing

respondents 1 to 3 in WP(C) No.15489/2020 to take effect

steps to release amounts due to the petitioner.

25. For the reasons stated above, WP(C)

No.23006/2019 is dismissed and W.P.(C) No.15489/2020 is

disposed of with the following directions:-

There will be a direction to respondents 1 to 3 in

WP(C) No.15489/2020 to release the amounts withheld from

and any other amounts due to the petitioner in WP(C)

No.15489/2020, within a period of two months. The claim and

question of interest made in WP(C) No.15489/2020, are left

open.

Sd/-

N. NAGARESH, JUDGE

aks/16.04.2021 WP(C) Nos.23006/2019 &15489/2020

APPENDIX OF WP(C) 23006/2019 PETITIONER'S EXHIBITS:

EXHIBIT P1 A TRUE COPY OF THE ORIGINAL ZONING PLAN, IDENTIFYING THE MINING AND NON-

MINING ZONES, SUBMITTED BY THE PETITIONER IN EARLY FEBRUARY 2013.

EXHIBIT P2 A TRUE COPY OF THE MINUTES OF THE MEETING HELD ON 14/02/2013.

EXHIBIT P3 A TRUE COPY OF THE LETTER DATED 15/02/2013 ALONG WITH THE NEW ZONING PLAN, IDENTIFYING THE MINING AND NON-

MINING ZONES, SUBMITTED BY THE PETITIONER.

EXHIBIT P4 A TRUE COPY OF THE LETTER DATED 19/06/2013 ISSUED BY THE HEAD OF THE DEPARTMENT OF STRUCTURAL ENGINEERING DEPARTMENT OF THE PETITIONER TO THE DIRECTOR OF PORTS.

EXHIBIT P5             A TRUE COPY OF THE LETTER DATED
                       19/06/2013   PASSED    BY   THE  4TH
                       RESPONDENT  CONTRACTOR   TO  THE 3RD
                       RESPONDENT.

EXHIBIT P6             A TRUE COPY OF THE LETTER DATED

05/04/2016 ISSUED BY THE PETITIONER TO THE 3RD RESPONDENT.

EXHIBIT P7 A TRUE COPY OF THE LETTER DATED 09/02/2019 ISSUED BY THE PETITIONER TO THE 2ND AND 3RD RESPONDENTS.

EXHIBIT P8             A TRUE COPY OF THE         LETTER DATED
                       29/06/2019 SENT BY THE     PETITIONER TO
                       THE 2ND RESPONDENT.
EXHIBIT P9             A TRUE COPY OF THE         LETTER DATED
                       03/08/2019 SENT BY THE     PETITIONER TO
                       THE   HON'BLE   MINISTER     FOR   PORTS,
                       GOVERNMENT          OF            KERALA,
                       THIRUVANANTHAPURAM.
 WP(C) Nos.23006/2019 &15489/2020



RESPONDENTS' EXHIBITS:

EXHIBIT R4(A)          A TRUE COPY OF THE 1ST ZONING PLAN.

EXHIBIT R4(B)          A TRUE COPY OF THE MINUTES                      OF   THE
                       MEETING DATED 25.6.2014.

EXHIBIT R4(C)          A TRUE COPY OF THE MINUTES                      OF   THE
                       MEETING DATED 27.4.2016.

EXHIBIT R4(D)          A TRUE COPY OF THE PILE FOUNDATION
                       DRAWING         NO.ST-WD-EDB-108-03-001
                       (ACADEMIC BLOCK) DATED 25.2.2013.

EXHIBIT R4(E)          A TRUE COPY OF THE PILE FOUNDATION
                       DRAWING         NO.ST-WD-EDB-108-05-001
                       (LIBRARY BLOCK) DATED 6.2.2013.

EXHIBIT R4(F)          A TRUE COPY OF THE MINUTES                      OF   THE
                       MEETING HELD ON 27.4.2016.

EXHIBIT R4(G)          A TRUE COPY               OF     THE   LETTER    DATED
                       28.4.2017.

EXHIBIT R4(H)          A TRUE COPY OF THE RELEVANT PAGE OF

ADDENDUM CONTAINING THE DESCRIPTION OF ITEMS IN FULL.

EXHIBIT R4(I) A TRUE COPY OF THE LETTER NO.C2-

289/2011 DATED 22.2.2019.

EXHIBIT R4(J) A TRUE COPY OF THE LETTER GIVEN BY THE RESPONDENT BASED ON THE QUERY RAISED BY THE 2ND RESPONDENT DATED 19.2.2019.

EXHIBIT R5(A) TRUE COPY OF NOTIFICATION NO.20/2019 DATED 2.5.2019 ISSUED BY FISHERIES AND PORT DEPARTMENT, GOVERNMENT OF KERALA.

EXHIBIT R6-A TRUE COPY OF THE LETTER NO.C2-

289/2014/DP DATED 12.7.2016.

EXHIBIT R6-B TRUE COPY OF THE AGREEMENT DATED 3.7.2010.

WP(C) Nos.23006/2019 &15489/2020

EXHIBIT R6-C TRUE COPY OF THE LETTER NO.C2-

289/2011/DP(1), DATED 28.5.2019.

EXHIBIT R6-D TRUE COPY OF THE MINUTES OF MEETING DATED 27.4.2016.

EXHIBIT R6-E TRUE COPY OF PROCEEDINGS NO.C2-

4327/2011 DATED 28.9.2012.

EXHIBIT R6-F TRUE COPY OF THE GOVERNMENT ORDER FOR MINING DATED 30.5.2012.

EXHIBIT R6-G TRUE COPY OF THE FIRST MINING PLAN DATED 20.6.2012.

EXHIBIT R6-H TRUE COPY OF REVISED MINING PLAN.

EXHIBIT R6-I TRUE COPY E-MAIL DATED 28.6.2012.

EXHIBIT R6-J TRUE COPY OF E-MAIL DATED 13.6.2012.

EXHIBIT R6-K TRUE COPY OF THE PILE FOUNDATION DRAWING FOR MULTI-STOREY ACADEMIC BLOCK DATED 25.2.2013.

EXHIBIT R6-L TRUE COPY OF THE PILE FOUNDATION FOR SINGLE-STOREY LIBRARY BLOCK DRAWING DATED 4.3.2013.

EXHIBIT R6-M TRUE COPY OF THE RECOMMENDATION LETTER OF THE PETITIONER DATED 13.12.2010.

EXHIBIT R6-N TRUE COPY OF THE CORRESPONDENCE VIA E-

MAIL DATED 8.8.2012.

EXHIBIT R6-O           TRUE COPY OF LETTER DATED 21.3.2013 TO
                       THE    PETITIONER   FROM    THE    5TH
                       RESPONDENT.

EXHIBIT R6-P           TRUE COPY OF THE LETTER BY THE

PETITIONER'S STRUCTURAL ENGINEER TO THE 6TH RESPONDENT.

EXHIBIT R6-Q TRUE COPY OF THE RECOMMENDATION LETTER BY THE PETITIONER DATED 1.4.2013.

WP(C) Nos.23006/2019 &15489/2020

EXHIBIT R6-R TRUE COPY OF SHALLOW FOUNDATION.

EXHIBIT R6-S TRUE COPY OF THE REPORT DATED 30.6.2015.

EXHIBIT R6-T TRUE COPY OF THE PROCEEDINGS OF RECOVERY DATED 28.4.2016.

EXHIBIT R6-U TRUE COPY OF THE MINUTES OF MEETING DATED 27.4.2016.

EXHIBIT R6-V TRUE COPY OF THE ADDENDUM DESCRIPTION ATTACHED AND SENT BY THE PETITIONER BY E-MAIL DATED 20.7.2012.

EXHIBIT R6-W TRUE COPY OF THE PROCEEDINGS DATED 7.1.2014.

EXHIBIT R6-X TRUE COPY OF THE MAIL DATED 31.12.2012.

EXHIBIT R6-Y TRUE COPY OF THE (ANALYSIS & BRIEF NOTE) LETTER DATED 28.2.2019.

EXHIBIT R6-Z TRUE COPY OF THE (DETAILED NOTE) LETTER DATED 28.5.2019.

EXHIBIT R6-AA TRUE COPY OF THE LETTER NO.C2-

289/2011/DP BY 2ND RESPONDENT TO THE 4TH RESPONDENT DATED 10.7.2018.

EXHIBIT R6-AB TRUE COPY OF THE CMC PROCEEDINGS DATED 11.7.2013.

EXHIBIT R6-AC TRUE COPY OF THE OFFICE NOTICES DATED 19.12.2018.

EXHIBIT R6-AD TRUE COPY OF THE SAID LETTER DATED 22.3.2018 TO THE PETITIONER ALONG WITH REMARKS DATED 22.11.2017.

EXHIBIT R6-AE TRUE COPY OF THE MINUTED DATED 5.5.2018.

WP(C) Nos.23006/2019 &15489/2020

APPENDIX OF WP(C) 15489/2020 PETITIONER'S EXHIBITS:

EXHIBIT P1             A TRUE COPY OF AN AGREEMENT DATED
                       18.02.2013    EXECUTED   BETWEEN   THE
                       PETITIONER AND THE RESPONDENT NO.2

EXHIBIT P2             A   TRUE  COPY   OF   THE  LETTER   NO.
                       35/SIC/11/16      DATED      24.11.2016
                       SUBMITTED BY THE PETITIONER.

EXHIBIT P3             A TRUE COPY OF THE PROCEEDINGS NO.

C2/289/2011/DP DATED 30.11.2016 ISSUED BY THE RESPONDENT NO. 1. DIRECTOR OF PORTS TO THE RESPONDENT. NO. 2.

PRINCIPAL SECRETARY.

EXHIBIT P4 A TRUE COPY OF THE COMMUNICATION DATED

AND 2 BY THE PETITIONER.

EXHIBIT P4 (A) A TRUE COPY OF THE COMMUNICATION DATED

AND 2 BY THE PETITIONER.

EXHIBIT P4 (B) A TRUE COPY OF THE COMMUNICATION DATED 11.4.2018 SENT TO RESPONDENT NO. 1 AND 2 BY THE PETITIONER.

EXHIBIT P4 (C) A TRUE COPY OF THE COMMUNICATION DATED

AND 2 BY THE PETITIONER.

EXHIBIT P4 (D) A TRUE COPY OF THE COMMUNICATION DATED

AND 2 BY THE PETITIONER.

EXHIBIT P4 (E) A TRUE COPY OF THE COMMUNICATION DATED

AND 2 BY THE PETITIONER.

WP(C) Nos.23006/2019 &15489/2020

EXHIBIT P4 (F) A TRUE COPY OF THE COMMUNICATION DATED

AND 2 BY THE PETITIONER.

EXHIBIT P4 (G) A TRUE COPY OF THE COMMUNICATION DATED

AND 2 BY THE PETITIONER.

EXHIBIT P5 A TRUE COPY OF THE LETTER NO. C2-

289/2011 DATED 28.02.2019 ISSUED BY THE DIRECTOR OF PORTS TO THE PRINCIPAL SECRETARY.

EXHIBIT P6 A TRUE COPY OF THE MINUTES OF THE MEETING CONDUCTED UNDER THE CHAIRMANSHIP OF MINISTER OF PORTS AND 02.08.2019.

RESPONDENTS' EXHIBITS:

EXHIBIT R4(a): A TRUE COPY OF THE RELEVANT PORTION OF MALAYALAM MANORAMA DAILY.

EXHIBIT R4(b): A TRUE COPY OF THE ORIGINAL ZONING PLAN, IDENTIFYING THE MINING AND NON-

MINING ZONES, SUBMITTED BY THE 4TH RESPONDENT IN EARLY FEBRUARY 2013.

EXHIBIT R4(c): TRUE COPY OF THE MINUTES OF THE MEETING HELD ON 14/02/2013.

EXHIBIT R4(d): A TRUE COPY OF THE LETTER DATED 15/02/2013 ALONG WITH THE NEW ZONING PLAN, IDENTIFYING THE MINING AND NON-

MINING ZONES, SUBMITTED BY THE 4TH RESPONDENT.

EXHIBIT R4(e): A TRUE COPY OF THE LETTER DATED 19/06/2013 ISSUED BY THE HEAD OF THE DEPARTMENT OF STRUCTURAL ENGINEERING DEPARTMENT OF THE 4TH RESPONDENT TO THE DIRECTOR OF PORTS.

EXHIBIT R4(f): A TRUE COPY OF THE LETTER DATED 19/06/2013 ISSUED BY THE PETITIONER CONTRACTOR TO THE 3RD RESPONDENT.

 WP(C) Nos.23006/2019 &15489/2020



EXHIBIT R4(g):          A TRUE COPY OF THE LETTER DATED
                        05/04/2016    ISSUED   BY    THE  4TH
                        RESPONDENT TO THE 3RD RESPONDENT.



SR
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter