Citation : 2021 Latest Caselaw 11640 Ker
Judgement Date : 9 April, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE SHAJI P.CHALY
FRIDAY, THE 09TH DAY OF APRIL 2021 / 19TH CHAITHRA, 1943
WP(C).No.9308 OF 2010(K)
PETITIONER/S:
K.A.AZEEZ, S/O. LATE K. ABDU,
KIZHHISSERY HOUSE, P.J.ANTONY ROAD, VADUTHALA, NOW
RESIDING AT 48/206 (J), GREEN RIPPLE ROAD,, SAMIPADY,
ELAMAKKARA, COCHIN-26.
BY ADVS.
SRI.LAL K.JOSEPH
SRI.P.MURALEEDHARAN (THURAVOOR)
RESPONDENT/S:
1 KERALA STATE ELECTRICITY BOARD
VYDHYUDHIBHAVANAM, PATTAM, THIRUVANANTHAPURAM.,
REPRESENTED BY ITS SECRETARY.
2 THE DEPUTY CHIEF ENGINEER, KERALA STATE
ELECTRICITY BOARD, ELECTRICAL CIRCLE ERNAKULAM.
3 THE EXECUTIVE ENGINEER, KERALA STATE
ELECTRICITY BOARD, ELECTRICAL DIVISION,ERNAKULAM.
4 THE ASSISTANT ENGINEER
KERALA STATE ELECTRICITY BOARD, ELECTIRCAL SECTION,
VADUTHALA, ERNAKULAM.
5 KERALA STATE ELECTRICITY REGULATORY
COMMISSION, VELLAYAMBALAM, THIRUVANANTHAPURAM.,
REPRESENTED BY ITS CHAIRMAN.
R1 BY SRI.SUDHEER GANESH KUMAR R., SC, KERALA STATE
ELECTRICITY BO
R1 BY SRI.P.P.THAJUDEEN, SC, K.S.E.B
R1 BY ADV. SRI.S.SREEKUMARSCKSERC
R1 BY ADV. SRI.T.R.RAJANSCK.S.E.B.
R1 BY ADV. SRI.ANEESH JAMESSCKSEB REGULATORY COM
R1, R5 BY SRI.S.SUJIN, SC, ELECTRICITY REGULATORY
COMMISSION
R1 TO 4-SRI.SUDHEER GANESH KUMAR,SC
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 09.04.2021,
THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
W.P.(C) No. 9308/2010 :2:
'CR'
Dated this the 9th day of April, 2021.
JUDGMENT
The petitioner, one of the Directors of a company namely West
Rock Properties Ltd., registered under the Companies Act engaged in
the business of property development, challenges Regulation 51(1) of
the KSEB Terms and Conditions of Supply, 2005 and to declare the said
provision as ultra vires of the Electricity Act, 2003 ('Act, 2003' for
short) and also to quash Ext.P1 invoice, Ext.P2 notice, Ext.P9 order
dated 27.01.2010 passed by the 4 th respondent -Assistant Engineer of
the Kerala State Electricity Board Ltd (K.S.E.B Ltd), Ext.P11 order
dated 07.02.2008 issued by the first respondent K.S.E.B Ltd making
certain clarifications with respect to the manner in which penalty is to
be imposed for the unauthorised connected load provided under
Section 126 of the Act, 2003 and Ext.P12 demand notice directing the
petitioner to pay an amount of Rs.8,75,902/-, failing which recovery
action was threatened.
2. Brief material facts for the disposal of the writ petition are as
follows:
The petitioner has availed an electricity connection having
consumer No. 18147 in his personal capacity for the purpose of
constructing a multi storied building complex. The issue started when
Ext.P1 notice dated 17.08.2009 was issued to the petitioner directing
him to pay an amount of Rs.8,75,902/- towards the short assessment
against fixed charges and energy charges for the period from 07/2007
to 05/2009. The allegation was that the petitioner had connected an
additional load of 23 KW, when the authorised connected load was
only 7 KW. According to the petitioner, the said allegation is not
correct, as in the invoice issued from 16.07.2007 onwards, the
authorised connected load of the petitioner is shown as 31000 Watts
(31KW); whereas, the present assessment is made by taking the total
load as 23000 Watts.
3. The case of the petitioner is that the connected load of the
petitioner, though not enhanced by any order from 7 KW, since the bills
are issued for 31000 Watts, there is no unauthorised load. Even
though the petitioner submitted an objection to Ext.P1 demand notice
and ExtP2 calculation statement, the Board was not prepared to accept
the contention raised by the petitioner and it was accordingly that
Ext.P9 final determination order was passed on 27.01.2010 after
providing an opportunity of hearing to the petitioner.
4. The learned counsel for the petitioner contended that there is
no unauthorised load in the premises, as in all the bills issued to the
petitioner from 16.07.2007 onwards, the authorised load of the
petitioner is shown as 31KW; whereas, the present penalty is based on
the allegation that the load exceeded by the petitioner is 23KW; that
the penalty for the normal consumption charges was also assessed by
the Board which is not permitted under law and therefore, the present
penalty imposed amounts to a mistake committed by the Board, since
the connected load stands regularised as is evident from the demand
made for 31KW; that no proceedings under Section 126 of the Act,
2003 can be initiated for unauthorised additional load as it will not
come under the definition of 'unauthorised use of electricity' as
defined in the explanation to Section 126 of the Act, 2003; that the
only provision which enables the Board for penalisation of additional
load is Regulation 51(1) of the KSEB Terms and Conditions of Supply,
2005, which was prepared by the first respondent Board and approved
by the 5th respondent i.e., the Kerala State Electricity Regulatory
Commission and since there is no provision in the Act, 2003
empowering the Commissioner or the Board to make any provision for
penalisation, Regulation 51(1) of the KSEB Terms and Conditions of
Supply, 2005 cannot be enforced; and that even if the Board is vested
with powers for imposing penalty for unauthorised load, the penalty
imposed is unreasonable and irrational and therefore, there is no
provision of law enabling the Board to recover the amount from the
petitioner.
5. No counter affidavit is filed by the KSEB. However, the learned
Standing Counsel for the Board has fully supported the findings
rendered by the primary authority under the provisions of the Act,
2003 and the Regulations thereto.
6. I have heard the learned counsel for the petitioner Sri. Lal K.
Joseph and the learned Standing Counsel for the KSEB Sri. Sudheer
Ganesh Kumar and Sri. G. Pramod, and perused the pleadings and
materials on record.
7. It is an admitted fact that though under Section 127 of the
Act, 2003, an alternative remedy is available to the petitioner to file an
appeal, the petitioner has not cared to do so. The sole question
emerges for consideration is whether any manner of interference is
warranted to Ext.P9 order passed by the Assistant Engineer as per
Section 126 of the Act, 2003. The said order reads thus:
"Findings Hearing examined all the documents and files related to this case and the provisions of Electricity Act, 2003. The undersigned has come to the following conclusions and decisions thereof.
Officials of Electrical Section Vaduthala conducted a surprise
inspection in the premises of Con No.18147 and detected unauthorized additional load of 16KW over and above the sanctioned inad of 7KW. The petitioner is not having any dispute with KSEB regarding the presence of additional load detected in this premises. He agreed that by levying Rs 3100/- as fixed charge in each monthly bill he is permitted to use additional load corresponding to fixed charge of Rs 3100/-.
Bill issued to the consumer as per Order No.B.O (FM) No.368/2008(DPCI/C-G1/182/2007) dt. Tvm 07-02-08. The Account General issued directions to issue back assessment bill to the consumer by imposing this order. The Hon. High Court judgment quoted by the consumer is purely applicable to a particular consumer only.
The consumer has not yet been submitted any application for regularization of connected load and no such approval orders issued from Board officials. Further the consumer has not remitted any ACD for regularization of UAL till the date. The undersigned examined this dispute in detail. The monthly invoice shows a connected load 31KW with effect from 16.07.2007. It is understood that it was actually a clerical error occurred in the computer system from the part of the staff who prepared this monthly bill and the same was continued for the last few years. The consumer did not make any complaint about this error and this was continued in succeeding bills. But it is clear that the petitioner has not submitted any application for enhancing the connected load during this period. The consumer has remitted Rs.3100/- as illustrated below.
Fixed Charge = 7KW X Rs.100 = 700.00
Penal Fixed Charge = 16KWx 100 x 1.5 = 2400.00
---------
Total Fixed Charged per month Rs. = 3100.00
======
It is very clear that the petitioner remitted the penalization charges till the date of the aforesaid back assessment bill without any dispute. Hence the presence of the 16KW unauthorized additional load is very well established and the short assessment bill issued to the consumer for Rs.8875902/- is in order.
The petitioner is hereby directed to remit the amount on or before 03-02-10 to avoid Revenue Recovery Proceedings. The petitioner is free to file an appeal before the Deputy Chief Engineer, Electrical Circle, Ernakulam within 30 days from the date of receipt of this order.
The objection petition is disposed as above."
8. The first issue that was raised by the petitioner is in regard to
the power of the State Regulatory Commission or the Kerala State
Electricity Board to make KSEB Terms and Conditions of Supply, 2005.
The Act, 2003 was brought into force on and with effect from
02.06.2003 by publication in the Gazette of India dated 02.06.2003.
Section 126 of the Act, 2003, which deals with 'assessment' comes
under Part XII dealing with 'investigation and enforcement' and it
reads thus:
"Section 126: (Assessment): -- (1) If on an inspection of any place or premises or after inspection of the equipments, gadgets, machines, devices found connected or used, or after inspection of records maintained by any person, the assessing officer comes to the conclusion that such person is indulging in unauthorized use of electricity, he shall provisionally assess to the best of his judgement the electricity charges payable by such person or by any other person benefited by such use.
(2) The order of provisional assessment shall be served upon the person in occupation or possession or in charge of the place or premises in such manner as may be prescribed.
[(3) The person, on whom an order has been served under sub- section (2) shall be entitled to file objections, if any, against the provisional assessment before the assessing officer, who shall, after affording a reasonable opportunity of hearing to such person, pass a final order of assessment within thirty days from the date of service of such order of provisional assessment, of the electricity charges payable by such person.] (4) Any person served with the order of provisional assessment, may, accept such assessment and deposit the assessed amount with the licensee within seven days of service of such provisional assessment order upon him:
[(5) If the assessing officer reaches to the conclusion that unauthorised use of electricity has taken place, the assessment shall be made for the entire period during which such unauthorized use of electricity has taken place and if, however, the period during which such unauthorised use of electricity has taken place cannot be ascertained, such period shall be limited to a period of twelve months immediately preceding the date of inspection.] (6) The assessment under this section shall be made at a rate
equal to [twice] the tariff rates applicable for the relevant category of services specified in sub-section (5).
Explanation.- For the purposes of this section,- --
(a) "assessing officer" means an officer of a State Government or Board or licensee, as the case may be, designated as such by the State Government;
(b) "unauthorised use of electricity" means the usage of electricity -
(i) by any artificial means; or
(ii) by a means not authorised by the concerned person or authority or licensee; or
(iii) through a tampered meter; or [(iv) for the purpose other than for which the usage of electricity was authorised; or
(v) for the premises or areas other than those for which the supply of electricity was authorized."]
9. Section 126 has undergone an amendment on and with effect
from 15.06.2007, whereby sub-Sections (5) and (6) were suitably
amended enhancing the penalty also. Going by the scheme of Section
126, it is clear that if and when it was found that there is unauthorised
connected load, the Board officials are vested with powers to issue a
notice calling for objections to the provisional assessment made
against the unauthorised connected load and after receiving the
objection, the Board authorities are vested with powers to pass the
final determination order, after considering the objections raised to
the provisional assessment. The term 'unauthorised use of electricity'
is defined under clause (b) of Explanation to Section 126(6) of Act,
2003 to include the usage of electricity for the purposes for which it
was not authorised and the usage of electricity to any premises or
areas other than those for which the supply of electricity was
authorized.
10. The learned counsel for the petitioner in that regard has
invited my attention to the judgment of a learned Division Bench of
this Court in Sulabha Marketing Pvt. Ltd. v. KSEB,
Thiruvananthapuram and others [2017(3) KHC 563]. Paragraph
31 of the said judgment is relevant to the context and it reads thus:
"31. For the reasons stated hereinbefore, we hold as follows;
(i) The presence of the assessing officer at the time of inspection
and detection of unauthorised use of electricity in the premises of
a consumer is not a mandatory requirement for initiating
assessment proceedings under S.126(1) of the Act.
(ii) The expression 'unauthorised use of electricity' under S.126
of the Act deals with cases of unauthorised use even in the
absence of intention. Hence, the intention of the consumer is not
the foundation for invoking powers of the competent authority
and passing of an order of assessment under S.126 of the Act.
(iii) Whenever a consumer commits the breach of the terms of
the agreement, Regulations and the provisions of the Act by
consuming electricity in excess of the sanctioned / connected
load, such consumer would be in blame and under liability to pay
at the rate equal to twice the tariff applicable for the relevant
category of services in terms of S.126 of the Act.
(iv) The term 'tariff' in S.126(6) of the Act includes both fixed
charges and charges for the electricity supplied, which has to be
assessed in the case of a consumer indulged in unauthorised use
of electricity, at a rate equal to twice the tariff applicable for the
relevant category of services specified in sub-section (5).
(v) In case of unauthorised use of electricity in a higher tariff,
such assessment shall be made at the rate equal to twice the tariff
applicable for the relevant category of services attracting such
higher tariff for which electricity supplied was unauthorisedly
used and not the relevant category of service to which the
consumer belongs.
(vi) However, in the case of a consumer, who is blamed with
overdrawal of electricity in excess of sanctioned / connected load
in the very same premises and for the very same purpose, which
do not involve any change in tariff applicable for the relevant
category of services, which consumption has already been
metered and paid by the consumer, since such usage being not by
any artificial means or through a tampered meter, assessment
under S.126(6) of the Act can only be equal to twice the fixed
charges payable and such consumer cannot be saddled with the
liability to pay twice the energy charges applicable for the
relevant category of services, unless regularisation of such
additional connected load or enhancement of contract demand
necessitates upgradation of the existing distribution system or
enhancement of voltage level of supply.
(vii) In all other cases falling under Explanation (b) to S.126 of
the Act, the assessing officer is empowered to assess
unauthorised use of electricity at the rate prescribed in S.126(6)
and for the period specified in S.126(5), as amended by the
Electricity (Amendment) Act, 2007 for both fixed charges and
enerenergy charges. Penalty charges for current charges shall be
levied for proportionate energy charge and normal current charge
collected shall be deducted.
(viii) Though Regulation 51(1) of the Conditions of Supply,
2005 employs the term 'penalised', what is contemplated under
the said Regulation is only assessment of unauthorised use of
electricity in terms of S.126 of the Act for the period specified in
S.126(5) and at the rate specified in S.126(6) of the Act. As such,
Regulation 51(1) of the Conditions of Supply, 2005 is neither
ultra vires the provisions of S.126 of the Act nor unenforceable.
(ix) What is contemplated under Board Order dated 07/02/2008
is only assessment of unauthorised use of electricity in terms of
S.126 of the Act, as amended by the Electricity (Amendment)
Act, 2007, for the period specified in S.126(5) and at the rate
specified in S.126(5) of the Act. As such, the said Board Order is
neither ultra vires the provisions of S.126 of the Act nor
unenforceable."
11. The learned counsel for the petitioner relied upon finding No.
(vi). I cannot agree with the same, since the said finding would apply
only in a case where usage of excess quantity of electricity than the
sanctioned connected load takes place without adding any other
equipment to interfere with the sanctioned connected load. In my
considered view, the issue raised by the petitioner is guided by finding
Nos. (ii), (iii) and (iv) of the judgment, which specifies that whenever a
consumer commits breach of the terms and conditions of the
agreement, regulations and the provisions of the Act by consuming
electricity/connected load, such consumption would be in blame and
under liability to pay at the rate equal to twice the tariff applicable for
the relevant category of services in terms of Section 126 of the Act,
even without any intention. Therefore, I am of the definite view that
the petitioner is not entitled to get the benefit of finding No.(vi) of the
said judgment.
12. It is an admitted fact that the connected load sanctioned to
the petitioner was 7 KW. However, due to the usage of other
equipments, connected load exceeds by 23KW and thus reads 31KW.
Which thus means, there was an unauthorised connected load of
23KW. However, the petitioner contends that the billing officer issued
the bills for the period in question for 31KW and therefore, it can only
be presumed that the Board has accepted and approved the connected
load availed by the petitioner as 31KW. In fact, admittedly the
connected load that was granted to the petitioner was only 7KW.
Merely because the Billing Officer has issued bills for the consumption
of the electricity recording the connected load as 31KW, it would not
make the additional connected load authorised. The said issue is taken
care of under Section 126 of the Act, 2003 itself. The Kerala State
Electricity Supply Code, 2005 is made by the Kerala State Electricity
Regulatory Commission by virtue of the powers conferred by Section
50 r/w Section 181 of the Act, 2003. Regulation 27A of the Kerala
Electricity Supply Code, 2005, which deals with 'method of assessment
of the electricity charges payable in case of unauthorized use of
electricity and theft of electricity pending adjudication by the
appropriate court', reads thus:
"27A. Method of assessment of the electricity charges payable in case of unauthorized use of electricity and theft of electricity pending adjudication by the appropriate court. (1) Unauthorized use of electricity.
(a) Assessment. - If on an inspection of any place or premises or after inspection of equipments, gadgets, machines, devices found connected or used, or after inspection of records maintained by any person, the assessing officer comes to the conclusion that such person is indulging in unauthorized use of electricity, he shall provisionally assess to the best of his judgement the electricity charges payable by such person or any other person benefited by such use.
(b) The order of provisional assessment shall be served upon the person in occupation or possession or in charge of the place or premises in such manner as may be prescribed.
(c) The person on whom a notice has been served under subsection (b) shall be entitled to file objections, if any against the provisional assessment before the assessing officer, who may, after affording a reasonable opportunity of hearing to such person, pass a final order of assessment of electricity charges payable by such person.
d) Any person served with the order of provisional assessment may accept such assessment and deposit the assessed amount with the licensee within seven days of service of such provisional assessment order upon him. In case the
person deposits the assessed amount, he shall not be subjected to any further liability or any action by any authority whatsoever.
(e) If the assessing officer reaches to the conclusion that unauthorized use of electricity has taken place, it shall be presumed that such unauthorized use of electricity was continuing for a period of three months immediately preceding the date of inspection in case of domestic and agricultural services and for a period of six months immediately preceding the date of inspection for all other categories of services, unless the onus is rebutted by the person occupier or possessor of such premises or place.
(f) The assessment under this section shall be made at a rate equal to one and a half times the tariff applicable for the relevant category of services specified in sub clause (e)."
13. Therefore, on a reading of Section 126 of the Act, 2003 and
Regulation 27A, it is clear that a clear cut procedure is prescribed for
dealing with unauthorised load, and merely because the Billing Officer
has calculated the excess connected load in the successive monthly
bills, that will not regularise the unauthorised connected load. A
connected load is fixed by the Board and if additional connected load is
required, necessary sanction has to be secured from the Board
authorities and thus refix the connected load. There is no case for the
petitioner that he has sought for re-fixing the connected load provided
to him, which was only 7KW.
14. Thus, on appreciation of the provisions of the Act, 2003 and
the Kerala Electricity Supply Code, 2005, it is clear that the assessing
officer has rightly proceeded against the petitioner, followed the
mandatory requirements under law and passed the final order. Even
though the petitioner had a statutory remedy to prefer an appeal
under Section 127 of Act 2003 read with regulation 27A of the Kerala
Electricity Supply Code, 2005, he has not availed the said benefit.
Reckoning all those aspects, it cannot be said that the Assessing
Officer has committed any illegality or arbitrariness in passing the final
order determining the liability of the petitioner for the additional
unauthorised load of 23KW.
15. Be that as it may, the petitioner has raised a contention that
Regulation 51 of KSEB Terms and Conditions of Supply, 2005 is ultra
vires the provisions of Act, 2003, since there is no enabling power for
the KSEB to make any such regulation. However, Section 30 of the
Kerala Electricity Supply Code, 2005 makes it clear that the licensee
i.e., the KSEB Limited within one month of coming into force of the
Supply Code, 2005 shall submit to the Commission for approval the
"Draft Terms and Conditions of Supply" in accordance with the Supply
Code, 2005 in regard to the following aspects mentioned thereof:
a) Application form for supply of electricity
b) Estimate amount for giving WP/OH service connection
c) Estimate amount for giving service connection - HT
d) Estimate amount for extension of line - Single Phase/Three Phase. LT
e) Estimate amount for extension of line - HT/EHT
f) Estimate amount for HT/EHT sub-station
g) Format of agreement for supply of electricity.
h) Format of installation completion report
i) Format of no-objection certificate
j) Initial Security deposit towards charges for power supply for different
category of consumers (LT, HT and EHT)
k) Security deposit for meter/metering equipment for different categories
of consumers. (LT, HT and EHT)
l) Schedule of miscellaneous charges
16. Therefore, on a reading of the said provision, it is clear that
the KSEB was duty bound to make the Terms and Conditions of Supply
and therefore it can only be legally presumed that by virtue of the
power conferred under Regulation 30 of the Supply Code, 2005, the
KSEB Terms and Conditions of Supply, 2005 was made by the Board.
Regulation 51 of the KSEB Terms and Conditions of Supply, 2005 deals
with 'unauthorised load', which reads thus:
"51. Unauthorised load--Where a Low Tension Consumer exceeds the connected load and/or resorts to unauthorized additional load and if the connected load exceeds 100 KVA, the unauthorized
additional load shall be disconnected by the consumer with-in twenty-four hours of detection of the unauthorized load by the Board's officers or take action to regularize the unauthorized additional load. If he fails to disconnect the unauthorized load within the time stipulated, the power supply to the premises shall be disconnected after the expiry of twenty-four hours. A notice to this effect shall be issued to the consumer by the Board's officer immediately on detection of the unauthorized additional load.
(1) The unauthorized additional load in case of LT/HT/EHT consumers shall be penalized as per Clause 50 (5) & (6) above.
(2) The penalty for unauthorized additional load shall be levied till the said unauthorized additional load is removed or regularized as per rules.
If the consumer fails to pay the bill amount, the service shall be disconnected without further notice. It shall be reconnected only after payment of penalty and other charges, if any, as per rules and removal/regularization of the unauthorized additional load by the consumer (3) If the consumer wants to continue to connect the additional load and if the total connected load exceeds 100 KVA, he has to convert the Low Tension service into High Tension for which he shall be given three months time from the date of detection of unauthorized load. But the penalty as in clause 50 (1) shall be payable by the consumer till the conversion of the service is permitted by the competent authority.
(4) In case of Low Tension consumers whose connected load does not exceed 100 KVA but who have exceeded the contracted load by 10% by adding unauthorized additional load, the procedure mentioned in clause 50 (1)shall be applicable. The unauthorized
load should be regularized by the consumer within a period of three months on application to the Assistant Executive Engineer and after payment of additional security deposit and other charges as per rules. The regularization shall be given effect from the date of collection of additional security deposit and other charges, if any, as per rules. The Assistant Executive Engineer shall issue proceedings to this effect. Penal charges as mentioned in clause 50 (1) shall be paid till the date of payment of additional security deposit.
(5) In the case of HT and EHT consumers the unauthorized additional load shall got disconnected by the consumer within twenty-four hours of detection of the unauthorized load by the Board's officer or take action to regularize the unauthorized additional load. A notice to this effect shall be issued to the consumer by the Board's officer immediately on detection of the unauthorized load. If the consumer fails to disconnect the unauthorized load within the time stipulated, the power to the premises shall be disconnected after the expiry of twenty-four hours.
As per agreement, change in installation should be with the permission of the KSE Board. Hence loads connected in excess of the connected load specified in the agreement shall be the additional unauthorized load and will be treated as unauthorized MD for charging penalty.
(6) The tariff applicable for charging the penalty shall be the HT/EHT tariff that would have been applicable for the unauthorized load depending upon the purpose for which the connection was utilized. If the consumer fails to pay the bill amount, the service shall be disconnected without further notice. It shall be reconnected only after payment of penalty and other charges, if any, as per rules
and removal/regularization of the unauthorized additional load by the consumer on application before the competent authority within a period of three months from the date of detection of the unauthorized additional load.
(7) Any person aggrieved by a final order of assessment under sub clause (5) & (6) above may, within thirty days of the said order, prefer an appeal in Form No.18 accompanied by the fee at the rate ordered by the Commission from time to time to the Deputy Chief Engineer of the Electrical Circle concerned.
17. Moreover, Regulation 51 of the KSEB Terms and Conditions
of Supply, 2005 is only an enabling provision empowering the Board
officials to take action against the unauthorised load and to regularise
the same, which can only be said to be a provision consequent to
Section 126 of the Act, 2003 and Regulation 27A of the Supply Code,
2005. The said aspect was also considered by the Division Bench in
Sulabha Marketing Pvt. Ltd. (supra), wherein it was held that
Regulation 51(1) of the KSEB Terms and Conditions of Supply, 2005 is
neither ultra vires the provisions of Section 126 of the Act nor
unenforceable. Therefore, the challenge made against Regulation 51
of the KSEB Terms and Conditions of Supply, 2005 is ultra vires of the
Act, 2003 cannot be sustained under law.
18. Taking into account the above factual and legal
circumstances, I do not think, the Assessing Officer has committed any
act of illegality or arbitrariness in passing Ext.P9 order dated
27.01.2010 justifying this Court to interfere by exercising the power of
judicial review under Article 226 of the Constitution of India. In fact,
no interim order was granted by this Court against the recovery of the
amount and therefore, if the amount is not already recovered by the
Board, the petitioner is given the liberty to pay the amount in two
instalments, first of which shall be paid within 45 days from today and
the balance amount within another 45 days.
Upshot of the above discussion is that the writ petition fails and
accordingly, it is dismissed, subject to the time granted for payment
sd/-
SHAJI P. CHALY, JUDGE.
Rv
APPENDIX
PETITIONER'S/S EXHIBITS:
EXHIBIT P1 TRUE COPY OF THE BILL DATED 17-08-2009.
EXHIBIT P2 TRUE COPY OF THE COMMUNICATION DATED 17-08-
2009.
EXHIBIT P3 TRUE COPY OF THE PENAL BILL ON 22-03-2006 FOR AN AMOUNT OF RS. 30,400/-.
EXHIBIT P4 TRUE COPY OF THE INVOICE DATED 16-07-2007.
EXHIBIT P5 TRUE COPY OF THE BILL DATED 15-06-2007.
EXHIBIT P6 TRUE COPY OF THE COMPLAINT BEFORE THE 3RD RESPONDENT.
EXHIBIT P7 TRUE COPY OF THE ORDER DATED 4-11-2009.
EXHIBIT P8 TRUE COPY OF THE OBJECTIONS DATED 23-11-2009.
EXHIBIT P9 TRUE COPY OF THE ORDER BEARING NO. DB41.VDLA-
AE/09-10/DATED 27-01-2020.
EXHIBIT P10 TRUE COPY OF THE B.O.(FB) NO. 1291/2002(PLG.COM 4206/01DATED 18-09-2002.
EXHIBIT P11 TRUE COPY OF THE B.O.(FM) NO. 368/2008 (DPCI/C-
G1/182/2007 DATED 07-02-2008 ISSUED BY THE 1ST RESPONDENT.
EXHIBIT P12 TRUE COPY OF THE DEMAND NOTICE DATED NIL.
/True Copy/
P.S To Judge.
rv
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!