Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

National Highways Authority Of India vs Sri K Sundar Rajan
2025 Latest Caselaw 2847 Kant

Citation : 2025 Latest Caselaw 2847 Kant
Judgement Date : 25 January, 2025

Karnataka High Court

National Highways Authority Of India vs Sri K Sundar Rajan on 25 January, 2025

Author: H.P.Sandesh
Bench: H.P.Sandesh
                            1



       IN THE HIGH COURT OF KARNATAKA AT BENGALURU

         DATED THIS THE 25TH DAY OF JANUARY, 2025

                         BEFORE

           THE HON'BLE MR. JUSTICE H.P. SANDESH

       MISCELLANEOUS FIRST APPEAL NO.3581/2024 (AA)
                           C/W
       MISCELLANEOUS FIRST APPEAL NO.3301/2024 (AA)

IN MISCELLANEOUS FIRST APPEAL NO.3581/2024:

BETWEEN:

NATIONAL HIGHWAYS AUTHORITY OF INDIA
PROJECT IMPLEMENTATION UNIT-BANGALORE
SY NO.13, 14TH KM, NAGADANDRA VILLAGE
BANGALOR - TUMKUR ROAD (NH-4)
BANGALORE - 560 073
REPRESENTED BY ITS PROJECT DIRECTOR
NHAL, PIU, BANGALORE.                        ... APPELLANT

     (BY SMT. SHILPA GHANSHYAMBHAI SHAH, ADVOCATE)

AND:

1.     SRI DAVURU VIJAY KUMAR REDDY
       SON OF GOPAL KRISHNA REDDY
       AGED MAJOR
       RESIDING AT KAMMARAMITTI VILLAGE
       MATUKUMAR MANDAL, NELLORE POST
       NELLORE DISTRICT - 524 001, A.P.

2.     THE ARBITRATOR AND
       SPECIAL DEPUTY COMMISSIONER-1
       BANGALORE URBAN DISTRICT
       (NH-75) (OLD NH-4), K.G.ROAD,
                            2



     NEAR DISTRICT REGISTRAR OFFICE
     BANGALORE - 560 009.

3.   THE ASSISTANT COMMISSIONER AND
     COMPETENT AUTHORITY
     NHAI, MULBAGILU - KOLAR
     BANGALORE SECTION OF NH- 4 (75)
     NO.678/3, NEERUBHAVI
     KEMPANNA LAYOUT, HEBBAL
     BANGALORE - 560 024
     REPRESENTED BY THE SPECIAL
     LAND ACQUISITION OFFICER.         ... RESPONDENTS

       (BY SRI VISHWANATHA M.S., ADVOCATE FOR R1;
          SRI GOPALAKRISHNA SOODI, AGA FOR R2;
               VIDE ORDER DATED 20.11.2024,
              NOTICE TO R3 - DISPENSED WITH)

     THIS M.F.A. IS FILED UNDER SECTION 37(1)(c) OF THE
ARBITRATION AND CONCILIATION ACT, AGAINST THE ORDER
DATED 21.12.2023 PASSED IN A.P.NO.22/2020 ON THE FILE OF
THE XXIV ADDITIONAL CITY CIVIL AND SESSIONS JUDGE
(CCH-6), BENGALURU, DISMISSING THE PETITION FILED
UNDER SECTION 34(2) OF ARBITRATION AND CONCILIATION
ACT, 1996 AND ETC.

IN MISCELLANEOUS FIRST APPEAL NO.3301/2024:

BETWEEN:

NATIONAL HIGHWAYS AUTHORITY OF INDIA
PROJECT IMPLEMENTATION UNIT-BANGALORE
SY.NO.13, 14TH KM., NAGASANDRA,
BANGALORE-TUMKUR ROAD (NH-4)
BANGALORE - 560 073
REPRESENTED BY ITS PROJECT DIRECTOR
NHAL, PIU, BANGALORE.                       ... APPELLANT

     (BY SMT. SHILPA GHANSHYAMBHAI SHAH, ADVOCATE)
                              3



AND:

1.     SRI. K. SUNDAR RAJAN
       SON OF LATE N. KRISHNAN
       AGED MAJOR
       RESIDING AT K. PHARMA
       AVALAHALLI, VIROGNAGAR POST
       BANGALORE-560049.

2.     THE ARBITRATOR AND
       SPECIAL DEPUTY COMMISSIONER-1
       BANGALORE URBAN DISTRICT,
       (NH-75), (OLD NH-4) K.G.ROAD,
       NEAR DISTRICT REGISTRAR OFFICE
       BANGALORE - 560 009.

3.     THE ASSISTANT COMMISSIONER
       AND COMPETENT AUTHORITY
       NHAI, MULBAGILU-KOLAR
       BANGALORE SECTION OF NH-4 (75)
       NO.678-3, NEERUBHAVI
       KEMPANNA LAYOUT, HEBBAL,
       BANGALORE - 560 024.
       REPRESENTED BY THE SPECIAL LAND
       ACQUISITION OFFICER.                ... RESPONDENTS

        (BY SRI VISHWANATHA M.S., ADVOCATE FOR R1;
           SRI GOPALAKRISHNA SOODI, AGA FOR R2)

       THIS M.F.A. IS FILED UNDER SECTION 37(1)(c) OF THE
ARBITRATION AND CONCILIATION ACT, AGAINST THE ORDER
DATED 21.12.2023 PASSED IN AP.NO.16/2020 THE FILE OF THE
XXIV    ADDITIONAL   CITY   CIVIL   AND   SESSIONS   JUDGE,
BENGALURU CCH-6, DISMISSING THE ARBITRATION PETITION
FILED UNDER SECTION 34(2) OF THE ARBITRATION AND
CONCILIATION ACT, 1996 AND ETC.
                                     4




      THESE APPEALS HAVING BEEN HEARD AND RESERVED
FOR   JUDGMENT        ON     17.01.2025   THIS    DAY,   THE    COURT
PRONOUNCED THE FOLLOWING:


CORAM:     HON'BLE MR. JUSTICE H.P.SANDESH


                             CAV JUDGMENT

These two Miscellaneous First Appeals are filed under

Section 37(1)(c) of the Arbitration and Conciliation Act, 1996

challenging the judgment dated 21.12.2023 passed in Arbitration

Petition Nos.22/2020 and 16/2020 respectively by the XXIV

Additional City Civil and Sessions Judge, Bengaluru as well as

challenging the Arbitral award dated 06.01.2020 in Case

No.LAQ/ARB/NH-4(BET)/104/2010-11 and case No. LAQ/ARB/

NH-4(BET)/74/2010-11 respectively passed by respondent No.2.

2. Heard the learned counsel appearing for the

respective parties.

3. The factual matrix of the case in MFA No.3301/2024

is that the preliminary notification under Section 3A of the

National Highways Act 1956 (for short 'NH Act') was published

by the Central Government declaring its intention to acquire

various lands in Bandapura village, K.R.Puram Taluk, Bengaluru

Urban District among other villages for the purpose of widening /

6 lane of National Highway No.4(NH4) and the final notification

was issued under Section 3D(1) and (2) of the NH Act declaring

that amongst others, the agricultural lands in Sy.No.28/2 to an

extent of 154 square meters situated at Bandapura village,

K.R.Puram Taluk, Bangalore Urban District belonging to

respondent No.1 shall vest absolutely with the Central

Government and respondent No.3 passed an award fixing the

market value of agricultural land at Rs.420.07/- per square

meter.

4. In MFA No.3581/2024 also proceedings were

initiated under Section 3A of the NH Act in respect of the very

same village and also final notification was issued in respect of

Sy.No.40 to an extent of 550 square meters situated in the same

village belonging to respondent No.1 shall vest absolutely with

the Central Government. Being aggrieved by the market value

determined by respondent No.3, respective respondent No.1

preferred an application before respondent No.2 under Section

3G(5) of the NH Act seeking for enhancement of compensation

in respect of Sy.Nos.28/2 and 40.

5. Respondent No.2 vide its order dated 06.01.2020

passed the award enhancing the compensation in both the

claims from Rs.420.07 per square meter to Rs.1,483/- per

square meter. Being aggrieved by the said order, the appellant

herein preferred A.P.Nos.16/2020 and 22/2020 under Section

34(2) of the Arbitration and Conciliation Act, 1996 (for short 'the

Act of 1996') before the XXIV Additional City Civil and Sessions

Judge, Bengaluru seeking to set aside the Arbitral award dated

06.01.2020 passed by respondent No.2 and both the petitions

were dismissed and being aggrieved by the said order, the

present miscellaneous first appeals are filed before this Court.

6. The issues involved between the parties are one and

the same and hence, these appeals are taken up together for

common consideration.

7. The learned counsel for the appellant in both the

appeals would vehemently contend that there is no dispute with

regard to issuance of preliminary notification and final

notification and also contend that SLO fixed the rate at

Rs.420.07 per square meter. It is contended that the land is an

agricultural land situated in Bandapura village and SLO passed

the award based on the sale statistics but the Arbitrator passed

the order enhancing the same determining the compensation at

Rs.1,483/- per square meter. The counsel in his arguments

would vehemently contend that the impugned orders of the

Arbitrator as well as the Civil Court are erroneous. The appellant

had specifically contend that arbitral award was not in

accordance with the substantive law i.e., Section 3G(7)(a) of the

NH Act which provides that the market value of the acquired

land has to be determined as on the date of publication of

preliminary notification. The appellant had urged that the

Arbitrator had relied upon a guidance value notification which

had come into effect subsequent to the issuance of the

preliminary notification and the same is patently illegal, perverse

as it is violative of Section 3G(7) of the NH Act. The Civil Court

has made an inherent finding that the appellant herein has not

established that the Arbitrator was under an obligation to

conduct enquiry. The petitioner had contended before the Civil

Court that Section 24 of the Act of 1996 specifically speaks

about hearing and the manner in which the Arbitral Tribunal is

required to conduct hearing.

8. The counsel also would vehemently contend that the

Arbitrator had considered the rates for the period 2007-08 and

found that there was no amount fixed during that period. The

Civil Court has comes to the conclusion that based on this

observation of the Arbitrator, sufficient enquiry had been

conducted. The said finding is an erroneous finding. The

counsel also would vehemently contend that there was no rates

fixed for the year 2007-08 and the same is still an incorrect

finding. It is contend that the preliminary notification was issued

on 18.12.2006 and therefore, the Arbitrator ought not to have

relied upon the notification of the year 2007. The Arbitrator

relied on the guidance notification dated 17.04.2007 and

therefore, it cannot be said that there is a violation of Section

28(1)(a). The same is an erroneous finding and the Court has

once again overlooked that the market value is required to be

determined as on the date of preliminary notification i.e.,

18.12.2006. The Civil Court also committed an error in

erroneously discussing in page Nos.16 to 18 and failed to

consider the judgments which have been quoted before the Trial

Court and the similar judgments are quoted before this Court.

The appellant herein was never given an opportunity to rebut the

document which has been relied upon by the Arbitrator and the

said document was not produced by either of the parties and the

Arbitrator relied upon that document while passing the arbitral

award suo moto and hence, the impugned Arbitral award is

contrary to the provision of Section 24(3) of the Act of 1996.

9. The counsel also relied upon the case of Ssangyong

and contend that non-disclosure of a document relied upon by

the Arbitral Tribunal would affect the case of the parties since

they would be unable to present their case and would amount to

denial of an opportunity to comment upon the documents relied

upon by the Tribunal and shockingly relied upon the guidance

notification and committed an error. The counsel also would

vehemently contend that inspite of citations referred, the same

have not been considered.

10. The counsel in support of his arguments relied upon

the judgment reported in AIR 2003 SC 2629 in the case of OIL

& NATURAL GAS CORPORATION LTD., vs SAW PIPES LTD.,

and brought to notice of this Court the discussions made in

paragraph 12 wherein question was raised whether the award

could be set aside, if the arbitral tribunal has not followed the

mandatory procedure prescribed under Sections 24, 28 or 31(3),

which affects the rights of the parties. The counsel also brought

to notice of this Court paragraph 21 wherein it is held that if the

award is patently against the statutory provisions of substantive

law which is force in India or is passed without giving an

opportunity of hearing to the parties as provided under Section

24 or without giving any reason in a case where parties have not

agreed that no reasons are to be recorded, it would be against

the statutory provisions. In all such cases, the award is required

to be set aside on the ground of patent illegality. The counsel

referring this judgment would vehemently contend that the

arbitral award obtained is patent illegality and without giving an

opportunity, relied upon the notification.

11. The counsel also relied upon the judgment reported

in (2009) 10 SCC 259 in the case of SOM DATT BUILDERS

LTD., vs STATE OF KERALA and brought to notice of this Court

the discussions made in paragraph 21 that Section 31(3)

mandates that the arbitral award shall state the reasons upon

which it is based, unless the parties have agreed that no reasons

are to be given or the award is an arbitral award under Section

30. It was obligatory for the arbitral tribunal to state reasons in

support of its award in respect of claim and now it is essential for

the arbitral tribunal to give reasons in support of the award. The

counsel also brought to notice of this Court the paragraph 25 of

the said judgment wherein it is held that requirement of reasons

in support of the award under Section 31(3) is not an empty

formality. It guarantees fair and legitimate consideration of the

controversy by the arbitral tribunal. The reasons must be stated

by the arbitral tribunal upon which the award is based.

12. The counsel also relied upon the judgment reported

in MANU/SC/0705/2019 in the case of SSANGYONG

ENGINEERING & CONSTRUCTION CO. LTD., vs NATIONAL

HIGHWAYS AUTHORITY OF INDIA (NHAI) and brought to

notice of this Court paragraph 45 of the said judgment wherein it

is held that there can be no doubt that the government

guidelines that were referred to and strongly relied upon by the

majority award to arrive at the linking factor were never in

evidence before the Tribunal. In fact, the Tribunal relies upon

the said guidelines by itself and states that they are to be found

on a certain website. If either of the parties not relied upon

such guidelines, the Tribunal had no jurisdiction to rely upon the

same while deciding the issue before it. The counsel also would

vehemently contend that in paragraph 46 of the said judgment it

is held that majority award needs to be set aside under Section

34(2)(a)(iii). The counsel also would vehemently contend that

the Arbitrator as well as the Trial Court committed an error in

relying upon the notification and erroneously comes to the

conclusion that no error has been committed.

13. Per contra, the learned counsel appearing for

respondent No.2 in his arguments would vehemently contend

that the property was acquired for road widening of Mulabagil -

Kolar road which is adjacent to the Highway. The Arbitrator has

taken note of the said fact into consideration and potentiality of

the property was also considered. The Civil Court in paragraph

12, in detail discussed and taken note of 30% of guidance value

and reasons were given while dismissing the petitions and

hence, it does not requires any interference. The counsel also

would vehemently contend that the SLO fixed the rate at

Rs.420.07 per square meter is only a peanut and when the

property comes within the purview of K.R.Puram Taluk which is

adjacent to the Bengaluru city and the same is a developed area,

the Arbitrator rightly taken the guidance notification and passed

an award and hence, it does not requires any interference.

14. The learned counsel for respondent No.1 would

vehemently contend that award passed by the Arbitrator is

based on the material available on record as well as the

guidance notification and the amount awarded by the SLO is

very meager and guideline was taken while enhancing the same

and even the enhancement made by the Arbitrator is very less

having taken note of the potentiality of the property and hence,

it does not requires any interference.

15. Having heard the learned counsel appearing for the

respective parties and also on perusal of the material available

on record as well as considering the principles laid down in the

judgments referred supra, the points that would arise for the

consideration of this Court are:

1. Whether the award passed by the Arbitrator and also the

judgment passed by the Civil Court invoking Section 34 of

the Act of 1996 requires interference?

2. What order?

Point No.1:

16. Having heard the learned counsel appearing for the

respective parties and also on perusal of the material available

on record, it discloses that it is not in dispute that lands to the

tune of 550 square meters and 154 square meters were acquired

by the National Highway Authority. It is also not in dispute that

the land is acquired for the purpose of widening of the road of

Mulabagil - Kolar road. It is also not in dispute that the

properties are situated in K.R.Puram taluk and the same is

abutting to the Bengaluru City. It is also important to note that

the main contention of the appellant that substantive law has not

been considered by both the Arbitrator as well as Civil Court. The

Arbitrator relied upon the document of guideline notification on

his own and the same has not been produced by either of the

parties and hence, it is against Sections 24 and 28 of substantive

law and the document which has been relied upon is not part of

record and even not notified to the parties and communicated

and hence, the counsel would vehemently contend that in view

of the principles laid down, it requires to be set aside and needs

to be set aside based on the relevant discussions made by the

Apex Court in the judgments referred supra.

17. It has to be noted that the SLO has fixed the rate at

Rs.420.07 per square meter. It is also not in dispute that the

properties are an agricultural land situated at Bandapura village

and the Arbitrator while passing an award taken note of extent

of land which was acquired for the purpose of widening the road.

It is also important to note that the Arbitrator also taken note of

the fact that the land was acquired in the year 2006 by way of

preliminary notification and final notification was issued in the

year 2007. The arbitrator also taken note of Section 3G(5) of

the NH Act and also taken note of Section 28 of the Act of 1996

wherein it discloses that Arbitral Tribunal shall decide the dispute

in accordance with substantive law for time being in force in

India and also discussed the same in the award itself that

competent authority or the arbitrator while determining the

amount under sub-section (1) or sub-section (5), as the case

may be, shall take into consideration the market value of the

land on the date of publication of the notification under Section

3A. The Arbitrator also had taken note of the fact that the land

which was acquired is an agricultural and non-agricultural land

wherein rate is fixed at Rs.420.07 per square meter and in

respect of NAK/Site, an amount of Rs.1.506.90 per square

meter. It is also important to note that the arbitrator also taken

note of the notification dated 17.04.2007 and the same is of the

year 2007-08, the amount of Rs.60,00,000/- has been fixed per

acre in terms of the said notification. But in respect of 2007-08,

rate was not fixed and in terms of the notification, if the property

comes within the purview of CMC and the converted land and

also if it is within the gramatana, 30% has to be added. The

Arbitrator relied upon the notification dated 17.04.2007

guidelines value for 2007-08 and an amount of Rs.60,00,000/- is

fixed and if it is converted into gunta it comes to Rs.1,50,000/-

hence, taken Rs.1,483/- per square meter and hence after

deducting the SLO amount fixed, taken Rs.1,063/- per square

meter and passed an order. The appellant not disputes the fact

that issuance of said notification but only contend that same was

not part of the record and admittedly the said guidelines

notification was issued by the Government.

18. It is also important to note that the Civil Court also

taken note of the fact that preliminary notification is dated

14.12.2006 i.e., it is in the verge of end of December 2006 and

final notification is dated 14.11.2007 and taking note of gap of

11 months, considered the loss for the said period, the

compensation is enhanced and the fact that applicant has filed

objections and the said fact also not disputed. The fact that the

land is adjacent to the National Highway and the said fact is also

not in dispute. It is worth about 1.80 crore and as on the date of

award it was worth of 6.50 crore and also taken note of the

enhancement sought at the rate of Rs.1,800/- per square meter

with 9% interest. Even in paragraph 12 discussed that there is

no rate fixed for the period of 2007-08 as the notification is

dated 17.04.2007, the guidance value is considered and an

increase of 30% of the value also taken note of.

19. The main contention of the appellant's counsel that

substantive law has not been considered and at the same time,

the Court has to take note of the fact that potentiality of the

property. The appellant's counsel also not disputed the fact that

the land which was acquired is abutting to the National Highway

for the purpose widening of the road and the Arbitrator also

given the reason that land which is abutting to the National

Highway is useful for non-agricultural purpose and the lands are

also capable of being further developed and detail discussion was

made by the Civil Court while confirming the judgment of the

Trial Court. No doubt, it is the contention of the appellant's

counsel that Section 3G(7)(a) of the NH Act is not complied and

ought to have been fixed based on the market value on the date

of publication of the notification and relies on decision in the

case of Oil and Natural Gas referred supra and also relied upon

the judgment of Kerala High Court as well as Apex Court and

brought to notice of this Court Section 24, 28, 31(3) of the Act

of 1996. No doubt, in the above judgment it is discussed that it

is not an empty formality and discussed the same in paragraphs

15 and 16 of the order. The Civil Court also taken note of the

fact that on perusal of the entire award passed by the Arbitrator

it discloses the reasons for coming to such a conclusion for

enhancement and also taken note of the fact that the Arbitrator

has taken into consideration of the fact that the property

acquired is adjacent to the National Highway and consideration

of the actual market value would be always high and rightly

awarded three times compensation. In paragraph 17 also

discussed in detail that the Arbitrator has considered the fact

that the plaintiff is a farmer and lost the agricultural land though

it was an agricultural land but it is adjacent to the National

Highway and abutting to the National Highway and hence, there

is increase of 30% in the areas within the purview of CMC and

converted sites and gramatana and all these factors taken note

of by the Trial Court and also taken note of the Government

notification and considered the case of the claimants who lost

the property.

20. The Trial Court also taken note of the fact that the

provisions of Section 23 and 28 of the Land Acquisition Act

wherein the land looser is entitled to solatium and interest and

also taken note of the fact that in the similar matter, the

enhanced compensation is deposited based on the same

guidance value but has proceeded to challenge the same with

respect to these properties are concerned. The Trial Court also

taken note of the judgment reported in AIR 2019 SC 4689

wherein the Apex Court has held that the provisions of Land

Acquisition Act relating to solatium and interest are applicable to

the National Highways Act also and while confirming the order

also reasoned order has been passed. When such reason has

been assigned by the Trial Court and Arbitrator also taken note

of the factual aspects that the land is abutting to the National

Highway and also having taken its potentiality and also located

in K.R.Puram taluk which is abutting to Bengaluru, I do not find

any error committed by the Arbitrator as well as the Civil Court

and in both the matters, considered the material available on

record and also though the notification was not the part of the

record as contended by the appellant's counsel, the guidance

value is fixed by the Government itself by issuing the

notification. I have already pointed out that preliminary

notification was in the verge of end of the year 2006 and final

notification was passed on 14.11.2007 and guidance notification

was issued within a span of three months of preliminary

notification that is in the month of April 2007 i.e., in between

preliminary notification and final notification in the case on hand

and when the Arbitrator relied upon the said notification and

taken note of the potentiality of the property and land is abutting

to the National Highway, it cannot be termed as arbitrarily and

not followed the substantive law and the same is contrary to

Sections 24, 28, 31(3) of the Act of 1996 cannot be accepted

since the acquisition of land is for purpose of widening the road

to a small extent i.e., to the extent of 550 square meter and 154

square meter. Hence, I do not find any merit in the appeals to

accept the contention of the appellant's counsel and it does not

requires any interference when reason was given while

enhancing and confirming the order of the Arbitrator by the Civil

Court. Accordingly, I answer the above point as negative.

Point No.2:

21. In view of the discussions made above, I pass the

following:

ORDER

The Miscellaneous First Appeals are dismissed.

Sd/-

(H.P. SANDESH) JUDGE

SN

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter