Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

D.S.Mallaplur S/O. Singadeppa vs State Of Karnataka
2024 Latest Caselaw 12485 Kant

Citation : 2024 Latest Caselaw 12485 Kant
Judgement Date : 5 June, 2024

Karnataka High Court

D.S.Mallaplur S/O. Singadeppa vs State Of Karnataka on 5 June, 2024

                                                -1-
                                                      NC: 2024:KHC-D:7490
                                                       WP No. 106221 of 2014




                        IN THE HIGH COURT OF KARNATAKA, DHARWAD BENCH
                              DATED THIS THE 5TH DAY OF JUNE, 2024
                                             BEFORE
                        THE HON'BLE MR JUSTICE SACHIN SHANKAR MAGADUM
                           WRIT PETITION NO. 106221 OF 2014 (GM-TEN)
                   BETWEEN:
                   D.S. MALLAPLUR S/O. SINGADEPPA,
                   AGE: 54 YEARS,
                   OCC: CLASS-I CONTRACTOR
                   R/O. SHAHAWAKAR, NEAR KMP ROAD,
                   BADAMI, DIST: BAGALKOT-587201.
                                                                 ...PETITIONER
                   (BY SRI. B.S. KAMATE, ADVOCATE)
                   AND:
                   1.   STATE OF KARNATAKA,
                        BY ITS SECRETARY,
                        DEPARTMENT OF MINOR IRRIGATION,
                        VIDHANASOUDHA, BANGALORE-01.

                   2.   THE EXECUTIVE DIRECTOR,
                        JALA SAMVARDHANE YOJANA SANGHA,
                        (DEPARTMENT OF WATER RESOURCES
Digitally signed
by BHARATHI H
M
                        AND MINOR IRRIGATION)
Location: HIGH
COURT OF
                        NO.42, 5TH CROSS, RMS LAYOUT,
KARNATAKA
DHARWAD
BENCH
                        SADASHIVANAGAR, BANGALORE-560080.
Date:
2024.06.13
12:18:48 +0530
                   3.   THE DISTRICT PROJECT CO-ORDINATOR,
                        JSYS, DISTRICT PROJECT UNIT (R),
                        GOVERNMENT OF KARNATAKA,
                        SECTOR 32, PLOT NO.51,
                        NAVANAGAR, BAGALKOT-587102.

                   4.   SHRI RANGASAMUDRA KERE
                        BALAKEDARARA SANGHA (R),
                        RANGASAMUDRA, TQ: BADAMI,
                        DIST: BAGALKOT-587201,
                        BY ITS SECRETARY.
                                -2-
                                     NC: 2024:KHC-D:7490
                                         WP No. 106221 of 2014




5.   THE SUPERINTENDING ENGINEER-I,
     JSYS, NO.42, 5TH CROSS RMS LAYOUT,
     SADASHIVANAGAR, BANGALORE-560080.

6.   THE UPPER DEPUTY COMMISSIONER,
     OFFICE OF DEPUTY COMMISSIONER,
     DISTRICT ADMINISTRATION BUILDING,
     NAVANAGAR, BAGALKOT-587102.

7.   THE TAHASILDAR,
     BADAMI TALUKA, BADAMI,
     DIST: BAGALKOT-587201.
                                                 ...RESPONDENTS
(BY SRI. V.S. KALASURMATH, HCGP FOR R1-R3 & R5-R7;
    SRI. S.C. HIREMATH, ADV. FOR R4)

      THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND 227
OF THE CONSTITUTION OF INDIA PRAYING TO ISSUE A WRIT IN THE
NATURE OF CERTIORARI OR ANY OTHER WRIT OR ORDER OR
DIRECTION, QUASHING THE IMPUGNED ORDER DATED 25.04.2014
BEARING NO.JA.SAM.YO.SAM/BHAG/TANTRIK/14-15/2185 PASSED
BY THE 3RD RESPONDENT PRODUCED           AT ANNEXURE-T AND THE
ORDER            DATED      02.06.2014        BEARING      NO.
JA.SAM.YO.SAM/JI.YO.GHA/BHAG/TANTRIK/2014-15/2215       PASSED
           RD
BY THE 3        RESPONDENT PRODUCED AT ANNEXURE-X AND ALSO
ORDER DATED 26.05.2014 PASSED BY THE 6TH RESPONDENT
DEPUTY COMMISSIONER IN RRC/CR-5/2014-15 AT ANNEXURE-Y.


      THIS PETITION, COMING ON FOR       HEARING, THIS DAY, THE

COURT MADE THE FOLLOWING:
                              -3-
                                     NC: 2024:KHC-D:7490
                                       WP No. 106221 of 2014




                          ORDER

The petitioner filed the captioned petition assailing

the impugned order dated 25.04.2014 passed by

respondent No.3 as per Annexure-T, consequent order

dated 02.05.2014 passed by respondent No.3 as per

Annexure-X and also order dated 26.05.2014 passed by

respondent No.6-Deputy Commissioner as per

Annexure-Y.

2. Respondent No.3 floated tender notification to

implement a project relating to canal concrete lining of

Rangasamudra Tank Development Work. Petitioner was

the successful bidder and a tender agreement came to be

executed between the petitioner and respondent No.4 on

20.11.2010. The petitioner completed the contract work

and on inspection of the project implemented by the

petitioner, respondent No.5 in his report indicated that the

work done by the petitioner is found to be satisfactory.

Similar opinion was expressed by respondent No.3.

NC: 2024:KHC-D:7490

3. De hors these two opinions expressed as per

Annexures-C, D and E, respondent No.2 issued a notice

indicating that respondent No.3 has not taken note of the

defects as per report dated 30.06.2011. The respondents

indicated certain shortcomings in respect of one of the

canal work.

4. Petitioner contends that, in terms of the defects

notified by the respondents, he has carried out the repairs

and the same is examined by the respondents and

satisfactory reports are issued as per Annexures-H and L.

Petitioner's grievances is that without taking cognizance of

the reports at Annexures-H and L, respondent No.3 has

issued the impugned order as per Annexure-T, thereby

ordering for forfeiture of the security deposit of

Rs.15,17,910/- and the retention of money to the tune of

Rs.1,86,395/- was also sought to be forfeited. Pursuant to

order passed by respondent No.2 as per Annexure-T,

respondent No.3 issued a communication addressed to the

Tahasildar on 02.06.2014 requesting to create a

NC: 2024:KHC-D:7490

charge/encumbrance on the properties of the petitioner as

per Annexure-X. Respondent No.6-Deputy Commissioner

directed respondent No.3 to recover the amount from the

petitioner as per the impugned endorsement vide

Annexure-Y.

5. Heard the learned counsel for the petitioner,

learned HCGP and perused the material on record.

6. The orders under challenge are found to be

cryptic in nature. Strangely, respondent Nos.2 and 3 have

not taken cognizance of the reports submitted by District

Project Coordinator, which is evident from Annexure-H. It

is relevant to take cognizance of the report submitted by

District Project Coordinator, which reads as under:

"Main canal left Bank: The rectification in the main canal and in Chimmalage Branch canal cement concrete lining is taken up 25-2-2011. The surface is demolished and redone. Thickness is maintained and curing is going on. This matter is noted for future guidance.

This is for favour of kind information."

NC: 2024:KHC-D:7490

7. The report submitted by EGIS India Consulting

Engineers Pvt. Ltd., 14.05.2011 to the District Project

Coordinator is also relevant and the same has a bearing on

the controversy relating to the deficiencies alleged against

the petitioner while implementing the project. The said

company has visited the site and on spot inspection, has

also submitted a report indicating that petitioner has

rectified the deficiencies indicated by the concerned

authorities and accordingly, the company has opined that

the work done by the petitioner is found to be satisfactory

and the bad quality of concrete found at some places has

been removed and rectified. The relevant portion of this

report prepared by the said company which was addressed

to District Project Coordinator is also relevant and the

relevant portion is extracted, which reads as under:

"RANGASAMUDRA TANK (TC: 200042)/RANGASAMDRA VILLAGE/BAGALKOT DFT/BADAMI TO:

Est.Cost: Rs.44.22 Lakhs.

This tank is under list of 10% Random Selection of works in tank.

• CC Lining work on LBC Branch canal completed for 600.00m. The section is trapezoldal and concrete

NC: 2024:KHC-D:7490

is M15 grade with a thickness of 7.50CM at sides and 7.50CM thick at bed. Curing period completed.

Concrete cubes have casted and results for 28 days strength is to be obtained from laboratory. Concrete has been checked at several locations and it is found satisfactory. The thickness also found 7.50CM. In some locations, there was a bad quality of concrete was laid and it was removed and rectified.

• In the RBC branch canal 675.00M length of CC lining has been done and the work is found satisfactory.

• We have reported in our letter no Egis India/Bang/Bagalkot/0208/2010-11, dated 14.02.2011, that the concrete was not satisfactory in LBC main canal. The defective portions have been removed and rectified the concrete work. Now the work is found satisfactory."

8. Now let me examine the impugned order

passed by respondent No.3 as per Annexure-T. The order

under challenge does not advert to these two reports and

therefore, the consequential orders passed as per

Annexures-X and Y are also not sustainable. The company

which was assigned to examine the quality of the project

implemented by the petitioner after visiting site, has

submitted a report indicating that deficiencies notified by

the concerned authorities are rectified by the petitioner.

Therefore, the impugned orders under challenge are not

sustainable. The order passed by respondent No.3 as per

NC: 2024:KHC-D:7490

Annexures-H and L, has not at all taken cognizance of the

reports. Even before this court, the respondent-State to

justify the orders passed by respondent No.3 as per

Annexure-T has not placed any credible material to doubt

the reports placed on record by the surveying company at

Annexures-H and L, which are culled out supra.

9. For the forgoing reasons, the impugned orders

are liable to be quashed. Accordingly, this court passes the

following:

ORDER

i) The writ petition is allowed.

ii) The impugned orders at Annexures-T, X and Y are hereby quashed.


           iii)     It is open for respondent No.3 to re-examine
                    the   matter    by   taking     cognizance   of

Annexures-H and L. Respondent No.3 shall also strictly adhere to the observations made by this court in the course of the judgment rendered.

NC: 2024:KHC-D:7490

iv) This exercise shall be completed within a period of three months from the date of receipt of a certified copy of this order.

v) Respondent No.3 shall secure any further explanation from the petitioner and after affording reasonable opportunity shall proceed to pass appropriate order.

In view disposal of the writ petition, I.A.No.1/2016

does not survive for consideration and the same is

disposed off.

Sd/-

JUDGE

MBS Ct-mck

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter