Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Royal Orchid Associated Hotels Private ... vs M/S Hotel Grand Centre Point
2024 Latest Caselaw 27316 Kant

Citation : 2024 Latest Caselaw 27316 Kant
Judgement Date : 14 November, 2024

Karnataka High Court

Royal Orchid Associated Hotels Private ... vs M/S Hotel Grand Centre Point on 14 November, 2024

Author: H.P.Sandesh

Bench: H.P.Sandesh

                                              -1-
                                                         NC: 2024:KHC:46323
                                                       MFA No. 7168 of 2024




                        IN THE HIGH COURT OF KARNATAKA AT BENGALURU
                                                                              R
                          DATED THIS THE 14TH DAY OF NOVEMBER, 2024

                                            BEFORE

                             THE HON'BLE MR JUSTICE H.P.SANDESH

                    MISCELLANEOUS FIRST APPEAL NO. 7168 OF 2024 (AA)

                   BETWEEN:

                   1.    ROYAL ORCHID ASSOCIATED
                         HOTELS PRIVATE LIMITED,
                         A COMPANY INCORPORATED UNDER THE
                         PROVISIONS OF THE COMAPANIES ACT 1956,
                         HAVING ITS REGISTERED OFFICE
                         AT NO.1, GOLF AVENUE,
                         KODIHALLI, OFF AIRPORT ROAD,
                         BANGALORE-560 008,
                         REPRESENTED BY ITS
                         AUTHORISED SIGNATORY
                         MR. MAURICE REDDY.
                                                                  ...APPELLANT

                            (BY SRI. ARUN KUMAR, SENIOR COUNSEL FOR
Digitally signed
                              SRI PRADHYUMAN SINGH, ADVOCATE FOR
by DEVIKA M                          M/S. CRESTLAW PARTNERS)
Location: HIGH
COURT OF           AND:
KARNATAKA

                   1.    M/S. HOTEL GRAND CENTRE POINT,
                         A PARTNERSHIP REGISTERED UNDER
                         THE PARTNERSHIP ACT AND
                         HAVING ITS REGISTERED OFFICE
                         AT HOTEL GRAND CENTRE POINT,
                         NEAR HATRICK RESTAURANT, RAJ BAGH,
                         SRINAGAR - 190 001,
                         REPRESENTED BY ITS PARTNER.

                   2.    MOHAMMAD RAFEEQ KARNAI,
                         S/O LATE ABDUL RAHEEM ,
                         PARTNER OF M/S. HOTEL GRAND CENTRE POINT,
                         HAVING ITS REGSITERED OFFICE
                           -2-
                                      NC: 2024:KHC:46323
                                   MFA No. 7168 of 2024




     ADDRESS AT HOTEL GRAND CENTRE POINT,
     NEAR HATRICK RESTAURANT, RAJ BAGH,
     SRINAGAR-190 001.

3.   MANSOOR AHMED KARNAI,
     S/O LATE ABDUL RAHEEM,
     PARTNER OF M/S. HOTEL GRAND CENTRE POINT
     HAVING ITS REGSITERED OFFICE
     AT HOTEL GRAND CENTRE POINT,
     NEAR HATRICK RESTAURANT, RAJ BAGH,
     SRINAGAR-190 001.

4.   NAZIR AHMED KARNAI,
     S/O LATE ABDUL RAHEEM,
     PARTNER OF M/S. HOTEL GRAND CENTRE POINT
     HAVING ITS REGSITERED OFFICE
     AT HOTEL GRAND CENTRE POINT,
     NEAR HATRICK RESTAURANT, RAJ BAGH,
     SRINAGAR-190 001.

5.   BASHIR AHMED KARNAI,
     S/O LATE ABDUL RAHEEM,
     PARTNER OF M/S. HOTEL GRAND CENTRE POINT
     HAVING ITS REGSITERED OFFICE
     AT HOTEL GRAND CENTRE POINT
     NEAR HATRICK RESTAURANT, RAJ BAGH,
     SRINAGAR-190 001.
                                         ...RESPONDENTS

         (BY SMT. SHEETHAL SONI, ADVOCATE C/R2)

     THIS MFA IS FILED UNDER SECTION 37(1)(b) OF THE
ARBITRATION AND CONCILIATION ACT 1996, AGAINST THE
ORDER DATED 01.10.2024 PASSED ON IA.NOS.5 TO 7 IN
AA.NO.4/2024 ON THE FILE OF THE IX ADDITIONAL CITY CIVIL
AND SESSIONS JUDGE, BENGALURU, DISMISSING THE IA.NO.V
TO VII FILED UNDER ORDER 39 RULE 1 AND 2 R/W SECTION
151 OF CPC AND SECTION 9 OF THE ARBITRATION RULES
(PROCEEDINGS BEFORE THE COURT) 2001.

    THIS APPEAL COMING ON FOR ADMISSION THIS DAY,
JUDGMENT WAS DELIVERED THEREIN AS UNDER:
                                  -3-
                                                  NC: 2024:KHC:46323
                                               MFA No. 7168 of 2024




CORAM:     HON'BLE MR JUSTICE H.P.SANDESH

                         ORAL JUDGMENT

Heard the learned counsel for the appellant and the

learned counsel for the caveator/respondent No.2.

2. This miscellaneous first appeal is filed challenging

the order of the Trial Court dated 01.10.2024 dismissing

I.A.Nos.5 to 7 in AA No.4/2024 which have been filed under

Order 39 Rules 1 and 2 read with Section 151 of CPC and

Section 9 of the Arbitration Act read with Rule 9 of the

Arbitration (Proceedings Before the Courts) Rules, 2001.

I.A.No.5 was filed praying to grant an order of temporary

injunction restraining respondent No.2, his representatives,

successors in interest and anyone claiming under through him

from obstructing or impeding the smooth functioning and

operations of the hotel premises/schedule property in any

manner, pending disposals of the suit.

3. I.A.No.6 was also filed under the very same

provision of law seeking the relief of temporary injunction

restraining respondent No.2, his representatives, successors in

interest and anyone claiming under through him from

interfering, obstructing and/or in any manner impeding, either

NC: 2024:KHC:46323

directly or indirectly with the management and operations of the

hotel premises/schedule property in any manner, pending

disposal of the suit.

4. I.A.No.7 was also filed under the very same

provision of law seeking the relief of temporary injunction

restraining respondent No.2, his representatives, successors in

interest and anyone claiming under through him from

interfering, obstructing and/or in any manner impeding, either

directly or indirectly with the staff member and/or

guests/customers of the petitioner in the hotel premises/

schedule property in any manner, pending disposal of the suit.

5. In support of the applications, an affidavit is sworn

to contending that on 23.03.2019, a franchise agreement was

entered between the parties for operating the hotel premises on

the schedule property. It is contended that the petitioner being

one of the India's finest and fastest growing hotel chain and

being one of the most sought-after hospitality brands in the

industry, enters into hotel operation agreement with the owner

of the properties and lending them goodwill associated with the

internationally renowned "Royal Orchid" "Regenta" and "Regenta

Central" brand name amongst others. The respondent No.1 is a

NC: 2024:KHC:46323

partnership firm registered under the Partnership Act, 1932.

The respondent Nos.2 to 5 are partners of respondent No.1.

The respondent No.1 is the owner of a hotel premises located

near Hatrick Restaurant, Raj, Bagh, Srinagar, Jammu and

Kashmir "Premises" or "Schedule Property". The parties entered

into a franchisee agreement dated 23.03.2019, wherein the

petitioner would aid and facilitate the business of respondent

No.1 by contributing through its brand reputation, technical

know-how, training and expertise in running premium quality

hotel businesses. Subsequent to execution of the agreement,

the management and operations of respondent No.1 were

smoothly being carried out. However, respondent No.2 started

unnecessarily interfering in the functioning of the hotel

premises. The respondent No.2 has been shouting at staff in

the reception and threatening to cancel bookings, take away

records if he is not paid exorbitant sums separately over and

above what is agreed under the agreement. Therefore, the

operations of the hotel under the petitioner's name and guests,

is under serious jeopardy.

6. It is further contended that the interference and

disturbances being caused by respondent No.2 are in blatant

violation of the agreement. Clause 5.1 of the agreement clearly

NC: 2024:KHC:46323

stipulates that respondent No.1 Firm will maintain a high moral

and ethical standard and atmosphere at the hotel premises. The

maintenance of atmosphere at the hotel premises is an essential

and indispensable part of providing the best quality hospitality

services to the customers of the petitioner. The disturbances

being caused by respondent No.2 has a direct bearing on the

customer experience and impacts the day-to-day functioning,

business operations and prospective profits of the petitioner. As

a consequence of the conduct of respondent No.2, the petitioner

was constrained to approach this Court to seek exparte ad-

interim injunctive relief's restraining the respondent from taking

any steps to interfere with the smooth operation of the hotel

premises, interference with staff and guests in the hotel

premises or from taking any steps to terminate the agreement

and create third party rights. It is contended that agreement is

for a period of ten years and notice was also issued and reply

was also given by respondent No.2 for initiating of the prima

facie proceedings despite being well aware of the interim order

that was passed by the Court, the respondent has continued to

interfere with the smooth operations of the hotel premises. The

respondent Nos.2 and 3 have threatened the use of physical

force to coerce the petitioner, their representatives and

NC: 2024:KHC:46323

employees to remove themselves from the hotel premises. The

petitioner received an e-mail dated 26.03.2024 from the General

Manager of the hotel, documenting the grave and serious

threats being made by respondent Nos.2 and 3 to close down

the hotel. These actions of respondent No.2 are in blatant

violation of the interim order dated 17.02.2024 passed by this

Court and once again the petitioner was constrained to approach

the Court for protection and also sought for appropriate

directions against the respondents and hence I.As. are filed

seeking for the interim order of temporary injunction.

7. The respondent No.2 appeared and filed the

statement of objections contending that the suit itself is not

maintainable and petitioner is not having any locus standi. It is

contended that respondent No.2 is not a signatory to the

franchisee agreement and the suit is hopelessly barred by

limitation as their franchisee agreement on which the case is

based upon is not in existence at the time of filing this petition.

It is also contended that the case is not maintainable before this

Court for want of territorial jurisdiction as the suit schedule

property is situated in the State of Jammu and Kashmir and

though it has been mentioned in Clause 19.1 of the franchisee

agreement that the jurisdiction will be at Bengaluru, but as per

NC: 2024:KHC:46323

the settled principal of injunction, for the relief of injunction

petition must be filed before the High Court of Karnataka. It is

pertinent to note down that no franchisee agreement is above

the law. It is contended that respondent No.5 started

concealing material information of the hotel and also started

obstructing the ingress and egress of the petitioner in the hotel

with an intention to grab the shares of respondent No.2 in the

profits of the hotel. The respondent No.2 have authority to

enter profits of hotel premises and participate towards smooth

operations of hotel business as per partnership agreement dated

01.04.2012. The respondent No.5 is not allowing respondent

No.2 in the profits of the hotel and hiding the profits of hotel

business and respondent No.5 is not allowing the respondent

No.2 to inspect the books of accounts, ledgers or bills etc. or

any stock register or any balance sheet. In the year 2021,

respondent No.3 filed a suit for declaration, partition and

injunction and for rendition of accounts before the Court of

Additional District and Sessions Judge, at Srinigar in Case

No.1071/2021. Accordingly, suit is arrived at compromise

between the parties by its compromise decree dated

20.04.2022. It is also the contention that respondent Nos.2 and

3 together filed a arbitration petition against respondent Nos.4

NC: 2024:KHC:46323

and 5 before the Court of Principal District Judge at Srinigar in

Case No.Arb.No.1771/2024 and accordingly petition arrived at

by its order dated 01.04.2024. The said suit was disposed of by

way of compromise between the parties whereby the operation

of the hotel was the responsibility of respondent No.5 and daily

cash transaction of the hotel was the responsibility of

respondent No.5 and the profit accrued from the hotel was to be

shared among the respondent Nos.5 and 2 in the ratio as per

the settlement between the parties. After the expiry of two

years, respondent No.5 did not step down from conducting the

operation of hotel and is not allowing respondent No.2 to enter

the hotel and operate the same nor respondent No.5 is allowing

the parties to conduct the voting as per the terms and

conditions of the settlement deed arrived between the parties.

8. The Trial Court having taken note of the pleading of

the parties, framed the points whether the petitioner proves the

prima facie case, balance of convenience and whether petitioner

proves that in case temporary injunction is not granted, it will be

put to irreparable loss and injury and the Trial Court answered

all the points in the negative. The Trial Court while coming to

such a conclusion made an observation in paragraph No.27 that

there is no dispute between the company, hotel and

- 10 -

NC: 2024:KHC:46323

characteristics of hotel by both the parties. The main contention

of the petitioner is that the respondents hotel used the name of

the petitioner for business and if any quarrels and unwanted

issues created by respondent No.2 in the hotel, then the

petitioner will lose the reputation of his name in the eyes of

customers. The Trial Court also taken note of that the

respondents contention is that the arbitration proceedings has to

be started within 90 days and franchisee agreement entered into

between one respondent and all other respondents have not

given any authorization as per the partnership deed and further

contended that as per Section 21 of the Arbitration and

Conciliation Act, both parties have to agree for which respondent

has not agreed to the same to notice sent by the petitioner. The

Trial Court in paragraph No.28 made an observation with regard

to the partnership deed produced by respondent No.2, that "no

partners shall without the previous consent in writing of the

other partner shall assign, mortgage or charge his/her share or

interest in the partnership wholly or in part to any person other

than the other partner and also taken note of the recital in the

partnership. The Trial Court also made an observation that

ofcourse this Court cannot decide the merits of the case but

here a crucial point is involved about the business transactions

- 11 -

NC: 2024:KHC:46323

and to who has prima facie case and balance of convenience

these facts are relevant to understand this. As per the above

clause in partnership deed the partner who enters into any

agreement has to get the consent in writing of other partners.

The Trial Court taken note of Section 21 of the Arbitration and

Conciliation Act and extracted the same and held that as per the

above provision, it is clearly stated that the other party has to

agree on the request made by one party for referring the matter

to arbitration and such request is received by respondent No. 2

herein. As per above provision respondent No.2 should agree for

the request of the petitioner to refer the matter to arbitration.

The Trial Court taking note of these aspects into consideration

comes to the conclusion that the plaintiff has not made out a

prima facie case and balance of convenience and rejected the

I.As.

9. Being aggrieved by the said order, this present

appeal is filed and the learned counsel for the appellant would

contend that earlier temporary injunction was granted on

17.02.2024. On two grounds the Trial Court has invoked for

vacating the interim order. The learned counsel brought to the

notice of this court Section 19 of the Partnership Act and

contend that franchisee agreement is for a period of 10 years

- 12 -

NC: 2024:KHC:46323

from 2019 to 2029. The learned counsel contend that notice

was given on 04.04.2024 for appointment of arbitrator wherein

also in the notice specifically mentioned the name of the

arbitrator and reply was given on 23.04.2024. The learned

counsel brought to the notice of this Court the judgment of the

Division Bench of this Court in the case of SERVE AND VOLLEY

OUTDOOR ADVERTISING PRIVATE LIMITED v. BRUHAT

BENGALURU MAHANAGARA PALIKE, BANGALORE AND

OTHERS reported in MANU/KA/1082/2021, wherein

discussion was made in paragraph No.14 with regard to Sections

21 and 43 of the Arbitration Act. It is held therein that as per

Section 21 read with 43(2) of the Arbitration Act, an arbitration

shall be deemed to have commenced on the date on which a

request for reference to arbitration is received by the

respondent. However, if the parties agree under the agreement

to some other event for commencement of arbitration that

would have effect. Notice under Section 21 has to be served

and received by the respondent. If no notice is received by the

respondent, then there is no commencement of arbitral

proceedings under Section 21. Thus, the date of commencement

of the arbitration would be relevant for determining whether any

claim is barred by limitation. A time barred claim in arbitration

- 13 -

NC: 2024:KHC:46323

is to be dealt with in the same manner as a time barred prayer

in a suit, covered by Section 3 of the Limitation Act. Thus, in

the absence of an agreement, Section 21 of the Arbitration Act

states that arbitral proceedings commence on the date on which

a request for reference to arbitration is received by the

respondent.

10. The learned counsel also submits that CMP

application was filed on 28.06.2024 and brought to the notice of

this Court Section 9(2) of the Arbitration and Conciliation Act

and contend that sub-Section (2) of Section 9 says where,

before the commencement of the arbitral proceedings, a Court

passes an order for any interim measure of protection under

sub-Section (1), the arbitral proceedings shall be commenced

within a period of 90 days from the date of such order or within

such further time as the Court may determine. The learned

counsel contend that in the case on hand, even though order

was granted on 17.02.2024 granting ad-interim injunction, on

04.04.2024 itself notice was given within a period of three

months and steps were taken and after the issuance of notice

only when the reply was given not agreeing for appointment of

arbitrator, a petition was filed on 28.06.2024 and hence the

- 14 -

NC: 2024:KHC:46323

very contention of respondent No.2 that not filed the petition

within time cannot be accepted.

11. Per contra, the learned counsel for respondent No.2

would contend that the very franchisee agreement is not valid

and submits that partnership is also dissolved and issue was

also taken before the Court of Srinagar and family settlement

was arrived between the parties. The learned counsel submits

that no authorization was given to enter the franchisee

agreement and respondent No.2 is not a consenting party. The

learned counsel submits that family settlement happened on

20.04.2022 and partnership also stands cancelled and when

such being the case, there cannot be any preventive order

against respondent No.2. The learned counsel submits that CMP

is filed after four months and should have been filed within three

months. The learned counsel in support of her arguments relied

upon the order passed by this Court in the case of M/S. PATON

CONSTRUCTIONS PRIVATE LTD. v. M/S. LORVEN

PROJECTS LTD. reported in AIR 2017 KAR 135 and brought

to the notice of this Court the discussion made by this Court in

paragraph No.2, wherein contention was raised by the learned

counsel for the appellant that, in view of Rule 9(4) of the High

Court of Karnataka Arbitration (Proceedings before the Courts),

- 15 -

NC: 2024:KHC:46323

Rules 2001, the impugned order dated 21.12.2013 granting the

interim measure under Section 9 of the Act stood vacated on the

expiry of three months from the date of presentation of the

application under Section 9 of the Act, as arbitral proceedings

were not initiated within the aforesaid three months. To examine

the contention urged, Rule 9(4) of the Rules requires to be

noticed and the same was extracted and discussion was made

that the above extracted sub-rule states that in the case of an

application for any interim measure made before initiating

arbitral proceedings, if the arbitral proceedings in respect of the

dispute are not initiated within three months from the date of

presentation of the application under Section 9 of the Act, any

interim order granted shall stand vacated without any specific

order to that effect by the Court which passed the order. It is

relevant to state that 'any interim order' referred to in Rule 9(4)

extracted above, in the context, shall include any order granting

any interim measure. The learned counsel referring this

judgment would contend that when the proceedings has not

been initiated within a period of three months from the date of

interim order, in view of the said Rule, automatically it stands

vacated and the contention of the learned counsel for the

- 16 -

NC: 2024:KHC:46323

appellant that initiation of notice itself is commencement of

arbitral proceedings cannot be accepted.

12. Having heard the learned counsel for the appellant

and the learned counsel for respondent No.2 and considering the

principles laid down in the judgments referred (supra) by both

the learned counsel and also considering Sections 9, 21 and 43

of the Arbitration and Conciliation Act as well as Rule 9(4) of the

said Rules, the points that arise for the consideration of this

Court are:

(i) Whether the Trial Court committed an error in vacating the interim order granted in dismissing I.A.Nos.5 to 7 and whether it requires interference of this Court?

(ii) What order?

13. Having heard the respective learned counsel, it is

not in dispute that there was a franchisee agreement between

the appellant and the respondent partners and the same is

dated 23.03.2019. It is also not in dispute that the appellant

was running a hotel without any hindrance from 2019 till

23.01.2024 and the appellant also specifically pleaded in the

plaint that respondent No.2 has been illegally interfering with

the smooth operations of the hotel premises. It is not in dispute

- 17 -

NC: 2024:KHC:46323

that the franchisee agreement was entered into between the

appellant, respondent No.1 and other partners and no doubt

there was a difference between the partners and then started

the problem. The respondent No.2 started interfering with the

business of the appellant. It is also not in dispute that the suit

is filed wherein it is specifically pleaded with regard to the

interference of respondent No.2 and also interim order was

granted on 17.02.2024 when the proceedings was initiated

under Section 9 of the Arbitration proceedings. The learned

counsel for the appellant brought to the notice of this Court that

they have issued notice on 11.04.2024 and the same is

acknowledged by respondent No.2 and he has given reply on

23.04.2024, wherein he has rejected the offer of appointing an

arbitrator to resolve the issues among them. It is not in dispute

that CMP was filed on 28.06.2024. The contention of

respondent No.2 is that franchisee agreement is not valid and

he is not a consenting party and the said contention cannot be

accepted for the reason that, there was an agreement in the

year 2019 itself for running the hotel. No doubt, there was a

dispute between the partners and there was a family settlement

between them and also the document is placed with regard to

the family settlement is concerned.

- 18 -

NC: 2024:KHC:46323

14. It has to be noted that when the period was given as

ten years for running the hotel and if there is any dispute

between the partners, the same was not inter se business of the

appellant and the respondent. It is also important to note that

when there is an arbitration dispute and reference is also made

after filing of the petition under Section 9, the only moot

question involved before this Court in view of the contention of

the learned counsel for the appellant and respondent No.2 is

whether the proceedings in CMP is initiated within three months.

No doubt, Section 9 of the Arbitration and Conciliation Act, 1996

discloses that the Court can grant interim relief to the aggrieved

party before or during arbitral proceedings or at any time after

making of the arbitral award. Section 9(2) of the Arbitration and

Conciliation Act, 1996 is very clear, before commencement of

arbitration proceedings, if the Court passes an order of interim

measure of protection under Section 9(1) of the Arbitration and

Conciliation Act, 1996 the arbitral proceedings shall commence

within a period of 90 days from the date of such order or within

an extendable timeline as per the courts' discretion.

15. In the case on hand, the extendable time which the

Court may determine does not arise, as there is no such order.

It is also important to note that Rule 9(4) of the High Court of

- 19 -

NC: 2024:KHC:46323

Karnataka (Proceedings before the Courts) Rules, 2001 is also

clear that after a party obtains any relief from a Court under

Section 9 of the Arbitration and Conciliation Act, 1996, such a

party is required to take steps to commence arbitration

proceedings. Rule 9(4) further states that if a party fails to take

steps to commence arbitration, any interim order granted by the

Court shall stand automatically vacated. Further, if the arbitral

proceedings are not initiated within three months from the date

of presentation of application, the interim order would stand

vacated. Hence, this Court has to read Section 9(2) of the

Arbitration and Conciliation Act, 1996 as well as Rule 9(4) of the

High Court of Karnataka (Proceedings before the Courts) Rules,

2001 conjointly and on conjoint reading of both Section 9(2) and

Rule 9(4), it is clear that within 90 days from the date of such

interim order being granted, under Section 9(1) of the

Arbitration and Conciliation Act, 1996, arbitration proceedings

has to be initiated and also Rule 9(4) is very clear that, in case

of any application for interim-measure is filed before the Court,

if the arbitration proceedings is not initiated within three months

from the date of presentation of application under Section 9,

interim order shall stand vacated. The word used is 'shall'.

- 20 -

NC: 2024:KHC:46323

16. Learned counsel for the appellant relies upon the

judgment of the Division Bench of this Court in SERVE AMD

VOLLEY OUTDOOR ADVERTISING PRIVATE LIMIED VS.

BRAUHAT BENGALURU MAHANAGARA PALIKE,

BANGALORE AND ORS. decided on 08.01.2021, wherein

discussion was made with regard to Section 21 as regards

commencement of arbitration proceedings, wherein Section 3 of

the Limitation Act is also discussed in paragraph No.14. The

Division Bench of this Court, having extracted Sections 21 and

43 of the Arbitration Act, 1996 discussed that as per Section 21

read with Section 43(2) of the Arbitration Act, an arbitration

shall be deemed to have commenced on the date on which a

request for reference to arbitration is received by the

respondent. However, if the parties agree under the agreement

to some other event for commencement of arbitration that

would have effect. In the case on hand, no such agreement is

entered into between the parties. It is also clear that notice

under Section 21 has to be served and received by the

respondent No.2. If no notice is received by the respondent

No.2, then there is no commencement of arbitral proceedings

under Section 21 of the Arbitration Act. Thus, the date of

commencement of arbitration would be relevant to determine

- 21 -

NC: 2024:KHC:46323

whether information claimed and received is barred by limitation

and the case on hand, the notice is given on 11.04.2024.

Whether the notice is a commencement of arbitration

proceedings is the issue, since the learned counsel for the

respondent No.2 would contend that the appellant ought to have

filed the petition within a period of 90 days in view of Rule 9(4)

which has been referred supra. It is also very clear that as per

Section 9(2) of the Arbitration Act, where before the

commencement of arbitral proceedings, a Court passes an order

of interim measure under 9(2) of the Arbitration Act, within a

period of 90 days from the date of such order or within such

period, the petition has to be filed. In the case on hand, no

doubt, the interim order has been granted on 17.02.2024,

having conjointly read Section 9(2) of the Arbitration Act as well

as Rule 9(4) High Court of Karnataka (Proceedings before the

Courts) Rules, 2001, it is clear that maximum period given is 90

days.

17. This Court also in the judgment referred supra by

the respondent No.2 in M/S. PATON CONSTRUCTIONS

PRIVATE LTD. v. M/S. LORVEN PROJECTS LTD. reported in

AIR 2017 KAR 135 invoked Rule 9(4) and extracted the same,

comes to the conclusion that in case of an application for any

- 22 -

NC: 2024:KHC:46323

interim measure made before initiating arbitral proceedings, if

the arbitral proceedings in respect of the dispute are not

initiated within three months from the date of presentation of

the application under Section 9 of the Act, any interim order

granted shall stand vacated without any specific order to that

effect by the Court which passed the order.

18. No doubt, in the case on hand, there was an interim

order on 17.02.2024, the very contention of the learned counsel

for the appellant is that notice was issued on 11.04.2024 and

notice was served and reply was given on 23.04.2024 rejecting

offer and the notice is within time and the appellant approached

the Court by filing CMP within the time period by issuing notice.

But, admittedly petition was filed on 28.06.2024 which was after

90 days and three months time as stipulated under Section 9(2)

and Rule 9(4). When such being the case, the contention of the

learned counsel for the appellant that issuance of notice is within

time cannot be accepted. The judgment of the Division Bench of

this Court in SERVE AMD VOLLEY OUTDOOR ADVERTISING

PRIVATE LIMIED's case is very clear that an arbitration shall

be deemed to have commenced on the date on which a request

for reference to arbitration is received by the respondent.

However, if the parties agree under the agreement to some

- 23 -

NC: 2024:KHC:46323

other event for commencement of arbitration that would have

effect. But, in the case on hand, no such agreement and the

same was refused while giving reply and mere initiation of

notice itself cannot be construed as commencement of

proceedings. Hence, the contention of the learned counsel of

the appellant cannot be accepted.

19. When the proceedings has not been initiated within

the period of 90 days or three months as contemplated under

Section 9(2) as well as Rule 9(4), the very contention of the

learned counsel for the appellant cannot be accepted as the

notice was given. However, there is a force in the contention of

the learned counsel for the appellant that Trial Court committed

an error in relying upon partnership deed in paragraph No.28

i.e., "None of the partners shall without the consent of the other

partner in writing monies, goods and effects belonging to the

partnership firm for the purposes other than those for the

purpose of partnership business and matters arising out of or in

the course of such business" and "No partners shall without the

previous consent in writing of the other partner shall assign,

mortgage or charge his/her share or interest in the partnership

wholly or in part to any person other than the other partner", in

coming to the conclusion that Court cannot decide the merits of

- 24 -

NC: 2024:KHC:46323

the case and decide who has prima facie case and balance of

convenience and these facts are relevant to understand this is

an erroneous observation, since there was an agreement in the

year 2019 itself and the partners have also kept quite from 2019

to 2023 i.e., till filing of the petition under Arbitration Act and if

any dispute arises between the partners that cannot be a

ground to come to a conclusion that there was no consent. The

Trial Court has given reasoning that there is no prima facie case,

since respondent No.2 was not party to the said agreement and

the same cannot be accepted as there was a franchisee

agreement to run the hotel.

20. However, taking note of the question involved in the

matter, particularly time frame under Section 9(2) as well Rule

9(4), initiation of the proceedings is not within time and Trial

Court also taken note of the same while vacating the interim

order in paragraph No.28 that respondent's contention is that

arbitration proceedings has to be started within 90 days and

Franchise agreement entered into between one respondent and

further contended that, all other respondents not given any

authorization as per the partnership deed and further contended

that as per Section 21 of the Arbitration and Conciliation Act,

both parties has to agree for which respondent has not agreed

- 25 -

NC: 2024:KHC:46323

to the same to notice sent by the appellant. But the very

approach with regard to the other partners have not given

authorization cannot be a ground and the same is an inter se

dispute between them. When the arbitration proceedings has

not been initiated within time and Section 9(2) proviso of the

Act is clear that it has to be initiated within 90 days and the

same has not been initiated within 90 days and issuance of

notice itself is initiation of the arbitration proceedings and it has

to be construed as commencement of arbitration proceedings

cannot be accepted and issuance of notice itself is not

commencement of proceedings and the same is only for steps

taken for initiation of proceedings. In the case on hand, in reply

rejected the offer on 23.04.2024 itself and ought to have filed

on or before 17.05.2024 itself, but filed on 28.06.2024. Hence,

I do not find any merit to come to the conclusion that the Trial

Court has committed an error in dismissing the applications.

Accordingly, the miscellaneous first appeal is dismissed.

Sd/-

(H.P.SANDESH) JUDGE

MD/ST

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter