Citation : 2023 Latest Caselaw 3447 Kant
Judgement Date : 19 June, 2023
-1-
NC: 2023:KHC:21118-DB
WA No. 180 of 2023
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 19TH DAY OF JUNE, 2023
PRESENT
THE HON'BLE MR PRASANNA B. VARALE, CHIEF JUSTICE
AND
THE HON'BLE MR JUSTICE M.G.S. KAMAL
WRIT APPEAL NO. 180 OF 2023 (GM-RES)
BETWEEN:
SRI H. SHYAMASHETTY
S/O LATE A.N. SHETTY
AGED ABOUT 63 YEARS
'PADMALEKHA', KODISASTAN ROAD
GUDNMI VILLAGE
UDUPI TALUK-576 226.
...APPELLANT
(BY SRI. HARISH KUMAR M S.,ADVOCATE)
AND:
Digitally
signed by
SUMA B N 1. M/S PROVIDENT HOUSING LTD.,
Location: REPRESENTED BY ITS AUTHORIZED SIGNATORY
High Court of HAVING REGISTERED OFFICE AT NO.8
Karnataka
ULSOOR ROAD
YELLAPPA CHITTY LAYOUT
BENGLAURU-560 042.
2. KARNATAKA REAL ESTATE REGULATION AUTHORITY
REPRESENTED BY ITS SECRETARY
2ND FLOOR, SILVER JUBILEE BLOCK
UNITY BUILDING
-2-
NC: 2023:KHC:21118-DB
WA No. 180 of 2023
CSI COMPOUND
BENGLAURU-560 027.
...RESPONDENTS
(BY SRI. JOSEPH ANTHONY, ADVOCATE FOR C/R1)
THIS WRIT APPEAL FILED UNDER SECTION 4 OF THE
KARNATAKA HIGH COURT ACT PRAYING TO ALLOW THE ABOVE
WRIT APPEAL AND SET ASIDE THE ORDER DATED: 02/01/2023
IN WP NO.18448/2021 PASSED BY THE LEARNED SINGLE
JUDGE.
THIS APPEAL COMING ON FOR PRELIMINARY HEARING,
THIS DAY, M.G.S.KAMAL J., DELIVERED THE FOLLOWING:
JUDGMENT
Present writ appeal is against the order dated
02.01.2023 passed in W.P.No.18448/2021(GM-RES) by
which the writ petition filed by the respondent no.1/writ
petitioner was allowed by learned Single Judge by setting
aside the order dated 30.9.2020 passed by the respondent
No.2-Karnataka Real Estate Regulation Authority.
2. The aforesaid writ petition was filed by the
respondent No.1/writ petitioner contending that it is in the
business of real estate development and the
NC: 2023:KHC:21118-DB WA No. 180 of 2023
appellant/respondent No.2 had filed an application for
allotment of an apartment in one of the projects of the
respondent no.1/writ petitioner and was allotted a flat
bearing No.SUN-II-5G-506 on the 5th floor of apartment
complex knows as "Provident Sunworth" constructed on
the land bearing Sy.No.1 to 26 of Venkatapura village,
Kengeri Hobli, Bengaluru. Agreements of sale and
construction both dated 10.09.2014 was entered into on
the basis of commencement certificate that was issued by
the Bangalore Development Authority. That the
construction building was completed and first partial
occupation certificate was issued by the Bangalore
Development Authority on 18.11.2015 and the second
partial occupation certificate was also issued. In the
meanwhile, the appellant /respondent No.2 sought
cancellation of the agreement on the ground that he had
learnt that land on which construction work was done, was
not acquired legally and that the respondent No.2/writ
petitioner had not obtained any communication from the
competent authority with respect to acquisition of land.
NC: 2023:KHC:21118-DB WA No. 180 of 2023
The respondent No.1/writ petitioner acceded to the
request of the appellant/respondent No.2 for cancellation
of agreements and allotment made in his favour and
refunded a sum of Rs.17,85,212/- on 04.12.2017 after
deduction of cancellation of charges and applicable taxes.
3. Long after receipt of said amount,
appellant/respondent No.2 approached the respondent
No.1/Karnataka Real Estate Regulatory Authority (RERA)
seeking refund of an amount of Rs.6,84,494/- along with
interest. Though objections with regard to maintainability
of the said complaint before respondent No.1 was raised,
the respondent No.1/RERA passed the order dated
30.09.2020 directing the respondent No.1/writ petitioner
to refund a sum of Rs.6,84,494/- to the
appellant/respondent No.2 within 60 days from
30.09.2020 failing which it was directed said amount
would carry 2% interest per month. Aggrieved by the said
order, respondent No.1/writ petitioner approached this
Court by filing said writ petition.
NC: 2023:KHC:21118-DB WA No. 180 of 2023
4. Taking note of the undisputed fact of the matter
that project had commenced and partial occupation
certificates was issued in favour of the
appellant/respondent No.2 on 18.11.2015 and 27.04.2017
and that Real Estate (Regulation and Development) Act,
2016 (hereinafter referred to as 'RERA' for short) had
come into force on and from 01.05.2016 and Rules
thereunder were notified on 10.07.2017 and that by that
time the said Act was put in force, the project was
completed and it was not an "on-going project" within the
meaning of the Act and that the respondent No.1 lacked
jurisdiction of the matter, learned Single Judge allowed the
writ petition on the sole ground of respondent No.1 is not
having jurisdiction to entertain the matter. Aggrieved by
the same, appellant/respondent No.2 is before this Court.
5. Sri. Harish Kumar M.S, learned counsel for the
appellant/respondent No.2 reiterating the grounds urged
in the memorandum of appeal contended that originally he
NC: 2023:KHC:21118-DB WA No. 180 of 2023
had approached to the District Consumer Court seeking
remedy of refund of money and on setting up of
respondent No.1 under the RERA Act, the said complaint
was returned to be presented before the respondent No.1.
Accordingly, appellant/respondent No.2 presented the
complaint before respondent No.1. That though the issue
of jurisdiction was raised, after hearing the parties,
respondent No.1 passed impugned order. Thus, he
submits that appellant/respondent No.2 would be left
remediless in view of the order passed by the learned
Single Judge warranting interference.
6. Sri. Joseph Anthony, learned counsel for the
respondent No.1/writ petitioner on the other hand,
justifying the order passed by the learned Single Judge
submitted that since the project was completed much prior
to promulgation of RERA Act and Rules, the project in
question could not have been considered as on-going
project and that the appellant/respondent No.2 being
completely aware of this factual and legal aspect of the
NC: 2023:KHC:21118-DB WA No. 180 of 2023
matter has drawn upon himself to the order impugned in
the writ petition, which has been rightly set aside.
7. Heard learned counsel for the parties and
perused the records.
8. It is not in dispute that the project in question
had been completed prior to coming into force of the Real
Estate (Regulation and Development) Act, 2016 and Rules.
As such, respondent No.2 lacked jurisdiction in the matter.
It is also not in dispute that upon the request of
appellant/respondent No.2 for cancellation of agreement
and allotment of flat, the respondent No.1/writ petitioner
had refunded a sum of Rs.17,85,212/- on 04.12.2017. It
is thereafter, the appellant/respondent No.2 approached
the District Consumer Court seeking redressal of the
grievance on the premise that he had paid Rs.24,71,208/-
and was still entitled for a balance amount of
Rs.6,84,494/-. That though the said complaint filed by the
appellant/respondent No.2 before consumer forum was
NC: 2023:KHC:21118-DB WA No. 180 of 2023
returned to be presented before respondent No.1, it was
for the appellant/respondent No.2 to have ascertained
regarding factual and legal aspect of the matter, more so,
when the issue with regard to jurisdiction was raised
before the respondent No.1 by respondent No.2/writ
petitioner. Needless to state that appellant/respondent
No.2 who opted to prosecute and proceed with the matter
before respondent No.1 knowing this legal position, cannot
now be heard to say that he is left remediless. It is for the
appellant/respondent No.2 to seek such remedy as may be
available under law.
With the above observation since the appeal lacks
merit, the same is dismissed.
Sd/-
CHIEF JUSTICE
Sd/-
JUDGE RU
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!