Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sri G R Jagadeesh vs Sri B S Chandrashekaraiah
2024 Latest Caselaw 27557 Kant

Citation : 2024 Latest Caselaw 27557 Kant
Judgement Date : 19 November, 2024

Karnataka High Court

Sri G R Jagadeesh vs Sri B S Chandrashekaraiah on 19 November, 2024

Author: K.Natarajan

Bench: K.Natarajan

                              1




    IN THE HIGH COURT OF KARNATAKA AT BENGALURU

       DATED THIS THE 19TH DAY OF NOVEMBER, 2024

                          BEFORE

         THE HON'BLE MR. JUSTICE K. NATARAJAN

           REGULAR FIRST APPEAL NO.14 OF 2014

BETWEEN:

1 . SRI. G. R. JAGADEESH
    S/O LATE G.S.RACHAPPA,
    AGED ABOUT 61 YEARS,

2 . J. SHRUTHI
    D/O SRI. G.R.JAGADEESH,
    AGED ABOUT 29 YEARS,

3 . J. DEEPTHI
    D/O SRI. G.R.JAGADEESH,
    AGED ABOUT 25 YEARS,

    ALL ARE R/AT NO.2158,
    8TH 'A' MAIN, 'B' BLOCK,
    WARD OFFICE ROAD, 2ND STAGE,
    RAJAJINAGAR, BANGALORE - 560 010.
                                                ...APPELLANTS
(BY SRI. NATARAJA H T., ADVOCATE)

AND:

   SRI. B. S. CHANDRASHEKARAIAH
   S/O LATE SIDDALINGARADHYA,
   AGED ABOUT 58 YEARS,
   R/AT MALLESHWARA NAGARA,
   ARSIKERE TOWN.
                                                ...RESPONDENT
(BY SRI. HARISH KUMAR M C., ADVOCATE FOR C/R)

     THIS REGULAR FIRST APPEAL IS FILED UNDER SEC.96(1) OF
CPC., AGAINST THE JUDGMENT AND DECREE DATED 7.10.2013
PASSED IN O.S.NO.11/2010 ON THE FILE OF THE SENIOR CIVIL
JUDGE & JMFC., ARASIKERE, PARTLY DECREEING THE SUIT FOR
DECLARATION, REFUND OF ADVANCE AMOUNT.
                                        2




     THIS REGULAR FIRST APPEAL HAVING BEEN HEARD AND
RESERVED FOR JUDGMENT ON 21.10.2024 THIS DAY, THE COURT
PRONOUNCED THE FOLLOWING:


 RESERVED FOR ORDERS ON: 21.10.2024
 PRONOUNCED ON          : 19.11.2024




CORAM: HON'BLE MR JUSTICE K.NATARAJAN

                              CAV JUDGMENT

This appeal is filed by the appellants-defendants under

Section 96 of CPC for setting aside the judgment and decree passed

by the Senior Civil Judge and JMFC, Arsikere (hereinafter referred

to as 'trial Court') in O.S. No.11/2010 dated 07.10.2013.

2. Heard the arguments of learned Counsel for the appellants

and learned counsel for the respondent.

3. The appellants were the defendants and the respondent

was the plaintiff before the trial Court. The rank of the parties is

retained for the sake of convenience.

4. The case of the plaintiff before the trial Court is that the

plaintiff filed the aforesaid suit for declaration that the agreement of

sale executed by the defendants dated 13.09.2010 in favour of the

plaintiff is unenforceable on account of fraud and misrepresentation

played by the defendants and to decree the suit for refund of the

advance amount of Rs.10,51,950/- with interest at 24% p.a. and

with cost.

5. The further case of the plaintiff is that the defendants told

the plaintiff that they are the owners and are in possession of suit

schedule sites which were situated 40 meters away from the middle

of the National Highway No.206 at Arsikere town and approached

the plaintiff for selling the same. Accordingly, the plaintiff agreed

to purchase the same for the sale consideration of Rs.37 lakhs and

the defendants received the advance amount of Rs.5.00 lakhs by

way of cash on 13.09.2010 and executed the agreement of sale. As

per the terms of the agreement, they agreed to receive Rs.32.00

lakhs at the time of registration. The defendants also agreed that if

any complication arises, they would be responsible to resolve the

complication and agreed to hand over all the documents to the

plaintiff. The defendants also started insisting the plaintiff to pay

the entire sale consideration within 15 days of the agreement. As

such, the plaintiff paid another sum of Rs.5.00 lakhs to the

defendants on 29.09.2010 by cash. A shara was also written on the

agreement of sale in the presence of the witnesses. The

defendants insisted for the full payment. There was some doubt in

the mind of the plaintiff and approached the government officials of

National Highway Authority and he came to know that the suit

schedule property is situated within 40 meters away from the

middle of National Highway No.206. The defendants pressurised

the plaintiff to pay the entire sale consideration and the plaintiff

took one retired surveyor and verified the property and he came to

know that the sites shown by the defendants prior to the agreement

of sale were totally different from the sites mentioned in the

agreement of sale. The sites agreed to be sold by the defendants

were situated within 40 meters from the middle of the National

Highway and therefore, the agreement is unenforceable. The

defendants misappropriated the plaintiff and committed fraud on

him. Hence, filed the suit after issuing legal notice to the

defendants.

6. In pursuance of summons, defendant Nos.1 to 3 appeared

and the written statement filed by defendant No.1 was adopted by

the other defendants. It was contended that the suit was not

maintainable and it was frivolous. It was contended that the

defendants were the owners of the property and they admit the

agreement of sale, receipt of Rs.10,00 lakhs i.e. Rs.5.00 lakhs on

13.09.2010 and another Rs.5.00 lakhs on 29.09.2010 and they

were ready to execute the sale deed. The defendants denied the

fact that they pressurised the plaintiff for further advance and

further denied that the suit property is situated within 40 meters

width from the middle of the National Highway No.206.

7. The defendants specifically contended that the plaintiff was

well aware about the alleged National Highway at the time of

inspection of sites and signing the agreement. Therefore,

conducting the survey through a retired surveyor does not arise.

The plaintiff had taken all precautionary measure before signing the

agreement as per the principle caveat emptor or buyer beware. It

is submitted that the office of the Executive Engineer, National

Highway Division had issued NOC to Smt. Manjula, wife of Sri G.C.

Anandappa and one Parvathamma, wife of Sri Gangadharappa,

whose sites were situated on National Highway No.206 and adjacent

to the sites in question belonging to the defendants for the purpose

of getting sanction plan for putting up the commercial buildings and

the said buildings were completed. The NOC given by the concerned

authorities clearly shows that the property in question is situated

beyond the distance stipulated in the alleged circular. Therefore,

the defendants are not liable to pay the advance amount to the

plaintiff.

8. It is further contended that though the time is stipulated

for completion of transaction for 3 months from the date of

agreement from 13.9.2010 the plaintiff fixed the date of registration

as 25.10.2010 he had got two separate sale deeds already in

respect of separate sites, had obtained demand drafts payable to

the defendants and also towards the registration expenses.

However, the plaintiff made unreasonable demand to reduce the

price by Rs.10 lakhs which was not acceptable by the defendants.

The plaintiff had got issued legal notice on 19.11.2010 which was

suitably replied by the defendant. There is no cause of action to file

the suit. Hence, prayed for dismissing the suit.

9. Based upon the pleadings the trial court framed 3 issues

as under:-

"1) Whether the plaintiff proves that for the reasons stated in the plaint paras, the agreement of sale dated: 13.9.2010, entered into between him and the defendants, in respect of suit schedule properties, is to be cancelled?

2) Whether plaintiff is entitled to get refund of earnest sum of Rs. 10,00,000/- with interest at 24% p.a. from the defendants, which was paid by him to the defendants, towards part payment of the sale consideration?

3) What decree or order?"

10. In order to prove the contention, the plaintiff examined

as PW1 and also examined 3 witnesses as PW.2 to PW.4 and got

marked 11 documents as per Ex.P1 to P11 and the defendant No.1

himself examined as DW1 he also examined DW.2 and DW.3 and

got marked 6 documents. After hearing the arguments, the trial

court answered the issue No.1 in the affirmative, issue No.2 partly

in the affirmative and decreed the suit directing the defendant to

refund the advance amount of Rs.10 lakhs with 9% interest from

the date of agreement, till realisation. Being aggrieved by the

judgment and decree, the defendants filed this appeal before this

court.

11. Learned counsel for the appellants has strenuously

contended that the plaintiff agreed to sell the schedule property

after verifying the place, the sale shall be complied within 3 months

and the evidence of the defendants was not properly appreciated by

them. There are building and other houses which were constructed

adjacent to the suit schedule property. The authorities have given

permission to construct the house and it does not come within the

40 meters in the middle of the high way, the other houses are

situated. Therefore, the agreement is enforceable but the plaintiff

failed to perform his duty under the contract. The appellant got

issued the legal notice by forfeiting the earnest money. However,

the said documents is not produced.

12. He also contended one Parvathamma obtained the

permission and put up construction of building within 22 meters

from the middle of the highway. Though there was prohibition to

put up construction within 40 meters from the middle of the

Highway, but there are many constructions came up in that area.

Therefore, the agreement is enforceable and the plaintiff was

unable to arrange the fund and avoided the payment of balance sale

consideration. Even though the appellant was ready to execute the

sale deed. Hence, prayed for allowing the appeal.

13. The respondent counsel supported the judgment of the

trial court and contended that the agreement itself is unenforceable

where the defendant trying to sell the property which is situated

within 40 meters from the National Highway NH-206. There is

prohibition for constructing any building by the defendant, hurriedly

pressurising the plaintiff for executing the sale deed and received

Rs.10 lakh as advance amount. Therefore, the plaintiff issued the

legal notice and thereafter filed the suit. The trial court rightly

decreed the suit after appreciating the evidence on record. If at all

some persons constructed the building within the prohibitory area,

the plaintiff cannot take risk for purchasing the same. Therefore,

there is nothing to interfere in the judgment. Hence, prayed for

dismissing the appeal.

14. The learned counsel for the appellants also filed I.A.

No.2/2014 under Order XLI Rule 27(1)(b) of CPC seeking

permission of this Court to produce document i.e. legal notice

issued by the appellants-defendant to the respondent-plaintiff on

16.12.2010 where the same was served on the respondent-plaintiff

both RPAD as well as UCP. If these documents were produced

before the court, the trial Court ought to have passed the judgment

by dismissing the suit and there will not be any order for refund of

the earnest money. The trial Court also stated that though the

defendants taken contention regarding forfeiting the earnest

money, but they have not produced the documents. Therefore, the

said document is necessary for the appellant-defendants to produce

before the Court to support their case. Hence, prayed for allowing

the application.

15. Learned counsel for the respondent-plaintiff has

contended that even if the said document is considered, it will not

help to the defendants as the defendants have already given reply

and they have not forfeited the amount. Therefore, prayed for

dismissing the I.A.

16. Having heard the arguments, perused the records, the

points that arise for my consideration is:

1. Whether, the plaintiff proves that agreement of sale entered into between plaintiff and the defendant is unenforceable and is liable to be cancelled?

2. Whether the plaintiff is entitled for refund of earnest money?

3. Whether the appellants-defendant made out a case for production of documents under Order XLI Rule 27(1)(b) of CPC ?

4. Whether the judgment and decree passed by the trial court calls for any interference?

17. Having heard the arguments, perused the records and on

perusal of the same, the case of the plaintiff is that he had entered

into an agreement of sale with the defendant on 13.9.2010 and paid

Rs.5 lakhs on the date of agreement and another Rs.5 lakhs

subsequently on 29.9.2010. The sale consideration was Rs.37 lakhs

and it is contended that after verifying the property, he came to

know that the properties is within 40 meters from the National

Highway - 206 (NH-206). Therefore, the authority will not permit

to construct any building within prohibitory distance of 40 meters.

Therefore, by issuing the notice, he has cancelled the agreement.

The defendant had admitted the agreement of sale and the receipt

of Rs.10 lakhs as earnest money but his contention is that the

plaintiff must have been aware, prior to entering into agreement of

sale for purchasing of the property. He has taken risk to purchase

the same. But he is unable to mobilise the fund, therefore, he has

taken some contention of prohibitory area which is not correct. It is

also contended by the defendant that there are other person

constructed, the building adjacent to suit schedule property, which

falls within 22 meters of the NH-206. Such being the case, the

plaintiff failed to perform his part of contract and hence prayed for

dismissing the suit.

18. On perusal of the record, it is seen that the plaintiff

himself was examined as P.W.1 and he has reiterated, in his

examination in chief, the averments made in the plaint. In the

cross examination, the plaintiff admits that the plaintiff is residing in

Arasikere and he is residing by constructing the house. He also

states that he verified the documents before purchasing the

schedule property. He further admits that there is a TVS show

room situated and a three storied building also situated near the

suit schedule property. He further says that the said building might

have been constructed 40 meters away from the road of the

National Highway. He further denies that all the buildings were

constructed after the expansion of road. Again, he denies that

about 6 months back, a four storied building was constructed

leaving the 3 feet margin within 40 feet away from the middle of

the road of the National Highway. He also admits that

subsequently, the defendants issued notice for forfeiting the earnest

money. He further denies that he had not received the notice

issued by the defendants forfeiting the agreement. However, he

admits that there is interpolation in the agreement of sale, where

the property was 40 meters away from the middle of the National

Highway.

19. Ex.P.1 is agreement of sale entered between the plaintiff

and defendants and there is no dispute in this regard. In the

agreement of sale, at paragraph 2, the last line has been added as

'the property is situated away from the prohibited area of NH 206'.

The appellant-defendants have disputed that it is the interpolation

by the plaintiff himself. However, Ex.P.2-notice is issued by the

plaintiff mentioning that the property is situated within 40 meters

from the middle of the National Highway and the notice was served

on the defendants on 19.11.2010. Ex.P.3 is the reply sent by the

defendants wherein the defendants have accepted that the property

is situated within 40 meters of the middle of the National Highway.

He further admits that Rs.10.00 lakhs has been received by way of

advance and Rs.27.00 lakhs is required to be payable and calling

the plaintiff to pay the balance amount and get the sale deed

executed. Ex.P.4 is the RTC which is also not in dispute. Ex.P.5 is

the copy of alienation issued by the Assistant Commissioner of

Hassan. Ex.P.8 is the NOC issued by the Assistant Executive

Engineer of Highway Department, Hassan, where he has stated that

the said property is situated outside the prohibition area and there

is a prohibition for putting up any construction within 40 meters

from the middle of the National Highway. Ex.P.9 is also the NOC

issued by the Assistant Executive Engineer of Highway Department,

Hassan, which reveals that no construction would be allowed within

40 meters from the middle of the National Highway. Ex.P.10 is the

proceedings of the government issued by the National Highway

Authority for widening the national highway road. Ex.P.11 is the

circular issued by the State Government on 22.12.2005 stating that

no construction would be allowed within 40 meters away from the

middle of the National Highway and within 40 meters away from the

middle of the State Highway. Even no construction would be

allowed on the district main road within 25 meters away from the

middle of the road. These documents reveal that there is

prohibition for construction of any building within 40 meters away

from the middle of the National Highway.

20. The plaintiff also examined P.W.2-an independent witness

which corroborates the evidence of plaintiff regarding the

agreement of sale and the payment of advance amount. P.W.2

says that the property is situated away from NH-206 margin as per

the agreement. There is lengthy cross examination done in respect

of P.W.2 and it is brought in the evidence that there are other

buildings situated near the suit schedule property and TVS hotel

was also situated and the same is admitted by the P.W.2.

21. P.W.3- Range Gowda, the Chief Officer of the Town

Municipality, also deposes that as per the Government Circular,

there cannot be any construction of the building within 40 meters

from the middle of the National Highway. In the cross examination,

this witness denies that there are other buildings within 40 meters

and the sanction plan was given by the same authority at Ex.D.3,

but this witness says that for any building within 40 meters, an

action will be taken to remove the same. However, he has stated

that no such action has been taken.

22. P.W.4-Anantharaju, Assistant Engineer of P.W.D, also has

stated that as per the government order, there shall not be any

building permitted to be constructed within 40 meters away from

the middle of the National Highway. In the cross examination, this

witness admits that Ex.D.5-letter given by National Highway

Authority was given to one of the persons for putting up

construction where the said building is situated within 22 meters of

the National Highway.

23. On looking to the evidence of P.Ws.1 to 4, it is clear that

the suit schedule property is situated within 40 meters away from

the middle of National Highway No.206. The defendant himself

examined and also examined two witnesses contending that some

houses were constructed and a building is also constructed within

40 meters from the middle of the National Highway, and therefore,

it is contended that there is no prohibition for construction on the

suit schedule property. It is further contended that others have put

up construction near the suit schedule property, and thereby, the

defendants are willing to perform their part of contract and hence,

the earnest money was forfeited by them. The contention of the

defendants cannot be acceptable. Once the defendants admit that

the suit schedule property is situated within 40 meters away from

middle of the National Highway and there is prohibition for putting

up construction, the plaintiff is not required to purchase the

property though initially without the knowledge of the same, agreed

to purchase by paying Rs.10.00 lakhs as advance amount. But,

definitely, if any, construction is put up, in future, the National

Highway Authority will take action to remove the building and such

a risk cannot be taken by the plaintiff. Therefore, the plaintiff has

issued notice to defendants to cancel the agreement. The

contention of the defendants is that some of the buildings are

situated near the suit schedule property and permission is given by

some of the officers in the Municipality for putting up construction,

but that cannot be a ground to say that the plaintiff should take the

risk of purchasing the property which is situated within 40 meters

from the middle of the National Highway.

24. Therefore, the plaintiff though entered into the

agreement of sale with the defendants and though the defendants

have taken the contention that they have clear title over the

schedule property, but the property is situated within 40 meters

from the middle of the National Highway No.206. The Division

Bench of this Court in the case of DAYANANDA B. SHETTY Vs.

EXECUTIVE ENGINEER, NATIONAL HIGHWAY AUTHORITY

AND OTHERS in W.P.36314/2019 (LB-RES) PIL decided on

25.08.2021, has held that there shall not be any construction within

the area of 40 meters from the centre of the road being National

Highway. The Division Bench has further referred the State

Government circular regarding 'no construction zone' in respect of

the National Highway upto 40 meters from the middle of the

National Highway.

25. Therefore, even if it is purchased by the plaintiff, the

highway authorities may take action to demolish the building on the

property and therefore, the agreement is not enforceable and the

defendants have no clear title over the property. Therefore, I hold

that the plaintiff has proved that the agreement is not enforceable

and liable to be cancelled.

26. Re : Point Nos.2 and 3:

In view of the observation made by this Court, the plaintiff is

able to prove that suit schedule property is not amenable for

construction and the defendants have no clear title and the plaintiff

will put in to trouble in future, since the property is situated within

40 meters from the middle of the National Highway, As per the

evidence of P.Ws.3 and 4, in future, the National Highway Authority

will take action for demolition of construction on the schedule

property. Such being the case, after knowing the information, the

plaintiff has rightly issued the legal notice to the defendants as per

Ex.P.2.

27. The learned counsel for the appellants-defendants has

filed an I.A.No.2/14 under Order XLI Rule 27(1)(b) of CPC along

with the legal notice issued to the appellants-defendant on

16.12.2010, but the respondent-plaintiff issued the legal notice on

19.11.2010 and the appellants-defendant also issued reply notice to

the plaintiff's counsel as per Ex.P.3 on 27.11.2010 and the

defendants have undertaken to execute the sale deed and they

have never forfeited the advance amount and cancelled the

contract. But, subsequently, on 16.12.2010, the defendants issued

the notice for cancelling and forfeiting the earnest money and after

receiving the notice by the appellants-defendant, the respondent-

plaintiff filed the suit before the Court. Such being the case, even if

the document of the appellant-defendants is taken into

consideration, the legal notice dated 16.12.2010 will not help the

appellants' case. Therefore, the provisions under Order XLI Rule

27(1)(b) of CPC and the documents produced therein will not come

to the aid of the appellants. On the other hand, the agreement itself

is unenforceable and therefore, the said agreement shall be

cancelled and the appellants are entitled for the refund of the

advance amount of Rs.10.00 lakhs.

28. The trial Court after considering the evidence on record

has rightly held that the agreement is not enforceable in law and

has rightly decreed the suit. Though the learned counsel appellant-

defendants has relied upon the judgment of the Hon'ble Supreme

Court in the case of SATISH BATRA Vs. SUDHIR RAWAL in C.A.

No.7588/2012 decided on 18.10.2012, it will not come to the aid

of the appellants' case. However, the trial Court has awarded

interest at 9% p.a. on the earnest money. There is no term in the

agreement of sale for repaying the amount with interest at either

24% or 9% p.a. Such being the case, the appellants are required

to pay only 6% interest p.a. on the decretal amount instead of the

interest at 9% p.a. awarded by the trial Court from the date of filing

the suit i.e. 18.12.2010, instead of, from the date of agreement.

Therefore, the judgment and decree passed by the trial Court is

liable to be modified accordingly.

29. In the result, I pass the following order:

(i) The I.A.No.2/14 filed by the appellants under Order XLI

Rule 27(1)(b) of CPC is dismissed.

(ii) Consequently, the appeal filed by the appellant-

defendants is allowed in part.

(iii) The Trial Court has already released the amount to

respondent-plaintiff and permitted to deposit the interest at the rate

of 6% p.a. from the date of filing the suit, within two months.

      (iv)    Parties shall bear their own costs.


                                                   Sd/-
                                              (K.NATARAJAN)
                                                  JUDGE
      CS/AKV
      CT:SK
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter