Citation : 2024 Latest Caselaw 539 Kant
Judgement Date : 8 January, 2024
1
Reserved on : 05.01.2024
Pronounced on : 08.01.2024
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 08TH DAY OF JANUARY, 2024
BEFORE
THE HON'BLE MR. JUSTICE M. NAGAPRASANNA
WRIT PETITION No.23461 OF 2023 (GM-KIADB)
BETWEEN:
JUST DIAL LIMITED
A COMPANY INCORPORATED UNDER THE
COMPANIES ACT, 1956
HAVING ITS REGISTERED OFFICE AT NO. 29
SRT STREET, CUNNINGHAM ROAD
BENGALURU - 560 052.
REPRESENTED BY ITS AUTHORIZED SIGNATORY
MR. NOORUDDIN M.,
... PETITIONER
(BY SMT. NALINI MAYEGOWDA, SENIOR ADVOCATE FOR
SRI. D.V.SHASHANK, ADVOCATE)
AND:
KARNATAKA INDUSTRIAL AREAS
DEVELOPMENT BOARD
4TH AND 5TH FLOOR, KHANIJA BHAVAN
NO. 49, RACE COURSE ROAD
BENGALURU - 560 001.
REPRESENTED BY ITS
CHIEF EXECUTIVE OFFICER AND
2
EXECUTIVE MEMBER.
... RESPONDENT
(BY SRI. B.B.PATIL, ADVOCATE FOR C/R)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND
227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THE
IMPUGNED ORDER DATED 25/09/2023 AND 11/10/2023 PASSED
BY THE RESPONDENT IN CASE NO. KIADBHO/ALLOT/
20689/12154/2023-24 PRODUCED AT ANNEXURE-A.
THIS WRIT PETITION HAVING BEEN HEARD AND RESERVED
FOR ORDERS ON 05.01.2024, COMING ON FOR PRONOUNCEMENT
THIS DAY, THE COURT MADE THE FOLLOWING:-
ORDER
The petitioner is before this Court calling in question an order
dated 25-09-2023 whereby a plot in Plot No.12-P of Hi-Tech,
Defence and Aerospace Park (IT-Sector), Bangalore Urban District
made to the petitioner is sought to be cancelled.
2. Facts, in brief, adumbrated are as follows:-
The petitioner is a company and claims to be a subsidiary of
Reliance Retail Ventures Limited and is also Information Technology
Enabled Services Company. Its main activity is providing
information (Data) services. It is engaged in the business of IT
enabled services right from its inception. The petitioner makes an
application before the respondent/Karnataka Industrial Areas
Development Board (hereinafter referred to as 'the Board' for short)
for the purpose of setting up of a development centre for its
business. An approval was granted by the State High Level
Clearance Committee to the project of the petitioner and an
allotment letter dated 26-09-2014 was issued to the petitioner
alloting 15 acres of schedule property to the petitioner on lease for
a period of 99 years. The allotment letter also detailed the
premium and the rent to be paid qua the schedule property.
3. In furtherance of the said allotment letter, a possession
certificate was granted putting the petitioner in possession of Plot
No.12 measuring 60,632.41 sq.mts. which bears description in the
schedule to the petition. It is claimed that the petitioner is in
possession of the property since 20-11-2014 uninterruptedly. A
lease agreement also comes to be executed between the parties for
a premium of `37,45,63,614/- with a fixed annual rental for a
period of 99 years.
4. It is claimed that on 14-10-2015 the petitioner enters into
a Design Consultant Appointment Agreement with one M/s Synergy
Property Development Services Private Limited for development of
the project in the schedule property and building plans were all
approved. On 09-08-2016 the petitioner also makes an application
to the BSNL for a no objection to telephone connection in the
property. When things stood thus, on 05-10-2016 the petitioner
communicates to the Board enclosing a plan and also paid building
approval fee as was necessary in law. In terms of the time limit
prescribed in the lease deed, the petitioner had to complete the
construction in the property within three years from the date of its
allotment i.e., 26-09-2014. On 06-10-2017 the petitioner
represents detailing out several hurdles faced by it and submitting
explanation as to why construction could not be carried out due to
hurdles. The petitioner requests for phase-wise development plan
vis-à-vis transport and other allied infrastructure to be carried out
by the Board so that the petitioner would begin construction.
Therefore, till 06-10-2017 no construction took place.
5. Owing to the fact that the petitioner did not complete the
construction, a notice comes to be issued to the petitioner on
12-02-2018 invoking Section 34B of the Karnataka Industrial Areas
Development Act, 1996 ('the Act' for short) for violation of the
terms and conditions of lease agreement. The notice alleged that
the petitioner has not taken any effective steps to implement the
project even after a lapse of two years. After this notice was sent,
another notice dated 23-02-2018 was sent directing the petitioner
to appear before the Chief Executive Officer and Executive Member
along with details of effective steps taken to implement the project.
The petitioner then replied to the notice on 09-03-2018 requesting
the respondent to withdraw the notice dated 12-02-2018 and
submitted detailed reasons for non-adherence to the time line qua
the construction. Another notice on 28-09-2018 comes to be
issued calling upon the petitioner to appear and produce documents
of construction activities in the allotted area. Four years after the
said notice have passed by, during which period neither,
construction takes place, nor was there any communication from
the Board.
6. On 16-07-2022 the Board sends another notice granting
time of 30 days to reply and 90 days to remedy the breach. The
petitioner submits its reply on 19-08-2022 reiterating what was
contended earlier. The petitioner is then sent a notice on 21-08-
2023 again to appear before the Authorities and the petitioner
replied to the same on 06-09-2023 seeking extension of time to
appear before the Chief Executive Officer and Executive Member
for a period of 8 weeks. The hearing on 06-09-2023 could not take
place. When the petitioner failed to show any progress, another
notice was issued on 13-09-2023 to reply within a week. The
petitioner is said to have received the notice on 13-09-2023 and
sent a reply on 21-09-2023 reiterating the request made for
deferment of all proceedings for a period of 8 weeks. When the
petitioner failed to adhere to the directions issued in any of the
notices so issued, the Board passes an order on 25-09-2023
cancelling the allotment and directing the petitioner to hand over
possession within 10 days from the date of receipt of the said
notice. It is this order that has driven the petitioner to this Court in
the subject petition.
7. Heard Smt Nalini Mayegowda, learned senior counsel
appearing for the petitioner and Sri B.B.patil, learned counsel
appearing for the respondent.
8. The learned senior counsel representing the petitioner
would vehemently contend that non-implementation or adherence
to the time line qua the construction is for the reason that there
was no infrastructure put in place including roads for entry of any
vehicle into the area. This was clearly brought out in a
representation submitted by the petitioner way back in the year
2017 that if the Board were to provide infrastructure, the
construction would be completed. It is her submission that even
today there is no proper infrastructure for the petitioner to
complete the construction. It is further submitted that the
petitioner was not heard prior to passing of the order of cancellation
of allotment and direction to hand over possession of the property.
Therefore, the learned senior counsel would submit that there has
been violation of law qua Section 34 of the Act in passing the order
contrary to the interest of the petitioner. She would seek
quashment of entire proceedings and a timeline be fixed for
providing infrastructure, so that the petitioner would adhere to the
time line fixed in the year 2014.
9. The learned counsel for the respondent Sri B.B. Patil would
vehemently contend that, on the face of it, there is violation of the
terms and conditions of the agreement. The allotment was in terms
of a contract entered into between the petitioner and Board. The
allotment is Plot No.12-P in the Bangalore IT Park measuring 15
acres which comes to about 60,632.41 sq.mts. The condition was
that any failure to implement or fulfill any condition in Clause 6 of
the contract would lead to cancellation of the agreement under
Clause 23. The petitioner has breached the conditions of the
agreement. The project had to be set up on before 19-11-2017 in
terms of the agreement. No steps have been taken by the
petitioner to implement the project and it is just holding the land as
a real estate. He would refute the submission with regard to lack of
infrastructure by placing a comparison to the adjacent lands where
projects of Amazon or logos and E-Mudra have all been fully
implemented and about 600 to 1000 employees are working in
those projects. He would submit that if Amazon and E-Mudra who
are neighbouring allottees to the petitioner can come up with
projects in the time stipulated, nothing prevented the petitioner
doing so. Therefore, he would submit that it is deliberately not
done and there is breach of agreement. He would seek dismissal of
the petition.
10. I have given my anxious consideration to the submissions
made by the respective learned counsel and have perused the
material on record.
11. The afore-narrated facts are not in dispute. The
petitioner was allotted plot No.12-P of Bangalore IT Park for setting
up of an industry for establishment of IT/ITES-BPO and software
development centre. The lease is for a period of 99 years. Clauses
6, 7 and 8 of the allotment read as follows:
".... .... ....
6. On taking possession of land, you shall adhere to the time schedule indicated in the Annexure-A.
7. Your failure to take possession of land within 30 days from the date of payment of the premium shall result in cancellation of allotment and 10% of the amount
paid towards premium and E.M.D. shall stand forfeited.
8. The Board may accept voluntary surrender of plot subject to levy of penalty at 15% of the allotment cost paid by you.
.... .... ...."
On taking possession of land, the petitioner was to adhere to the
time schedule. Failure to take possession within 30 days would
result in cancellation of allotment and payment of 10% premium.
The conditions of allotment that was appended to the letter of
allotment read as follows:
"CONDITIONS OF ALLOTMENT
The time schedule prescribed for various activities subsequent to payment of premium.
1.(a) For taking over 30 days from the date of possession of land. payment of entire premium.
(b) For execution of 30 days from the date of Lease Agreement. receipt of possession certificate
(c) For commencement Construction should be of construction and commenced within nine completion of project months from the date of taking by commencing over possession and production production should be commenced:-
i) Within a period of three years after taking over possession in case of
MSME and large industries.
ii) Within a period of five years after taking over possession in cases of mega, ultra mega and super mega projects
iii) Promoters to seek extension of time in writing by giving valid reasons to be concerned investment approving committees viz., DLSWCC/SLSWCC/SHLCC/ Allotment Committee prior to the above mentioned periods.
2. On being satisfied that the land is not put to use for the purpose for which it was allotted, the Board will be free to re-enter upon and take possession of the whole or any part of the land which has not been put to proper use.
3. If necessary, the interest in this plot of land may be offered as security in order to obtain financial assistance from the Government or Corporate bodies like Life Insurance Corporation of India, Karnataka State Financial Corporation, Karnataka State Industrial Investment & Development Corporation, Trustees for Debenture Stock or Banks. However, prior permission of the Board shall be obtained for creating second and subsequent charges on the land."
(Emphasis added)
A possession certificate was issued on 20-11-2014 in terms of the
allotment. Later comes about a lease agreement. The lease
agreement contained time limit for commencement and completion
of construction work. Clause 6 deals with time limit for
commencement and completion and Clause 7 deals with extension
of time. They read as follows:
".... .... ....
6. Time limit for commencement and completion of construction work.
(i) The Lessee shall commence civil construction works within nine months from the date of handing over possession and after obtaining licence from the Chief Inspector of Factories and Boilers in Karnataka and/or from any other Authority as required under law.
(ii) The Lessee shall complete civil construction works, erect machineries and complete the project by commencing production within a period of three years from the date of handing over possession of the Schedule Property, that is from Twentieth day of November month two thousand Fourteen in case of MSME, large and five years for mega, ultra mega and super mega projects as defined in the industrial policy from time to time after obtaining necessary licences/clearances/approvals from the concerned from time to time.
(iii) After construction of buildings, the Lessee shall not make any major modifications/alterations/additions to the existing buildings/structures except with the prior approval of the Lessor in writing.
(iv) The Lessee shall maintain the Schedule Property and the buildings erected thereon in good repairs and conditions to the satisfaction of the Lessor.
(v) The Lessee, in respect of the Schedule Property, shall observe and conform to all rules, regulations and byelaws of the local Authority concerned or any other
statutory regulations in force relating to public health and sanitation.
7. EXTENSION OF TIME
(i) The Lessee shall seek extension of time in writing by giving valid reasons to the concerned investment approving committees viz., DLSWCC/SLSWCC/SHLCC through Lessor and the investment approval committees may at its discretion extend the time for completion of civil construction works, erection of machineries and commencement of production for a further period of:
(a) One year subject to the Lessee paying penalty of 2% of allotment cost.
(b) Subsequent extension of another one year subject to the Lessee paying penalty of 5% of allotment cost.
ii) No further extension beyond two years will be allowed."
(Emphasis added)
The lessee had to complete entire project at an outer limit of nine
months and extension was only for two years. It was indicated that
extension beyond two years would not be allowed. The petitioner
did not complete the construction/project within two years. It
appears that the petitioner enters into a design consultancy service
agreement with M/s Synergy Property Development Services
Private Limited on 14-10-2015. That remained only on paper. This
led the Board to issue first notice on 12-02-2018 which reads as
follows:
"M/s Just Dial Limited, No.29, Cunningham Road, SRT Street, Bengaluru - 560 052.
Sir,
Notice Under Clause-14 of the lease-cum-sale agreement (Section34-B of the KIAD Act, 1966)
Sub: Violation of terms and conditions of lease-cum-
sale agreement dt:19/10/2015 in respect of 60632.41 Sqmtrs of land in Plot No.12-P of Hi-tech Defence and Aero Space Park(IT Sector) Bengaluru(R)District.
Ref: 1. Lease-cum-sale agreement executed by your with the Board on 19/10/2015.
2. Report dt.16/11/2017 of DO & EE, KIADB Zonal Office, Bengaluru
********
You were allotted an extent of 60632.41Sqmtrs of land in Plot No.12-P of Hi-tech Defence and Aero Space Park(IT Sector) Bengaluru Rural District for establish and industry for "IT/ITES.BPO & Software Development Center". As per the terms and conditions of the lease-cum- sale agreement executed by you with the Board on 19/10/2015, you were expected to implement the project on the plot allotted on or before 19/11/2016.
In spite of the time frame prescribed in the lease-cum-sale agreement, you have failed to implement the project and utilize the land for the purpose for which it is leased even after lapses of more than 2 years from the date of execute of lease- cum-sale agreement. The DO & EE-3, KIADB Zonal Office, Bengaluru vide report dt:16/11/2017 has reported that the plot is vacant and the allottee has
not taken any effective steps to implement the project and not submitted the building plan for approval and thereby committed, the breaches of the conditions of the lease-cum-sale agreement.
Your failure to utilize the land and establish the proposed industry is contrary to the objective of allotment as well as the objective of the KIAD Act- 1966, namely Systematic and Rapid Industrial Growth this act on your part has also resulted in deprivation of opportunity to other entrepreneurs seeking allotment of land for establishing Industry.
You have failed to utilize the land for the purposed for which it is leased. Even after the lapse of more than 2 years from the date of execution of the lease-cum-sale agreement, i.e., on 19/10/2015, Section 34-B of KIAD Act, Read with Clause-14 of the lease-cum-sale agreement stipulates that the KIADB shall be entitled to determine the lease and resume the possession of whole of the land or any part thereof for violate on of terms and conditions prescribed in the lease-cum-sale agreement executed with the Board.
In view of the above, you are called upon to remedy the specific breaches noted here within a period of 90 days from the date of issue of this notice failing which further steps will be taken to terminate the lease and resume the possession of land by the Board for Violation of terms and conditions of agreement.
Please note that if no reply is received with 30 days from the date of this notice, it will be presumed that you have no genuine reason to who cause and further action in terms of the lease-cum-sale agreement will be taken.
Yours faithfully, Sd/-
Secretary-1."
(Emphasis added)
The petitioner submits its reply that there is no proper
infrastructure and it is committed to build its software development
centre which would not only create jobs but also develop IT
software infrastructure of the State. The request in the reply was
to revoke the notice dated 12-12-2018 and grant 4 years of
extension to complete the work. Another notice was issued on
23-02-2018 which reads as follows:
"M/s Just Dail Limited, No. 29, Cunningham Road, SRT Street, Bengaluru - 560 052.
Sir,
Sub: Notice under section 34 (B) (1) of KIADB Act 1966- Violation of terms and conditions of allotment of land in respect of 60632.41 sq.mtrs. of land at Plot No.12-P of Hitech Defence and Aero Space Park (IT Sector) Bengaluru(R)District.
Ref: 1. Notice U/s 34 (B) vide No:KIADB/HO/ Allot/20689/Secy-1/17499/2017-18 Date:12- 02-2018.
*******
With reference to the notice cited under reference above, you are requested to make it convenient to appear before the Chief Executive Officer & Executive Member in his chamber at the following address on 13th April 2018 at 11.00 A.M. along with the details of the effective steps taken by you, if any, to implement the project and to utilize the
land for the purpose for which it is allotted at the following venue.
"Khanija Bhavan", East Wing, No.49, 4th Floor, Race Course Road, Bengaluru-560 001."
(Emphasis added)
The petitioner was directed to appear before the Chief Executive
Officer and divulge the details of steps taken for construction.
Though this was served, it appears the petitioner did not appear.
Four years passed by. Even if it is construed that there is tacit
acceptance of four years time by the Board, even as on today there
is no development in the plot allotted to the petitioner. This is an
admitted fact. It is then after 4 years on 16-07-2022 another notice
comes to be issued indicating that even after lapse of 7½ years no
development in the project has taken place. The notice reads as
follows:
":: NOTICE UNDER SECTION 34-B (1) OF KIAD ACT 1966::
Sub: Violation of terms and conditions of Lease Deed dtd: 19.10.2015 executed by you with the Board in respect of Plot No. 12-P measuring 60632.41 Sq mtrs. of land at Hi- tech, Defence & Aerospace Park (IT Sector), Bengaluru
Ref: 1. Lease Deed dated 19-10-2015.
2. Report did 01-06-2022 of Executive Engineer-3. KIADB Zonal Office, Bengaluru.
******
With reference to the above subject, you were allotted an extent of 60632.41 sq.mtrs land in Plot No. 12-P at Hi-tech, Defence & Aerospace Park (IT Sector), Bengaluru vide allotment letter dtd: 26-09-2014 for setting up of a unit for "IT/ITES- BPO & Software Development Centre" Possession of the said land has been handed over to you on 20.11.2014. Lease Deed has been executed on 19-10-2015 As per the clause 6(ii) of lease deed you were expected to implement the project, on or before 19-11-2017.
The Executive Engineer-3, KIADB Zonal Office, Bengaluru vide report dtd: 01.06 2022 has informed that, the plot is physically vacant
In spite of the time frame prescribed in the lease deed you have failed to take effective steps to complete the implementation of the project & utilize the land for the purpose for which it is leased even after lapse of 7 ½ years from the date of possession. It is reported that, the plot is physically vacant, project is not Implemented and thereby committed the breaches of the lease deed
Your failure to utilize the land to establish the proposed industry is contrary to the object of allotment as well as the objects of the KIAD Act, 1966, namely systematic and rapid industrial growth. This act on your part has also resulted in deprivation of opportunity to other entrepreneurs seeking allotment of land for establishing industry.
You have failed to utilize the land for the purpose for which it is leased, even after more than 7 ½ years from the date of handing over of possession. Section 34-B of KIAD Act read with Clause 23 of the lease deed stipulates that "It shall be open to the Lessor during the currency of the lease to take possession of the allotted plot together with factory and other buildings and fixtures located for any violation of any of the conditions of this deed or the
terms and conditions of allotment after following the provisions contained in the KIAD Act, 1966.
In view of the above, you are called upon the remedy the specific breaches noted herewith within a period of 90 days from the date of issue of this notice failing which further steps will be taken to terminate the lease and resume the possession of land by the Board for violation of terms and conditions of agreement.
Please note that if no reply is received within 30 days from the date of this notice, it will be presumed that you have no genuine reason to show-cause and further action in terms of the lease cum sale agreement will be taken.
Yours faithfully.
Sd/-
Joint Director"
(Emphasis added)
This was replied to by the petitioner contending that there was no
infrastructure. The reply dated 19-08-2022 reads as follows:
"19th August, 2022
The Joint Director, Karnataka Industrial Areas Development Board, #49,4th & 5th Floor, 'East Wing', Khanija Bhavan, Race Course Road, Bengaluru-560 001.
Sir,
Subject: Reply to your notice dated July 16, 2022, under Section 34-B (1) of the Karnataka Industrial Areas Development Act, 1966.
Ref: (1) Notice dated July 16, 2022, bearing No. KIADB/ HO/ Allot/ 20689/7059/2022-23.
(2) Letter addressed by Just Dial Limited to the Secretary-1, Karnataka Industrial Areas Development Board, dated March 09, 2018 & 5th October 2018.
1. As you are aware, we Just Dial Limited ("Justdial" or "the Company") are the lessee of Plot No.12-P (Non- Corner) at the Hi-Tech, Defence and Aerospace Park (IT Sector), Bengaluru ("leasehold property") vide a lease agreement dated October 19, 2015, between the Company and Karnataka Industrial Areas Development Board ("KIADB"). Be notified that the company has acquired the aforementioned leasehold property on lease for a period of 99 years commencing from October 19, 2015.
2. Be notified that our company in response to your notice dated February 12, 2018, bearing No. KIADB/HO/Allot/20689/Secy-117499/2017-18, vide a letter dated March 09, 2018, communicated its commitment to build the software development center within a period of 48 months. It was also communicated that the company's investment was predominantly considering the world-class amenities transport facilities promised by KIADB. Further, it was also communicated that the company sought for an extension of time primarily owing to the lack of transportation facilities and as such the lack of basic amenities at the Hi-Tech, Defence, and Aerospace Park. In view of the aforementioned, the company called upon your good offices to revoke the notice dated February 12, 2018, bearing No. KIADB/HO/Allot/20689/Secy-117499/2017-18 and grant the company a minimum of 48 months for completion of construction work.
3. As things stood thus, we are appalled to have received the notice dated July 16, 2022, bearing No. KIADB/ HO/ Allot/ 20689 /7059/2022-23 issued by your good office in connection to the aforementioned leasehold property. Be notified due to certain circumstances such as the
pandemic, economic slowdown, etc., as is evident for the past couple of years being faced not only by our company but by the world at large has certainly created hindrances in executing the plans as against originally committed.
4 Be notified that our company on numerous occasions Earlier vide letters dated April 13, 2016, July 11, 2016, and October 06, 2017, has communicated to your good offices the various constraints and difficulties faced by the company in the execution of the infrastructural developments at the leasehold property. Whilst, we are clear about our commitment and are working towards achieving it. It is imperative to note that we are still recovering from the aftermath of COVID-19 and recovering at a much faster pace comparatively.
5. Be notified that there is no deliberate attempt by the company to delay the project on our part except for the reasons mentioned above which are definitely not within our control despite of commitment & conviction nonetheless we hereby express our commitment & adherence to the terms of the lease agreement as executed & the communications addressed to your good office so far. Furthermore, we wish to bring to your notice that our company has now been a part of Reliance group. Given this tie-up, we definitely foresee the boost that project may have and the benefit to the overall development of IT/software centre including that of State.
6. We humbly request your good offices to accommodate us further and grant us an extension till the year 2025 without levying any penalty. This generous step from your good offices would definitely help us in and/or further strengthen us in executing our plans on the leasehold land allotted to us.
In view of the aforesaid, we pray to your good offices to revoke your notice dated 16TH July 2022 bearing No. KIADB/ HO/ Allot/ 20689 /7059/2022-23 and grant us the extension as prayed by the company.
We look forward for your kind cooperation in this regard."
(Emphasis added)
Extension was sought up to 2025 for development without
imposition of any penalty. The Board again issues a notice on
21-08-2023 for appearance. It reads as follows:
"No: KIADE/HO/Allot/20689/9638/2023-24 Date: 21.08.2023.
R.P.A.D
M/s. Just Dial Pvt. Ltd., No. 29, S.R.T. Street, Cunningham Road, Bengaluru-560 052.
Sir,
Notice Under Section 34-B(3) of KIAD Act 1966
Sub: Violation of terms & conditions of lease deed dtd 26.09.2014 and deed of rectification did 28.01.2016 in respect of 60632:41 Sq.Mtrs, of land situated in Plot No. 12-P at Hi-Tech, Delence & Aerospace Park (IT Sector), Bengaluru.
-o0o-
Please make it convenient to appear before the Chief Executive Officer & Executive Member, In his chamber on 8th September 2023 at 11.00 AM on the subject matter, along with the details of the effective steps taken by you, if any, to
implement the project and to utilize the land for the purpose for which it is allotted at the following venue.
Venue Detalls:
"Khanija Bhavan"
No.49, 4th Floor, East Wing, Race Course Road, Bengaluru-560 001.
This letter is issued with the prior approval of Chief Executive Officer & Executive Member."
The respondent submits a representation to accommodate 8 weeks
time to comply with the notice. The representation dated
07-09-2023 reads as follows:
"06th September 2023
Assistant Secretary, Karnataka Industrial Areas Development Board, #49,4th & 5th Floor, 'East Wing', Khanija Bhavan, Race Course Road, Bengaluru-560 001.
Ref: Your Notice dated 21.08.2023 bearing No. KIADB/HO/ Allot/20689/9638/2023-24.
Subject: Reply to your notice dated 21.08.2023, under Section 34-B (3) of the Karnataka Industrial Areas Development Act, 1966.
Sir,
This is with reference to your Notice under Section 34 B (3) of the Karnataka Industrial Areas Development Act, 1966 dated 21.08.2023 bearing No. KIADB/HO/ Allot/20689/9638/2023-24, wherein you have instructed us to appear before the Chief Executive Officer & Executive Member in his chamber on 08 September, 2023 at 11 am.
We would like to inform you that our officials, who were likely to attend the upcoming meeting with the CEO and Executive Officer of your good office on 8th September 2023 at 11 a.m, will, unfortunately, be unable to attend due to some personal difficulties and also that fact some of an official is currently our of the country. This situation as such makes it practically difficult for officials to prepare adequately & and present our case for the meeting.
We humbly request your good offices to accommodate us further and deferment of the upcoming meeting schedule for a period of approximately 8 (eight) weeks, to comply with your notice. The request for deferment is purely on account of reasons beyond the control of the parties and the same is neither intentional nor deliberate but for the reasons as stated above. In view of the aforesaid, we pray to your good offices to grant us the deferment as prayed by the company.
We look forward for your kind cooperation in this regard."
(Emphasis added)
Again the Board issues another notice on 13-09-2023. It reads as
follows:
"No: KIADB/HO/Allot/20689/109451/2023-24 Date: 13.09.2023
R.P.A.D
M/s. Just Dial Pvt. Ltd., No. 29, S.R.T. Street, Cunningham Road, Bengaluru 560 052.
Sir,
Notice Under Section 34-B(3) of KIAD Act 1966
Sub: Violation of terms & conditions of lease deed dtd 26.09.2014 and deed of rectification did 28.01.2016 in respect of 60632.41 Sq.Mtrs. of land situated in Plot No. 12-P at Hi-Tech, Defence & Aerospace Park (IT Sector), Bengaluru
Ref: This office letter No: KIADB/HO/Allot/ 20689/9638/2023-24, dated 21.08.2023.
-o0o-
Please make it convenient to appear before the Chief Executive Officer & Executive Member, in his chamber on 22nd September 2023 at 11.00 AM on the subject matter, along with the details of the effective steps taken by you, if any, to implement the project and to utilize the land for the purpose for which it is allotted at the following venue.
Venue Details:
"Khanija Bhavan"
No.49, 4th Floor, East Wing, Race Course Road, Bengaluru-560 001.
This letter is issued with the prior approval of Chief Executive Officer & Executive Member."
It is after receipt of these notices, it appears on 10-10-2023, a
service agreement is entered into with one M/s Maruthi Enterprises
to provide service to the plot/construction of pre-cast compound
wall, earth work excavation etc. What would unmistakably emerge
from the agreement is admission on the part of the petitioner that
for about 9 years from allotment of the plot not an inch of
development has taken place as the earth work excavation is given
only on 10-10-2023 to escape the rigour of the notice.
Photographs are produced to demonstrate that work has begun in
the year 2023 which ought to have been completed in the year
2017. The Board not acceding to the request made, went on to pass
the impugned order on 25-09-2023 which reads as follows:
"DzÉñÀ
¸ÀASÉå:PÀ.PÉÊ.¥Àæ.ªÀÄA/PÉÃA.PÀ./ºÀAaPÉ/20689/12154/2023-24, ¢£ÁAPÀ: 25.09.2023.
M/s. Just Dial Ltd., PÀA¥À¤AiÀÄÄ ºÉÊ-mÉPï, r¥sÉ£ïì & KgÉÆÃ¸ÉàÃ¸ï ¥ÁPïð (Ln ¸ÉPÀÖgï), ¨ÉAUÀ¼ÀÆgÀÄ E°è gÀÆ.445.08 PÉÆÃn §AqÀªÁ¼À ºÀÆrPÉ ªÀiÁr ¸ÀĪÀiÁgÀÄ 20991 d£ÀjUÉ GzÉÆåÃUÀ CªÀPÁ±ÀUÀ¼À£ÀÄß PÀ°à¸ÀĪÀÅzÁV w½¹ 2010£Éà ¸Á°£À°è AiÉÆÃd£É C£ÀÄªÉÆÃzÀ£É ¥ÀqÉ¢zÀÄÝ, 2014£Éà ¸Á°£À°è ¤ªÉñÀ£À ¸ÀASÉå: 12- P gÀ°è 15.00JPÀgÉ «¹ÛÃtðzÀ d«Ää£À ºÀAaPÉ ªÀÄvÀÄÛ ¸Áé¢üãÀ ¥ÀqÉ¢gÀÄvÀÛzÉ.
DzÀgÉ, ªÀÄAqÀ½AiÀÄÄ ¸Áé¢Ã£À ¥ÀvÀæ ¤Ãr ¸ÀĪÀiÁgÀÄ 8 ªÀµÀð 10 wAUÀ¼ÀÄUÀ¼ÄÀ PÀ¼É¢zÀÝgÀÆ PÀA¥À¤AiÀÄÄ d«Ää£À°è AiÉÆÃd£ÉAiÀÄ£ÀÄß C£ÀĵÁ×£ÀUÉÆ½¹gÀĪÀÅ¢®è, C£ÀĵÁ×£ÀUÉÆ½¸ÀĪÀ PÀÄjvÀÄ AiÀiÁªÀÅzÉà ¸ÀPÁgÁvÀäPÀ PÀæªÀÄUÀ¼À£ÀÄß vÉUÉzÀÄPÉÆArgÀĪÀÅ¢®è ºÁUÀÆ AiÉÆÃd£É C£ÀÄªÉÆÃzÀ£É ¥ÀqÉAiÀÄĪÀ CªÀ¢üAiÀÄ°è ¸À°è¸À¯ÁzÀ ¨sÀgÀªÀ¸ÉAiÀÄAvÉ §AqÀªÁ¼À ºÀÆrPÉAiÀÄÆ ªÀiÁrgÀĪÀÅ¢®è ªÀÄvÀÄÛ GzÉÆåÃUÀ CªÀPÁ±ÀUÀ¼À£ÀÄß ¸ÀºÀ PÀ°à¹gÀĪÀÅ¢®è.
DzÀÄzÀjAzÀ, PÉLJr PÁ¬ÄzÉ 1966gÀ PÀ®A 34-©(3) ªÀÄvÀÄÛ 34(4) gÀrAiÀÄ°è ªÀÄAqÀ½AiÀÄÄ ¥ÀævÁåAiÉÆÃf¹gÀĪÀ C¢üPÁgÀªÀ£ÀÄß ZÀ¯Á¬Ä¹, M/s. Just Dial Ltd., EªÀjUÉ ºÉÊ-mÉPï, r¥sÉ£ïì & KgÉÆÃ¸ÉàÃ¸ï ¥ÁPïð(Ln ¸ÉPÀÖgï), ¨ÉAUÀ¼ÀÆgÀÄ E°è£À ¤ªÉñÀ£À ¸ÀASÉå:12- P gÀ°è ºÀAaPÉ ªÀiÁqÀ¯ÁzÀ 60632.41 ZÀ.«ÄÃ.«¹ÛÃtðzÀ d«Ää£À ºÀAaPÉAiÀÄ£ÀÄß F ªÀÄÆ®PÀ gÀzÀÄÝUÉÆ½¸À¯ÁVzÉ.
M/s. Just Dial Ltd., PÀA¥À¤AiÀÄÄ ¤ªÉñÀ£À ¸ÀASÉå:12-P gÀ°è£À ¸Áé¢üãÀªÀ£ÄÀ ß ¢£ÁAPÀ:24.10.2023 gÉÆ¼ÀUÁV PÁAiÀÄð¥Á®PÀ C©üAiÀÄAvÀgÀgÀÄ-3, PÉLJr©, ªÀ®AiÀÄ PÀbÉÃj, ¨ÉAUÀ¼ÀÆgÀÄ EªÀjUÉ ªÀÄgÀĪÀ»¹PÉÆqÀ®Ä DzÉò¹zÉ.
MAzÀÄ ªÉÃ¼É PÀA¥À¤AiÀÄÄ ªÉÄîÌAqÀ ¤ªÉñÀ£ÀªÀ£ÀÄß ¢£ÁAPÀ:24.10.2023 gÉÆ¼ÀUÁV ªÀÄAqÀ½UÉ ªÀÄgÀ½ ¸À»¹PÉÆqÀ¢zÀÝgÉ PÉLJr PÁAiÉÄÝ 1966gÀ PÀ®A 34-©(5) gÀrAiÀİè
G¢ÝªÉÄzÁgÀgÀ C£ÀÄ¥À¹ÜwAiÀÄ°è ªÀĺÀdgï ªÀiÁr ¤ªÉñÀ£ÀzÀ ¸Áé¢üãÀªÀ£ÀÄß ªÀÄAqÀ½UÉ »A¥ÀqÉAiÀÄ®Ä PÁAiÀÄð¥Á®PÀ C©üAiÀÄAvÀgÀgÀÄ-3, PÉLJr©, ªÀ®AiÀÄ PÀbÉÃj, ¨ÉAUÀ¼ÀÆgÀÄ EªÀjUÉ ¸ÀÆa¹zÉ.
F DzÉñÀªÀ£ÀÄß ºÀAaPÉzÁgÀjUÉ £ÉÆÃAzÁ¬ÄvÀ CAZÉ ¹éPÀÈw (RPAD)ªÀÄÄSÁAvÀgÀ gÀªÁ¤¸ÀĪÀÅzÀÄ.
F DzÉñÀªÀ£ÀÄß EAzÀÄ ¢£ÁAPÀ:25.09.2023 gÀAzÀÄ ºÉÆgÀr¸À¯ÁVzÉ.
¸À»/- 25/9/23 ¢£ÁAPÀ:25.09.2023 qÁ,JA.ªÀĺÉñï, ¨sÁ.D.¸ÉÃ., ¸ÀܼÀ: ¨ÉAUÀ¼ÀÆgÀÄ. ªÀÄÄRå PÁAiÀÄð¤ªÁðºÀuÁ¢üPÁj ºÁUÀÆ PÁAiÀÄð¤ªÁðºÀPÀ ¸ÀzÀ¸ÀågÀÄ."
12. The submission of the learned senior counsel is that
orders are not reasoned. I fail to understand what reason can be
given in a case where there is blatant breach of agreement. The
photographs are appended by the petitioner and when there is
admission that it has begun to construct or excavate the earth only
on 10-10-2023 what other reason need be given to the petitioner is
ununderstandable, as it is a clear case where admitted facts and
documents would reveal that the petitioner is in breach of the
agreement not 2 years, 4 years or 6 years, but 9 years have passed
by as on today and no development in the project has taken place.
13. The submission that there is no infrastructure at all for
the petitioner for development the property is belied by the
documents produced by the respondent. The other two entities
which were allotted the land along with the petitioner were E-Mudra
Digital Campus and Amazon Logos. Photographs are appended to
the statement of objections. The plot allotted to the petitioner looks
barren with no construction and only shrubs are grown. The plot
next to the petitioner is E-Mudra which is fully developed and next
to it is Amazon Logos again fully developed. The development in
fact, in terms of photographs of the other two, is to international
standards. Therefore, the bogey that there is no infrastructure for
even vehicles to enter is a ruse to get over the order passed.
14. Reliance is placed on several judgments rendered by the
co-ordinate Bench with regard to orders passed being unreasoned.
Those are cases which are distinguishable on facts without much
ado. The case at hand depicts palpable and demonstrable breach of
agreement for not undertaking any development for close to 9
years. Therefore, no fault can be found in the action taken by the
Board.
15. In the result, the petition lacking in merit deserves to be
rejected. It is accordingly rejected.
Sd/-
JUDGE
bkp CT:SS
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!