Citation : 2025 Latest Caselaw 6207 Kant
Judgement Date : 16 June, 2025
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 16TH DAY OF JUNE, 2025
PRESENT
THE HON'BLE MRS. JUSTICE ANU SIVARAMAN
AND
THE HON'BLE DR. JUSTICE K.MANMADHA RAO
MISCELLANEOUS FIRST APPEAL NO.633 OF 2019
(LAC)
BETWEEN:
1. SRI. S. BALAJI
S/O. LATE BYRAPPA
AGED ABOUT 70 YEARS
R/AT SRIRANGANATHA NILAYA
7TH CROSS,
SREE CHANNABASAVESHWARA LAYOUT
UPPARAHALLI
TUMAKURU
2. SRI. VEERABHADHRAIAH
S/O. LATE NANJAIAH
AGED ABOUT 55 YEARS
R/AT SOGENAHALLI VILLAGE
KASABA HOBLI
MADHUGIRI TALUK
TUMAKURU DISTRICT
3. SRI. S.N. BYRAPPA
S/O. LATE NANJAIAH
AGED ABOUT 55 YEARS
R/AT SOGENAHALLI VILLAGE
KASABA HOBLI
MADHUGIRI TALUK
TUMAKURU DISTRICT ... APPELLANTS
(BY SRI. G. S. VENKAT SUBBARAO, ADVOCATE)
-
2
AND:
THE LAND ACQUISITION OFFICER
AND ASSISTANT COMMISSIONER
MADHUGIRI SUB-DIVISION
MADHUGIRI - 572 132
TUMAKURU DISTRICT ... RESPONDENT
(BY SRI. G.S. ARUN, AGA)
THIS MFA IS FILED U/S 54(1) OF THE LAND ACQUISITION
ACT, 1894, PRAYING TO SET ASIDE THE IMPUGNED ORDER
DATED 30.06.2018 PASSED BY THE PRL.SENIOR CIVIL JUDGE
AND JMFC, MADHUGIRI IN L.A.C.NO.1/2014 AND
CONSEQUENTLY REMAND THE MATTER TO TRIAL COURT FOR
FRESH ADJUDICATION.
THIS APPEAL HAVING BEEN HEARD AND RESERVED FOR
JUDGMENT ON 05.06.2025 AND COMING ON FOR
PRONOUNCEMENT OF JUDGMENT THIS DAY, ANU SIVARAMAN
J., PRONOUNCED THE FOLLOWING:
CORAM: HON'BLE MRS. JUSTICE ANU SIVARAMAN
and
HON'BLE DR. JUSTICE K.MANMADHA RAO
CAV JUDGMENT
(PER: HON'BLE MRS. JUSTICE ANU SIVARAMAN)
This MFA is filed by the petitioners/appellants under
Section 54(1) of the Land Acquisition Act, 1894 ('LA Act' for
short) aggrieved by the order dated 30.06.2018 passed in
LAC No.1/2014 by the Principal Senior Civil Judge and JMFC,
Madhugiri ('Reference Court' for short).
-
2. We have heard Shri. G.S. Venkat Subbarao,
learned counsel appearing for the appellants and Shri.
G.S.Arun, learned Additional Government Advocate
appearing for the respondent.
3. Appellants No.1, 2 and 3 are the absolute owners
of property bearing Sy.No.11/1 measuring 2 acres 6 guntas
situated at Pujarahalli Village, Kasaba Hobli, Madhugiri
Taluk. The said land was acquired by respondent by
awarding a compensation of Rs.1,71,743/-.
4. The appellants, not being aware of the legal
remedies available to them to seek enhancement of
compensation did not obtain any legal assistance nor did
they approach any authorities for seeking enhancement.
However, the award amount was received on 03.07.2013,
after which they approached the competent Court by filing
an application under Section 18 of the LA Act and also filed
an application under Section 5 of the Indian Limitation Act,
1963 ('Limitation Act' for short) for condoning the delay of
107 days in filing the above application.
-
5. The Reference Court dismissed the application
holding that the petitioner had failed to make an application
within 90 days from the date of service of notice of Award
and no reasons were made out in the interim application to
prove that the delay caused was unintentional. It was held
that before receiving the amount on 03.07.2013, the
petitioners were duly served with three notices, which were
also acknowledged by them.
6. It is contended by the learned counsel appearing
for the appellants that the Reference Court has allowed the
respondent to cross-examine the witness, PW.1 even when
the respondent has not filed any objections to the
application filed, seeking condonation of delay. It is further
contended that since there was no objection raised nor any
material produced to show that the notices under Section 12
of the LA Act had been served on the appellants/petitioners,
the Reference Court erred in rejecting the application. It is
contended that the appellants are illiterate land losers and
that the order is liable to be set aside and the matter is to
be remanded to the Reference Court to consider whether the
-
notices under Section 12 of the LA Act had actually been
served on the appellants and whether the application is
actually belated.
7. The learned Additional Government Advocate
appearing for the respondent, on the other hand, contends
that the language of Section 18(2) of the LA Act is perfectly
clear. The Reference Court could not have entertained an
application which was filed beyond 90 days from the date of
the award or the date on which the land loser was informed
about the passing of the award, whichever is later. It is
submitted that in the instant case, the land losers admitted
case was that the award amount was received on
03.07.2013 and that the application under Section 18 of the
LA Act was preferred belatedly after 107 days from the
expiry of the period of 90 days. It is submitted that an
application under Section 5 of the Limitation Act per se was
not maintainable in the light of the provisions of Section
18(2) of the LA Act. After admitting that the application was
belated, the appellants cannot be heard to contend that the
respondent had not raised the question of limitation.
-
8. We have considered the contentions advanced.
Section 18 of the LA Act as amended and applicable in
Karnataka specifically provides as follows:
"18. Reference to Court.-(1) Any person interested who has not accepted the award [or amendment thereof] may, by written application to the [Deputy Commissioner], require that the matter be referred by the [Deputy Commissioner] for the determination of the Court, whether his objection be to the measurement of the land, the amount of the compensation, the persons to whom it is payable, or the apportionment of the compensation among the persons interested.
(2) The application shall state the grounds on which objection to the award [or the amendment] is taken:
[Provided that every such application shall be made within ninety days from the date of service of the notice from the Deputy Commissioner under sub-section (2) of Section 12.]
[(3)(a) The Deputy Commissioner shall within ninety days from the date of receipt of an application under sub- section (1) make a reference to the Court.
(b) If the Deputy Commissioner does not make a reference to the Court within a period of ninety days from the date of receipt of the application, the applicant may apply to the Court to direct the Deputy Commissioner to make the reference, and the Court may direct the Deputy
-
Commissioner to make the reference within such time as the Court may fix.]"
9. It is therefore clear that an application under
Section 18 of the LA Act for a reference has to be made
within a period of 90 days from the date of the award or
from the date of receipt of notice of the award. In the
instant case, it appears that the petitioners themselves had
pleaded that three notices had been issued to them. It was
also the specific pleading in the petition filed under Section 5
of the Limitation Act preferred before the Reference Court
that the award amount was paid on 03.07.2013 and that the
application under Section 18 of the LA Act is being filed
belatedly.
10. The Apex Court has clearly held that the time
limit provided under Section 18(2) of the LA Act is
mandatory in nature and no application can be preferred
beyond the period as provided in the Statute.
(i) In the case of Officer on Special Duty (Land
Acquisition) and another v. Shah Manilal Chandulal
and others reported in (1996) 9 SCC 414, the Apex Court
-
has clearly held that, if the application for reference is not
made within time, the Collector will not have the power to
make the reference. Further, if the reference is wrongly
made by the Collector, the Court will have to determine the
validity of the reference.
(ii) In the case of Bhagwan Das and others v.
State of Uttar Pradesh and others reported in (2010) 3
SCC 545, the Apex Court has held that in paragraph No.31,
which reads as follows:-
"31. Actual or constructive knowledge of the contents of the award can be established by the Collector by proving that the person interested had received or drawn the compensation amount for the acquired land, or had attested the mahazar/panchanama/proceedings delivering possession of the acquired land in pursuance of the acquisition, or had filed a case challenging the award or had acknowledged the making of the award in any document or in statement on oath or evidence. The person interested, not being in possession of the acquired land and the name of the State or its transferee being entered in the revenue municipal records coupled with delay, can also lead to an inference of constructive knowledge. In the absence of any such evidence by the Collector, the claim of the person interested that he did not have knowledge earlier will be accepted, unless there are compelling circumstances not to do so."
-
(iii) In the case of Manharlal Shivlal Panchal and
others v. Deputy Collector & Special Land Acqusition
Officer and others reported in 2022 SCC OnLine SC
1707, the Apex Court has held that in paragraph No.17,
which reads as follows:-
"17. Now so far as the reliance placed upon the decisions of this Court in the cases of Shah Manilal Chandulal (supra) and Mahadeo Bajirao Patil (supra) are concerned, there cannot be any dispute on the proposition of law laid down by this Court that the limitation for making reference under Section 18 of the Act, 1894 cannot be extended and that Section 5 of the Limitation Act shall not be applicable. However, in the present case, it is not the case of condoning the delay in exercise of powers under Section 5 of the Limitation Act. As observed hereinabove, in the present case, the appellants challenged the acquisition proceedings which ended on the dismissal of the special leave petition by this Court vide order dated 11.4.2013 and thereafter pursuant to the liberty reserved by the High Court, reserved while dismissing Writ Petition No.1428/2012, within a period of six months from the date of dismissal of the special leave petition, i.e., on 1.7.2013, the original landowners filed reference application under Section 18 of the Act, 1894. In the aforesaid two decisions before this Court, there were no such facts. Therefore, on facts, the aforesaid two decisions shall not be applicable to the facts of the case on hand."
-
11. It is also clear from a plain reading of the
provision that what is intended is that the application must
be filed within 90 days from when the land loser is made
aware of the fact of the award. In the instant case,
admittedly, the award amount has been disbursed on
03.07.2013. In the affidavit filed in support of the
application to condone the delay in preferring LAC
No.1/2014, the claimants state that they have received the
compensation under protest and are not satisfied with the
compensation awarded. They state that they had requested
the Land Acquisition Officer to send the records for higher
compensation to the Civil Court but have not received any
intimation and hence have filed the application for
enhancement of compensation. Since it is an admitted fact
that the appellants had clear knowledge of passing of the
award on 03.07.2013 and since it is an admitted fact that
there was no written application made to the Deputy
Commissioner within 90 days, the LAC was filed long
thereafter, that is, in November 2014, we are of the opinion
that the contention of the learned counsel appearing for the
-
appellants that the date of issuance and the receipt of the
notice under Section 12 of the LA Act are to be proved
before the Reference Court is completely fallacious and
unsustainable.
12. Having admitted before the Reference Court that
the award amount had been received on 03.07.2013, and
having filed an application for condonation of delay, the land
losers had admitted that their application under Section 18
of the LA Act was belated.
13. In the circumstances, we are of the opinion that
there is no error committed by the Reference Court in
rejecting the application which was filed beyond time and
could not have been entertained by the Reference Court.
The appeal therefore fails and the same is accordingly
dismissed.
Sd/-
(ANU SIVARAMAN) JUDGE
Sd/-
(DR. K.MANMADHA RAO) JUDGE cp*
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!