Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Mangal Reality vs Nandkumar
2025 Latest Caselaw 8803 Kant

Citation : 2025 Latest Caselaw 8803 Kant
Judgement Date : 25 September, 2025

Karnataka High Court

M/S Mangal Reality vs Nandkumar on 25 September, 2025

Author: H.P.Sandesh
Bench: H.P.Sandesh
                                            -1-
                                                      NC: 2025:KHC-K:5854-DB
                                                  RERA.A No. 200001 of 2025


                   HC-KAR




                             IN THE HIGH COURT OF KARNATAKA,

                                    KALABURAGI BENCH

                       DATED THIS THE 25TH DAY OF SEPTEMBER, 2025

                                         PRESENT
                            THE HON'BLE MR. JUSTICE H.P.SANDESH
                                            AND
                             THE HON'BLE MR. JUSTICE T.M.NADAF


                              RERA APPEALS NO.200001 OF 2025
                   BETWEEN:

                   M/S MANGAL REALITY,
                   REPRESENTED BY ITS MANAGING DIRECTOR,
                   HAVING ITS REGISTERED OFFICE AT A2 AND A3,
                   SHIVASHARAN SANKIRAN,
                   KHUBA PLOT,
                   COURT ROAD,
                   KALABURAGI-585 103.

                                                                ...APPELLANT
Digitally signed
by
BASALINGAPPA       (BY SRI. PREETAM DEULGAONKAR, ADVOCATE)
SHIVARAJ
DHUTTARGAON
Location: HIGH
COURT OF
KARNATAKA
                   AND:

                   NANDKUMAR S/O LATE SHARANAPPA NAREL,
                   AGED ABOUT 45 YEARS,
                   OCC: SOFTWARE ENGINEER,
                   R/O. FLAT No. G-11,
                   SRI SAI ENCLAVE,
                   4TH CROSS, THULASI LAYOUT,
                   KASAVANAHALLI, BENGALURU-560 035.

                                                              ...RESPONDENT

                   (RESPONDENT NANDKUMAR - SERVED)
                               -2-
                                          NC: 2025:KHC-K:5854-DB
                                    RERA.A No. 200001 of 2025


HC-KAR




     THIS RERA APPEAL IS FILED U/S. 58 OF THE KARNATAKA
REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016,
PRAYING TO ALLOW THE APPEAL AND SET ASIDE THE ORDER
DATED 28.01.2025 PASSED BY THE KARNATAKA REAL ESTATE
APPELLATE    TRIBUNAL      BANGALORE      IN   APPEAL   (K-REAT)
NO.42/2023 AND CONFIRM THE ORDER DATED 19.12.2022
PASSED BY THE KARNATAKA REAL ESTATE REGULATORY
AUTHORITY IN COMPLAINT NUMBER CMP/190104/0001825, IN
THE INTEREST OF JUSTICE AND SUBSEQUENTLY DISMISS THE
COMPLAINT OF THE FIRST RESPONDENT. KINDLY GRANT ANY
OTHER RELIEF TO THE APPELLANT IN CONSIDERATION OF THE
FACTS AND CIRCUMSTANCES OF THE PRESENT CASE.


     THIS APPEAL HAVING BEEN HEARD AND RESERVED FOR
JUDGMENT       ON    23.08.2025     AND      COMING     ON   FOR
'PRONOUNCEMENT OF JUDGMENT', THIS DAY, THE COURT
DELIVERED THE FOLLOWING:


CORAM:    HON'BLE MR. JUSTICE H.P.SANDESH
          AND
          HON'BLE MR. JUSTICE T.M.NADAF


                       CAV JUDGMENT

(PER: HON'BLE MR. JUSTICE T.M.NADAF)

This second appeal is filed by the Promoter under

Section 58 of the Real Estate (Regulation and

Development), 2016 (for short, 'the Act, 2016') calling in

NC: 2025:KHC-K:5854-DB

HC-KAR

question the order dated 28.01.2025 in Appeal (K-REAT)

No.42/2023 passed by the Karnataka Real Estate

Appellate Tribunal, Bengaluru, whereby the appeal filed by

the allottee comes to be allowed setting aside the

judgment dismissing the complaint being

CMP/190104/0001825 dated 19.12.2022 by the

Adjudicating Authority.

2. Though this appeal is listed for admission, with

the consent of learned counsel for the appellant as the

respondent is served and unrepresented, taken up for final

disposal.

3. The brief outline of fact leading to the filing of

this second appeal are as under:

The respondent/allottee (hereinafter referred to as

'allottee') had booked a plot bearing No.75, measuring

4000 sq. ft. in a Real Estate Project, known as 'Gita

Nagar', developed by the appellant - M/s. Mangal Reality

(hereinafter referred to as 'Promoter'). Both the parties

NC: 2025:KHC-K:5854-DB

HC-KAR

have entered into an agreement dated 02.01.2012,

wherein sale consideration was fixed at Rs.14,20,000/-,

payable in 59 monthly installments, commencing from

03.01.2012. The allottee has paid a sum of Rs.10,05,000/.

As there was delay on the part of the Promoter in

executing the Project within the time stipulated, the

allottee did not paid the subsequent EMIs towards sale

consideration, subsequently, offered a plot measuring

3874 sq. ft. lesser than the one for which the agreement

was executed. That apart, the Promoter sought extra

payment and additional amount. Accordingly, the allottee

filed a complaint before the Regulatory Authority seeking a

direction to hand over the possession of the plot and

interest on delayed period and direction to complete the

Project.

4. Subsequent to registering the complaint, in

response to the notice, the promoter appeared through its

counsel before the Regulatory Authority and filed

statement of objections admitting the fact that there was

NC: 2025:KHC-K:5854-DB

HC-KAR

an agreement dated 02.01.2012 for sale of plot No.75

(New No.91) in the Project namely, 'Gita Nagar'. In the

agreement itself, it was made clear by the promoter to the

allottee, that in addition to payment of sale consideration,

he will have to pay additional sum towards Government

levies and development charges etc. for the said plot. The

allottee required to pay all the installments in timely

manner, however he has defaulted. Vide communication

dated 09.08.2013, when the same was demanded along

with delay charges, but, the allottee has failed to pay

remaining installments even after repeated reminders.

5. The plot No.75 earlier allotted for which the

agreement was entered. In the agreement, the

measurement of the said plot was shown as 4000 sq. ft.

i.e., prior to the sanction of the layout plan. However, as

per the sanctioned layout plan, the measurement of the

plot had been reduced to 3877 sq. ft. which the Promoter

taken into consideration, proportionately reduced the total

price by Rs.355/- per sq. ft. and reduced the sum to an

NC: 2025:KHC-K:5854-DB

HC-KAR

extent of Rs.44,730/- out of Rs.14,20,000/-, fixed under

the agreement. As per the Promoter, the Urban

Development Authority, Kalaburagi on 07.10.2015

sanctioned the layout plan for the development of halted

development Project consisting 329 sites of various

dimensions and 40% of the said sites i.e., 132 sites were

released for sale. The EMI commenced from the date of

agreement and ended on 02.01.2017 i.e., after the

completion of 59th month. The release of plot bearing

No.91 to the allottee had been obtained as on 31.12.2016

and duly intimated to the allottee. As per Clause-12 of the

Agreement, the allottee required to pay Government levies

to an extent of Rs.44,955/-. Since there is delay in

payment and additional charges towards Government levy,

the Promoter issued a legal notice on 08.07.2022

canceling the plot allotted to the allottee for non-

adherence to payment conditions, which is in terms of

Clause No.8 contained in the Agreement. The Clause No.8

NC: 2025:KHC-K:5854-DB

HC-KAR

is reproduced by us as depicted in para No.11 of the

Appellate Court judgment, reads as under:

"8. That, it is agreed if the Second party fails to pay three installments his membership will be Cancelled and the installments already paid by Second Party stands forfeited to the First Party as damages for breach of contract as Second Party failed to make the payment in time as agreed."

6. Upon submission of pleadings, the Karnataka

Real Estate Regulatory Authority proceeded to hear the

parties and subsequently passed the judgment, whereby

dismissed the petition holding that the allottee is not

entitled for the relief claimed. The Regulating Authority

further observed that the relief of compensation for mental

agony does not come under the purview of the Regulating

Authority. The allottee required to file complaint before

the Adjudicating Officer, RERA for claiming such relief.

Accordingly, proceeded to dismiss the complaint.

NC: 2025:KHC-K:5854-DB

HC-KAR

7. Feeling aggrieved by the said judgment, the

allottee preferred an appeal under Section 44 of the Act,

2016 before the Karnataka Real Estate Appellate Tribunal,

Bengaluru (for short, 'the Appellate Tribunal'). Before the

Appellate Tribunal, the allottee has contended that in view

of delay in Project and offering the site which is lesser in

dimensions than the one under the agreement entered

into, though the allottee has paid more than 75% of the

amount towards sale consideration. In view of delay, the

allottee on several occasion intimated the Promoter the

reason for delayed payment and had also stated that there

is default committed by both the parties i.e., allottee as

well as the Promoter. The reason for non-payment is

delayed execution of Project work and allotment of site in

plot No.91 instead of plot No.75 in a reduced

measurement i.e., 3875 sq. ft. instead of 4000 sq. ft. and

the Promoter had demanded additional payments under

the guise of Government levy. When the plot was

demanded along with interest, the same was unilaterally

NC: 2025:KHC-K:5854-DB

HC-KAR

cancelled by the Promoter invoking Clause No.8 of the

agreement without there being any reason for forfeiting

the amount, paid towards the sale consideration. This

aspect of the matter has not been properly considered by

the Regulatory Authority which has resulted in dismissing

the complaint causing miscarriage of justice to the

allottee, who had made payments of nearly 75% of total

sale consideration.

8. The Promoter refuted the submissions of the

learned counsel for the allottee before the Appellate

Tribunal contending that the Regulatory Authority having

considered the materials placed before it and in view of

breach of Clause No.8 comes to a right conclusion that

there is fault committed by the allottee in making the

regular payments and accordingly held that he is not

entitled for any relief at the hands of Regulatory Authority

and for the complaint of compensation for mental agony

and other as contended by the allottee, relegated him to

file necessary application before the Adjudicating Authority

- 10 -

NC: 2025:KHC-K:5854-DB

HC-KAR

as contemplated under the provisions of the Act, 2016.

The said judgment does not call for any interference at the

hands of the Appellate Authority as the same is well

reasoned and sought to dismiss the appeal.

9. The Appellate Tribunal after hearing both sides,

formed a point for consideration as to whether the

Appellant/allottee proves that the Authority was not

justified in dismissing the complaint and answered the

point No.1 partly in affirmative holding that the dismissal

of the complaint is unjustified, whereby allowed the

appeal, setting aside the judgment passed by the

Regulatory Authority dated 19.12.2022 stated supra and

modified the impugned order, directing the respondent/

Promoter to execute the full-fledged sale deed in favour of

the allottee receiving a sum of Rs.4,15,225/- which

includes Rs.3,70,270/- towards the sale consideration and

Rs.44,955/- towards Government levy within a period of

three months from the date of receipt of copy of the

judgment.

- 11 -

NC: 2025:KHC-K:5854-DB

HC-KAR

10. Calling in question this order passed by the

Appellate Tribunal, the Promoter is before this Court in this

second appeal.

11. Heard Sri Preetam Deulgaonkar, learned

counsel appearing for the appellant. Respondent though

served unrepresented.

12. Sri Preetam Deulgaonkar vehemently submitted

that the Appellate Tribunal failed to consider well reasoned

judgment of the Regulatory Authority, wherein the

Regulatory Authority considering Clause No.8, which

clearly prescribes that in the event any default in paying

three installments by the member, the agreement would

be cancelled and all the installments already paid stands

forfeited in favour of the Promoter as damages for breach

of contract in view of failure on the part of second party to

make payment in time as agreed, dismissed the

complaint. There is no delay caused by the

appellant/Promoter as alleged. The Promoter in terms of

- 12 -

NC: 2025:KHC-K:5854-DB

HC-KAR

law, got sanctioned the plan, however in view of changed

plan, there is reduction in the measurement of the site

which he has intimated to the allottee and also agreed to

deduct the amount towards reduced measurement to an

extent of Rs.355/- per sq.ft. and re-fixed the sale

consideration only to the extent 3875 sq. fq. instead of

4000 sq. ft. He has given intimation subsequent to

change of sanction plan. There is a delay on the part of

the allottee in payment of regular installments. Despite

several reminders, there is no payment. Since February

2016, there is total stoppage of installments. The Project

was completed as agreed in the agreement within the

stipulated time. It is the allottee who has defaulted in

making the proper payments. This in terms of Clause-8

amounts to a breach of conditions and failure on the part

of the allottee, entitling the Promoter to cancel the

allotment as well as forfeiting the amounts already paid

towards sale consideration. This aspect of the matter has

not been properly considered by the Appellate Tribunal.

- 13 -

NC: 2025:KHC-K:5854-DB

HC-KAR

The Appellate Tribunal swayed, on the aspect that the

RERA Act is a social legislation enacted to protect the

interest of home buyers and promote transparency,

accountability in the real estate sector and this aspect has

been failed to consider by the Regulatory Authority. That

apart, the reason for the Appellate Tribunal to consider the

case of the allottee is the e-mail sent on 05.11.2018,

wherein the allottee has stated that the Project was

supposed to get completed by January, 2017 was actually

completed in March, 2018. There was delay of 13 months

from January, 2017 and the allottee has further stated

that he has paid Rs.10,05,000/- towards the sale

consideration, he has also stated in the said e-mail that

the delay charges on Rs.10,05,000/- be adjusted towards

the delay charges for the remaining amount to be paid by

him and after re-calculating the said sums to the plot, he

is ready to pay the amount. This has taken the Appellate

Tribunal to hold that the order passed by the Regulatory

Authority dismissing the appeal as unjustified. Further, to

- 14 -

NC: 2025:KHC-K:5854-DB

HC-KAR

hold that the cancellation by the Promoter and forfeiture of

the amount is highly arbitrary when considerable amount

towards the sale deed has already been paid. Accordingly

sought that the appeal deserves to be allowed setting

aside the judgment passed by the Appellate Tribunal.

13. To buttress his argument, the learned counsel

appearing for the appellant relied on the judgment of the

Hon'ble Apex Court in the case of M/s. Newtech

Promoters and Developers Pvt. Ltd. Vs. State of U.P.

and Others etc.1 and stressed on para No.80, which we

reproduce as under:

"80. The further submission made by learned counsel for the appellants that if the allottee has defaulted the terms of the agreement and still refund is claimed which can be possible, to be determined by the adjudicating officer. The submission appears to be attractive but is not supported with legislative intent for the reason that if the allottee has made a default either in making installments or made any

C.A.No.6745-6749 of 2021

- 15 -

NC: 2025:KHC-K:5854-DB

HC-KAR

breach of the agreement, the promoter has a right to cancel the allotment in terms of Section 11(5) of the Act and proviso to sub- section 5 of Section 11 enables the allottee to approach the regulatory authority to question the termination or cancellation of the agreement by the promoter and thus, the interest of the promoter is equally safeguarded."

14. Having heard the learned counsel for the

appellant, perused the entire appeal papers, the only

question that would arise for consideration is:

Whether the appellant has made out any case to consider the appeal on any substantial question of law to answer even to admit the appeal to answer his claims?

15. Our answer to the above point for consideration

is in 'Negative' for the following:

REASONS

16. Before dwelling on the point for consideration, it

is profitable to answer on the power under Section 58 of

- 16 -

NC: 2025:KHC-K:5854-DB

HC-KAR

the Act, 2016. As per Section 58 of the Act, 2016, to

maintain an appeal before this Court which is as good as a

regular second appeal within the meaning of Section 100

of CPC, the appeal must contain substantial question of

law, involved in the case. For easy reference, we

reproduce Section 58 of the Act, 2016, which reads as

under:

"58. Appeal to High Court - (1) Any person aggrieved by any decision or order of the Appellate Tribunal, may, file an appeal to the High Court, within a period of sixty days from the date of communication of the decision or order of the Appellate Tribunal, to him, on any one or more of the grounds specified in section 100 of the Code of Civil Procedure, 1908 (5 of 1908):

Provided that the High Court may entertain the appeal after the expiry of the said period of sixty days, if it is satisfied that the appellant was prevented by sufficient cause from preferring the appeal in time.

Explanation- The expression "High Court"

means the High Court of a State or Union territory where the real estate project is situated.

- 17 -

NC: 2025:KHC-K:5854-DB

HC-KAR

(2) No appeal shall lie against any decision or order made by the Appellate Tribunal with the consent of the parties."

17. To the query of Court's question, the appellant

has submitted that he has raised point for consideration

totally seven in number and same be read as substantial

question of law.

18. As could be seen from the records, it is clear

that there was an agreement dated 02.01.2012 between

the allottee and the Promoter for allotment of a site

bearing No.75, measuring 4000 sq. ft. and sale

consideration was fixed at Rs.14,20,000/- which is to be

paid in 59 equal monthly installments by the allottee to

the Promoter. As per Clause-12 of the Agreement, the

allottee apart from paying sale consideration is required to

make good the Government levy, if any, to be paid as

agreed in the said agreement.

- 18 -

NC: 2025:KHC-K:5854-DB

HC-KAR

19. It is also on record and not disputed by the

Promoter, that a sum of Rs.10,05,000/- paid towards sale

consideration. It is also not in dispute that earlier site

No.75 being changed to site No.91 as also the

measurement of the same reduced to 3875 sq. ft. from

4000 sq. ft. It is also not in dispute that the balance to be

paid towards the sale consideration after deducting the

amount towards the measurement reduced would be

Rs.3,70,270/-. It is also not in dispute that the allottee is

required to pay additional sum of Rs.44,955/- towards

Government levy. The e-mail sent by the allottee which

has been reproduced by the Appellate Tribunal in para

No.15 clearly states that there is a delay in executing the

project within the stipulated time and non-disclosers of

particulars sought by the Promoter; so also there is delay

on the part of the allottee to pay the installments agreed

by him. The fact remains that a considerable amount

nearly to 75% has already been paid by the allottee

towards the sale consideration for the site allotted in his

- 19 -

NC: 2025:KHC-K:5854-DB

HC-KAR

favour. In view of changed circumstances, the allottee is

required to pay reduced amount towards the sale

consideration. The balance payable by him is only

Rs.3,70,270/- along with Government levy which is fixed

at Rs.44,955/-. The clause which has been referred by the

Appellate Tribunal in paragraph No.11 clearly states that if

there is a failure to make three installments, the

membership will be cancelled and the installments already

paid would be forfeited as damages for breach of contract

for the failure of the allottee to pay the installments.

20. In the peculiar facts and circumstances of the

case where 75% of sale consideration has been paid, the

rest is withheld only for the reason that there is delay in

completing the project. As per the agreement, the project

required to be completed on or before, January, 2017.

The shortcomings pointed by the allottee towards

Promoter is, he has not supplied the required particulars in

terms of Section 11 of the Act, 2016 and Rule 15 of the

- 20 -

NC: 2025:KHC-K:5854-DB

HC-KAR

Karnataka Real Estate (Regulation and Development)

Rules, 2017 (hereinafter referred to as the Rules, 2017)

21. In view of the same, since there is shortfall

attributable to both the parties, none of the parties are

entitled for any interest as contemplated under Sections

16 and 17 of the Act, 2016. The allottee by his e-mail has

clearly stated the reason for delayed payment and also

has requested to adjust the delayed charges on

installment towards the delay charges payable to the

Promoter by him for delay in handing over the possession.

The agreement was entered in the year 2012, whereas the

plan was sanctioned in the year 2015. The plot agreed to

be allotted was bearing No.75, measuring 4000 sq. ft. that

has been reduced to 3875 sq. ft. and entire plot has been

changed to plot No.91 though the promoter has now

agreed for reduced rate than the one fixed earlier and

nothing is placed by the Promoter to say that the entire

project has been completed without there being any

shortfalls on the part of the Promoter. This aspect of the

- 21 -

NC: 2025:KHC-K:5854-DB

HC-KAR

matter has been missed by the Regulating Authority which

has been considered by the Appellate Authority.

22. No doubt, it is true that the Act, 2016 is

enacted with the object to safeguard the interest of both

the parties and give a transparency in the transaction and

security to both the parties. The paragraph No.80 in M/s

M/s. New Tech Promoters (supra), relied on by the

appellant clearly shows that the Promoter under the

provisions has a right to cancel allotment owing to default

attributable to allottee in terms of the agreement towards

the payment and the allottee can approach the Regulatory

Authority to question the termination or cancellation of

agreement by the Promoter. Accordingly, in this context

the Hon'ble Apex Court has observed that under the Act,

2016, the interest of the Promoter is equally safeguarded,

but the same cannot be construed as the allottee bound to

pay interest on the delayed payment as argued by the

learned counsel Sri Preetham.

- 22 -

NC: 2025:KHC-K:5854-DB

HC-KAR

23. The appellant has not placed any material on

record to show that he has made any application seeking

for interest as contemplated under Section 16 of the Act,

2016. Even there is nothing on record, to suggest that

there is an order by the Regulatory Authority, that the

appellant is entitled for interest on the delayed payment.

The Appellate Tribunal safeguarded the interest of both

parties taking into consideration the default committed by

both the parties in directing the appellant to execute the

full-fledged sale deed after receipt of entire amount stated

in the order including the Government levy by the allottee

within three months from the date of receipt of copy of the

order.

24. The Hon'ble Apex Court in M/s. New Tech

Promoters (supra) extensively considered the object and

provisions of the Act of 2016 in Paragraph Nos.9 to 37.

The object with which the Act, 2016, enacted indicates

that primary position of the Regulatory Authority is to

regulate the real estate sector having jurisdiction to

- 23 -

NC: 2025:KHC-K:5854-DB

HC-KAR

ensure compliance with the obligation cast upon on the

Promoters. The opening statement of objects and reasons

with which the Act enacted reads as under:

" The real estate sector plays a catalytic role in fulfilling the need and demand for housing and infrastructure in the country. While this sector has grown significantly in recent years, it has been largely unregulated, with absence of professionalism and standardisation and lack of adequate consumer protection. Though the Consumer Protection Act, 1986 is available as a forum to the buyers in the real estate market, the recourse is only curative and is not adequate to address all the concerns of buyers and promoters in that sector. The lack of standardisation, has been a constraint to the healthy and orderly growth of industry. Therefore, the need to regulating the sector has been emphasised in various forums.

2. In view of the above, it becomes necessary to have a Central legislation, namely, the Real Estate (Regulation and Development) Bill, 2013, in the interest of the effective consumer protection, uniformity and standardisation of business practices and transactions in the real

- 24 -

NC: 2025:KHC-K:5854-DB

HC-KAR

estate sector. The proposed Bill provides for the establishment of the Real estate Regulatory Authority (the Authority) for regulation and promotion of real estate sector and to ensure sale of plot, apartment or building, as the case may be, in an efficient and transparent manner and to protect the interest of consumers in real estate sector and establish the Real Estate Appellate Tribunal to hear appeals from the decisions, directions or orders of the Authority."

25. As such, it is clear from the statement of object

and reasons, the Act was introduced with an object to

ensure greater accountability towards consumers, to

significantly reduce frauds and delays and also the current

high transaction costs, and to balance the interests of

consumers and promoters by imposing certain

responsibilities on both, and to bring transparency of the

contractual conditions, set minimum standards of

accountability and a fast-track dispute resolution

mechanism. It also proposes to induct professionalism

and standardization in the sector, thus paving the way for

accelerated growth and investments in the long run.

- 25 -

NC: 2025:KHC-K:5854-DB

HC-KAR

Some of the important objects and reasons stated to

impose, relevant to mention here are:

"4. xxxxx.

d) to impose liability upon the promoter to pay such compensation to the allottees, in the manner as provided under the proposed legislation, in case if he fails to discharge any obligations imposes on him under the proposed legislation.

(f) the functions of the Authority shall, inter alia, include - (i) to render service to the appropriate Government in matters relating to the development of real estate sector; (ii) to publish and maintain a website of records of all real estate projects for which registration has been given, with such details as may be prescribed; (iii) to ensure compliance of the obligations cast upon the promoters, the allotees and the real estate agents under the proposed legislation.

xxx

(i) to appoint an adjudicating officer by the Authority for adjudging compensation under

- 26 -

NC: 2025:KHC-K:5854-DB

HC-KAR

sections 12, 14 and 16 of the proposed legislation."

26. Now looking to the point for consideration

raised in the appeal as per the appellant are the

substantial question of law involved in this appeal, we find

all the points for consideration framed by the appellant are

on facts. None of the points for consideration raised by

him suggest involving any substantial question of law.

27. The finding of the Appellate Tribunal is on

material fact placed before it. The clause No.8 as

contended by the appellant cannot be stretched too far to

make unjust enrichment in a case where 75% of amount

of sale consideration has been paid and balance withheld

for short of execution of the Project in time and non-

furnishing of particulars sought by the allottee. As there is

no substantial question of law involved in the appeal, the

same deserves to be dismissed. We find no reasons to

interference with the judgment passed by the Appellate

Tribunal which has properly considered the case put-forth

- 27 -

NC: 2025:KHC-K:5854-DB

HC-KAR

by the parties even taking into consideration the Clause-8

as well as Clause No.12 in the agreement so also Section

11 of the Act, 2016. We find no infirmities in the order

passed by the Appellate Tribunal.

28. The learned counsel Sri Preetam Deulgaonkar

while arguing the matter had submitted that the direction

issued is with regard to payment of amount by the allottee

within three months and thereafter the appellant to

execute the sale deed. However, the allottee without

making payment approached the Appellate Tribunal and

keeping the Promoter exparte, the Appellate Tribunal

directed the party to approach Civil Court to execute the

Award and in terms of such direction, execution notice has

been issued by the Civil Court executing the order passed

by the Appellate Court. The allottee is duty bound to

make the payment first to seek for execution of sale deed,

sought that and this requires clarification.

- 28 -

NC: 2025:KHC-K:5854-DB

HC-KAR

29. For the foregoing reasons, we find no

substantial question of law involved in the appeal, the

same sans merits, accordingly dismissed, however, with

an observation that in terms of the order passed by the

Appellate Tribunal for the Promoter to execute the sale

deed within the time bound period, the allottee required to

make the balance amount stated in the order i.e., in total

Rs.4,15,225/- first, which includes a sum of Rs.3,70,270/-

towards balance sale consideration and Rs.44,955/-

towards Government levy.

With the above observations, the appeal stands

dismissed.

Sd/-

(H.P.SANDESH) JUDGE

Sd/-

(T.M.NADAF) JUDGE BL

CT: AK

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter