Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Mrs. Sampada Ballal vs Mr. K Sooryanarayana
2024 Latest Caselaw 999 Kant

Citation : 2024 Latest Caselaw 999 Kant
Judgement Date : 11 January, 2024

Karnataka High Court

Mrs. Sampada Ballal vs Mr. K Sooryanarayana on 11 January, 2024

Author: M.G.S. Kamal

Bench: M.G.S. Kamal

                                             -1-
                                                         NC: 2024:KHC:1623
                                                      RSA No. 1099 of 2018




                   IN THE HIGH COURT OF KARNATAKA AT BENGALURU

                      DATED THIS THE 11TH DAY OF JANUARY, 2024

                                          BEFORE
                         THE HON'BLE MR JUSTICE M.G.S. KAMAL
                   REGULAR SECOND APPEAL NO. 1099 OF 2018 (MON)
                   BETWEEN:
                      MRS. SAMPADA BALLAL
                      AGED ABOUT 48 YEARS,
                      W/O VRISHABHA ARIGA,
                      R/AT:NEAR NEERACHILUME
                      UJIRE VILLAGE & P.O.
                      BELTHANGADY TALUK, D.K. DISTRICT - 574 214.
                                                              ...APPELLANT
                   (BY SRI. N. SUKUMAR JAIN, ADVOCATE)

                   AND:
                      MR. K SOORYANARAYANA
                      AGED ABOUT 53 YEARS,
                      S/O LATE H. SHRIDHAR,
                      PRO:M/s.GRAPHICS DESIGNER,
                      CIVIL ENGINEERS & CONTRACTORS,
Digitally signed
by SUMA B N           MAIN ROAD, UJIRE VILLAGE & P.O.,
Location: High        BELTHANGADY TLAUK, D.K. DISTRICT - 574 214.
Court of
Karnataka
                                                            ...RESPONDENT
                   (BY SRI. K SHRIHARI, ADVOCATE)

                        THIS RSA IS FILED UNDER SECTION 100 OF CPC.,
                   AGAINST THE JUDGMENT & DECREE DATED 03.03.2018
                   PASSED IN R.A.NO.23/2017 ON THE FILE OF THE PRINCIPAL
                   DISTIRCT JUDGE, D.K.MANGALURU, DISMISSING THE APPEAL
                   AND    CONFIRMING    THE    JUDGMENT    AND    DECREE
                   DATED:07.03.2017 PASSED IN O.S.NO.62/2007 ON THE FILE
                   OF THE PRL.SENIOR CIVIL JUDGE AND JMFC., BELTHANGADY,
                   D.K.
                               -2-
                                             NC: 2024:KHC:1623
                                          RSA No. 1099 of 2018




     THIS APPEAL, COMING ON FOR FINAL HEARING, THIS
DAY, THE COURT DELIVERED THE FOLLOWING:



                        JUDGMENT

This appeal is by the defendant aggrieved by the

Judgment and decree dated 07.03.2017 passed in

O.S.No.62/2007 on the file of the Principal Senior Civil

Judge and JMFC, Belthangady, (Trial Court) by which trial

court had decreed the suit directing the

appellant/defendant to pay Rs.2,04,567/- with interest at

8% p.a. from the date of suit till realisation. Aggrieved by

the same appellant/defendant preferred regular appeal in

R.A.No.23/2017 on the file of Principal District Judge, D.K.,

Mangaluru (First Appellate Court). The first appellate court

by its Judgment and order dated 03.03.2018 dismissed the

appeal confirming the Judgment and decree passed by the

trial court. Being aggrieved by the same,

appellant/defendant is before this Court.

NC: 2024:KHC:1623

2. The above suit was filed in O.S.No.62/2007 by the

plaintiff seeking Judgment and decree in the nature of

direction to the defendant/appellant to pay Rs.2,04,567/-

towards the outstanding dues payable by the defendant for

plaintiff having constructed her house. It is the case of the

plaintiff that he is a building contractor by profession

carrying on the business in the name and style of

"M/s.Graphic Designers". That the defendant who owns a

house site at Ujire Village had instructed plaintiff to

construct a residential house on the said site which was

agreed by the plaintiff. There was no written agreement

between plaintiff and defendant with regard to rates and

other terms of the contract. However, defendant had

expressed that she would instruct the plaintiff of her

requirement as and when the construction work would

progress. Acting upon the representation of the defendant

plaintiff had commenced the construction and had

submitted first running account bill dated 24.07.2006 for

Rs.2,28,942/-. Plaintiff had continued the work and had

submitted second running account bill on 11.12.2006 for a

NC: 2024:KHC:1623

sum of Rs.4,80,625/- and after completion of some works

plaintiff had raised third running account bill dated

04.04.2007 for Rs.1,95,000/-. Thus in aggregate plaintiff

submitted three bills amounting to Rs.9,04,567/-. That as

against the same defendant had paid a sum of

Rs.7,00,000/- and was due and liable to pay

Rs.2,04,567/-. It is further contended that defendant had

promised that she would arrange to pay the entire amount

and acting upon the promise made by the defendant,

plaintiff continued the work but when the plaintiff had

raised third running account bill defendant started evading

the payment and started to complain about the quality of

the work. It is contended that the plaintiff had completed

the work upon instructions of defendant and her husband.

He also effected changes during the course of work as

instructed by the defendant. Plaintiff had caused issue of

notice through his lawyer on 26.04.2007 calling upon the

defendant to make the payment. As there was no

compliance to the said demand notice, plaintiff filed a suit

for recovery of dues.

NC: 2024:KHC:1623

3. On receipt of summons defendant appeared and

filed written statement contending that the estimation of

the work as on 03.05.2006 was for Rs.7,50,355/- for the

purpose of construction of the residential house and the

defendant had agreed for the said estimation and

accordingly entrusted the work to the plaintiff. That

plaintiff had not constructed the house as per the

specification furnished and undertaken by him through

estimate and that there was deficiency in construction of

work and that the plaintiff was paid Rs.7,00,000/- by

defendant which itself was on a higher side. That plaintiff

submitted false exaggerated bills and thereby cheated

defendant and induced her to make certain excess

payment. It is also contended value of the work

completed by the plaintiff was only worth Rs.5,00,000/-.

Since there was incomplete and deficiency of work

defendant requested plaintiff to complete the work which

was refused by the plaintiff. Based on these pleadings

defendant sought dismissal of the suit.

NC: 2024:KHC:1623

4. Based on the pleadings trial Court framed

following issues:

"1. Whether plaintiff proves that as per the oral understanding with the defendant they have completed the construction work of defendant's house and in respect of such construct defendant is due to pay Rs.2,04,567/- as contended?

2. Do they further proves that in view of unilateral reputation of contract by the defendant they have been forced to file this suit for recovery of alleged due amount of their bills?

3. Whether the plaintiff is entitled for a decree for recovery of the suit claim from the defendant as prayed?

4. Does the defendant proves that due to deficiencies in the construction work by the plaintiff she has suffered irreparable injury and great loss and nothing is due by her to the plaintiff?

5. Is the defendant entitled for compensatory costs from the plaintiff?

6. To what reliefs the parties are entitled?

7. What Order or Decree?".

5. Plaintiff examined himself as PW-1 and got

marked exhibits P1 to P-25 and defendant examined

herself as DW-1 and witnesses DW-2 to DW-6 and got

NC: 2024:KHC:1623

marked exhibits D-1 to D-39. On appreciation of

pleadings, oral and documentary evidence, the trial court

answered issues 1 to 3 in the affirmative and issues 4 and

5 in the negative and consequently decreed the suit as

sought for. Aggrieved by the same, defendant preferred

regular appeal in R.A.No.23/2017. Considering the grounds

urged in the memorandum of appeal first appellate court

framed following points for its consideration:

"1.Whether the impugned Judgment/Decree is not tenable under law?

2. Whether the impugned Judgment/Decree requires interference?

3. What Order?".

6. On re-appreciation of the pleadings and evidence,

the first appellate Court answered point Nos.1 and 2 in the

negative and dismissed the appeal confirming the

Judgment and decree passed by the trial court. Being

aggrieved by the same defendant/appellant is before this

Court.

NC: 2024:KHC:1623

7. This Court by order dated 10.01.2019 admitted

the appeal for consideration of the following substantial

question of law:

"i) Whether both the Courts below have rightly appreciated the work contract document, based on which the Suit claim is made?

ii) Whether both the Courts below have rightly appreciated the defence raised by the appellant herein with reference to excess payment said to have been made by him?".

8. Learned counsel for appellant reiterating the

grounds urged in the memorandum of appeal submits that

the trial court and first appellate court have adopted the

wrong approach in appreciating pleadings and evidence.

He submits that though issues have been framed casting

burden on the plaintiff to prove his claim, while dealing

with said issue trial court as well as first appellate court

burdened the defendant to prove her case. He submits

that such approach is illegal and erroneous in as much as

it is plaintiff to have proved his case in justification of his

claim for money. He submits that the defendant had

NC: 2024:KHC:1623

specifically averred in the written statement regarding

deficiencies in the work committed by the plaintiff.

However, merely because plaintiff had lost before the

Consumer Disputes Redressal Forum. The first appellate

court has taken the same as a reason to negate the

defence set up by the defendant. He further submits that

the plaintiff ought to have independently established his

case for a claim of Rs.9,04,567/- while admittedly

defendant had already paid Rs.7,00,000/-. Trial court and

first appellate court failed to appreciate that the plaintiff

has not produced any evidence to justify his claim for

additional claim of Rs.2,04,567/-. Learned counsel

referring to deposition of DW-2 to DW-6 submits trial court

and first appellate court have not appreciated the evidence

in the nature of deposition of these witnesses. Had the trial

court and first appellate court taken into consideration

their deposition they would have dismissed the suit of the

plaintiff. Thus he submits substantial question of law

raised by this Court needs to be answered in favour of the

defendant.

- 10 -

NC: 2024:KHC:1623

8. Per contra, Sri.Srihari K., learned counsel

appearing for plaintiff/respondent submits that the trial

court has framed appropriate issues casting the burden on

the plaintiff to prove and establish his case for recovery of

Rs.2,04,567/-. He submits that the plaintiff apart from

making averment in the plaint had also produced three

running account bills aggregating a sum of Rs.9,04,567/-

giving minute details of the claim being made by him. It is

his further submission that the said bills were made

available by the plaintiff much ahead of filing of the suit.

Instead of complying the said bills, the defendant had

opted to have the dispute adjudicated before the District

Consumer Disputes Redressal Forum and same having met

with dismissal, the plaintiff had filed the suit for recovery.

Nothing prevented the defendant from specifically denying

the claim of the plaintiff in the written statement. That

having not been done defendant cannot be heard to say

that the burden was casted on the defendant to prove the

case. He submits that the trial court and first appellate

court have appreciated the material evidence produced by

- 11 -

NC: 2024:KHC:1623

the plaintiff and rightly come to the conclusion of

defendant being due and liable to make payment to the

plaintiff. He submits that substantial question needs to be

answered in favour of the plaintiff/respondent and hence

seeks for dismissal of the appeal.

9. Heard. Perused the records.

10. The admitted facts in the matter are that plaintiff

had agreed to put up construction of a residential house

for the defendant and said agreement was an oral

agreement. However, plaintiff appears to have raised

three running account bills which are produced by plaintiff

at Ex.P-3 to P-5 (Ex.D32 to Ex.D34). The plaintiff has also

produced Ex.P-6 to P-17 in justification of his claim of he

purchasing materials for purpose of putting up

construction. Contents of the bills at Ex.P-3 to P-5 reveal

that the plaintiff has given details of items of the work,

extent of work and cost of the work. Ex.P-3 is dated

24.07.2006 which broadly consists of nine (9) items of

work with all details provided thereunder. The value of the

- 12 -

NC: 2024:KHC:1623

said bill is Rs.2,28,942/-. EX.P-4 is the second running

account bill dated 11.12.2006 which consists of thirteen

(13) items of work with all details provided there under.

The value of the said bill is Rs.4,80,625/-. Ex.P5 is the

third running account bill dated 04.04.2007 consisting of

six(6) items of work with all details contained thereunder

aggregating at Rs.1,95,000/-. There is also an

endorsement on the said bill with regard to intermittent

payments made by the defendant between 30.04.2006 to

27.06.2007 aggregating to sum of Rs.7,00,000/-.

11. It is also an admitted fact that these bills were

received by the defendant. Admittedly defendant being

dissatisfied with the work carried out by the plaintiff had

preferred a complaint before the District Consumer

Disputes Redressal Forum, Mangaluru in complaint

No.159/2007 as per Ex.P-22 and the said complaint

resulted in dismissal. There upon the plaintiff had filed the

above suit for recovery.

- 13 -

NC: 2024:KHC:1623

12. In her written statement the defendant has

made ground denial of the claim made by the plaintiff.

The trial court has taken note of the contents of the

written statement filed by the defendant as seen at

paragraph 10 while answering issue Nos.1 to 4, that there

is no specific denial made by the defendant. The trial

court has also taken note of the requirement of law namely

provisions of Order VIII Rule 3 of CPC and Order VIII Rule

4 adverting to `denial in specific' and `evasive reply'. The

trial court has taken note of the fact that despite

defendant having opportunity to set forth her case

specifically has not chosen to do so. Rightly so more

particularly, when the defendant had opted to file

complaint before the District Consumer Disputes Redressal

Forum. Upon receipt of the three running account bills

cannot be heard to say that she was not aware of the

contents of Ex.P-3 to P-5. If at all defendant was clear in

her defence that the plaintiff had made excess billing and

had claimed amount in respect of the work not carried out

the defendant ought to come clear in pointing out details

- 14 -

NC: 2024:KHC:1623

of work which according to the defendant were not carried

out by plaintiff. It is this lack of specific denial and

pleading by the defendant has been considered by the trial

court and first appellate court as inadequate defence which

is now construed and argued by learned counsel for

appellant as casting burden on the defendant. The said

submission cannot be countenanced. It is not the case of

the defendant that the plaintiff has not given details of the

work carried out by him. It is the case of the defendant

that the plaintiff is making excess claim. Therefore the

defendant ought to have specifically dealt with each item

of work in respect of which the plaintiff has claimed and

demanded the payment as per Ex.P-3 to P-5 running

account bills. Defendant not having met with this basic

and elementary requirement cannot contend that trial

court and first appellate court has casted burden on the

defendant to prove the case of the plaintiff.

13. Another aspect of the matter to be looked at is

that defendant do not deny payment of Rs.7,00,000/- but

- 15 -

NC: 2024:KHC:1623

does not give details as to the nature and extent of work

to which the said Rs.7,00,000/- has been paid. Merely

saying that defendant has made payment of Rs.7,00,000/-

and the claim of Rs.2,04,567/- as excess demand without

providing any details thereof would not be sufficient. In

that view of the matter, the reasoning and finding

recorded by the trial court and first appellate court cannot

be found fault with. It is another aspect that the defendant

got certain work done and completed through a third party

contractor. But not having adverted to the claim of the

plaintiff defendant cannot seek to contend that the said

additional work carried out by the third party contractor

was because of excess claim made by the plaintiff or

because of the work not done by the plaintiff. Necessary

to mention that the defendant has not filed any counter

claim regarding purported work got executed by her

through a third party contractor and witnesses DW-2 to 5

who are apparently got examined by the defendant in

justification of her case of she getting the work done

- 16 -

NC: 2024:KHC:1623

through a third party, the said evidence hardly met the

requirement of denying claim of the plaintiff.

14. The trial court and first appellate court have taken

these aspects of the matter into consideration and have

come to the just and right conclusion. As such substantial

question of law raised for consideration as noted above are

answered in the affirmative in favour of the plaintiff and

appeal is accordingly dismissed confirming the Judgment

and decree passed by the first appellate court and trial

court.

The amount deposited by the appellant be transmitted

to the Executing Court.

Sd/-

JUDGE

SBN

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter