Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Mr Sumanth Reddy vs Jaganmayi Builders And ...
2023 Latest Caselaw 4075 Kant

Citation : 2023 Latest Caselaw 4075 Kant
Judgement Date : 6 July, 2023

Karnataka High Court
Mr Sumanth Reddy vs Jaganmayi Builders And ... on 6 July, 2023
Bench: Alok Aradhe, Anant Ramanath Hegde
                        1



IN THE HIGH COURT OF KARNATAKA AT BENGALURU
       DATED THIS THE 6TH DAY OF JULY, 2023
                    PRESENT
     THE HON'BLE MR. JUSTICE ALOK ARADHE
                       AND
THE HON'BLE MR. JUSTICE ANANT RAMANATH HEGDE
            MFA NO.7929 OF 2022 (AA)

BETWEEN:

  1. MR.SUMANTH REDDY,
     S/O MR.KUMARASWAMY REDDY,
     AGED ABOUT 44 YEARS,
     R/AT NO.S-001,
     LE PROMENADE,
     PROMENADE APARTMENTS,
     LE PROMENADE ROAD,
     FRAZAER TOWN,
     BENGALURU - 560 005.

  2. MR.SREENADHA REDDY,
     S/O MR.JANARDHANA REDDY,
     AGED ABOUT 44 YEARS,
     HAVING ITS OFFICE AT
     KAY KAY TOWERS, NO.18,
     17TH CROSS, SECTOR 7,
     HSR LAYOUT,
     BENGALURU - 560102.

  3. M/S RR PLATINA,
     A PARTNERSHIP FIRM,
     HAVING ITS REGISTERED
     OFFICE AT KAY KAY TOWERS,
     NO.18, 17TH CROSS, SECTOR-7
                           2



       HSR LAYOUT,
       BENGALURU - 560 102.

       REPRESENTED BY ITS PARTNER
       MR.SREENADHA REDDY.          ... APPELLANTS

(BY SRI D.R.RAVISHANKAR, SR.COUNSEL FOR
 SRI RAMU S., ADVOCATE)

AND:

  1. JAGANMAYI BUILDERS
     AND DEVELPERS PRIVATE LTD.,
     A COMPANY INCORPORATED
     UNDER THE PROVISIONS OF
     COMPANIES ACT, 2013,
     HAVING ITS REGISTERED OFFICE AT
     SALARPURIA WINDSOR,
     NO.3, 4TH FLOOR, ULSOOR ROAD,
     BENGALURU - 560 042.

       REPRESENTED BY ITS
       DIRECTORS ASHWIN SANCHETI.

  2. NEELANCHAL HAPPY GRIHA LLP,
     A LIMITED LIABILITY PARNERSHIP
     REGISTERED UNDER THE PROVISIONS
     OF LIMITED LIABILITY PARTNERSHIP
     ACT, 2008, HAVING ITS
     REGISTERED OFFICE AT SALARPURIA
     WINDSOR, NO.3, 4TH FLOOR,
     ULSOOR ROAD,
     BENGALURU - 560 042.

       REPRESENTED BY
       ITS AUTHORIZED SIGNATORY
       ASHWIN SANCHETI.
                           3



  3. JAGANMAYI CONSTRUCTIONS
     PRIVATE LTD., A COMPANY
     INCORPORATED UNDER THE
     PROVISIONS OF COMPANIES
     ACT, 2013, HAVING ITS
     REGISTERED OFFICE AT
     SALARPURIA WINDSOR,
     NO.3, 4TH FLOOR, ULSOOR ROAD,
     BENGALURU - 560 042.

      REPRESENTED BY ITS
      DIRECTORS ASHWIN SANCHETI.
                                       ... RESPONDENTS

(BY SRI G.L.VISHWANATH SR.COUNSEL FOR
 SRI ARUN PRADESH E, ADVOCATE FOR C/R1-R3)

      THIS MFA IS FILED UNDER SECTION 37(1)(b) OF
THE   ARBITRATION   AND    CONCILIATION    ACT,      1996,
AGAINST THE JUDGMENT AND AWARD DT.29.10.2022
PASSED IN A.A.NO.02/2022 ON THE FILE OF THE VIII
ADDITIONAL    DISTRICT     AND       SESSIONS     JUDGE,
BENGALURU     RURAL      DISTRICT,     ALLOWING       THE
ARBITRATION APPLICATION FILED UNDER SECTION 9 OF
ARBITRATION AND CONCILIATION ACT, 1996.


      THIS APPEAL HAVING BEEN HEARD AND RESERVED
FOR   JUDGMENT   ON   03.07.2023     COMING     ON    FOR
PRONOUNCEMENT OF JUDGMENT THIS DAY,               ANANT
RAMANATH HEGDE J., DELIVERED THE FOLLOWING:
                              4



                        JUDGMENT

This appeal under Section 37(1)(b) of the

Arbitration and Conciliation Act, 1996 (hereinafter referred

to as the 'Act, 1996' for short) has been filed by the

respondents in the proceeding under Section 9 of the Act.

In terms of the order dated.29.10.2022 the application is

allowed and the respondents are directed to furnish cash

security of Rs.50.00 crores along with interest @ 18% per

annum from the date of payment. The respondents have

also been restrained from alienating or creating any third-

party interest over petition properties (hereinafter referred

to as 'schedule properties') till the disposal of arbitration

proceedings.

2. The parties to the proceeding are referred to as

appellants and respondents, as per their designation

before this Court.

3. Brief facts necessary for adjudication of the case

can be summarised as under:

- the appellants and respondent No.1 entered into a

Memorandum of Understanding (MOU) on 06.10.2018 to

develop scheduled properties. Thereafter, on 04.12.2018 a

supplementary agreement was executed modifying certain

terms and conditions of the MOU.

4. On 10.10.2018 the respondents paid Rs.25.00

crores to the appellants as security deposit. Later, on

3.12.2018, respondents paid Rs.25.00 crores to the

appellants. In all Rs.50.00 crores is paid towards security

deposit. The payment of Rs.50.00 crores is not in dispute.

The appellants acknowledge the receipt of Rs.50.00 crores.

5. Alleging violation of the terms and conditions

of the MOU as well as supplementary agreement, the

respondents filed petition under Section 9 of the Act, 1996

praying some interim measures before the commencement

of the arbitral proceedings. The appellants opposed the

Section 9 petition and urged that there is no arbitration

clause and prayed for dismissal of the petition on merits.

6. It is relevant to note that in a petition filed

under Section 11 of the Act, 1996, this Court has kept

open the question of the existence of an arbitration clause

to be decided by the arbitrator.

7. After hearing the parties, the District Court

allowed the application and directed the appellants to

furnish cash security of Rs.50.00 crores along with interest

@ 18% per annum from the date of payment.

8. Aggrieved by the said order, the appellants are

in appeal.

9. Heard Sri D.R. Ravishankar, learned Senior

Counsel for the appellants and Sri G. L. Vishwanath,

learned Senior Counsel for the respondents.

10. Learned Senior Counsel appearing for the

appellants submitted that the question relating to the

maintainability of the proceeding before the arbitrator is

kept open, and that being the position, the impugned

order could not have been passed. It is urged that in view

of the supplementary agreement dated 04.12.2018, the

earlier agreement dated 06.10.2018 stands superseded in

respect of the matters contained in the supplementary

agreement, and the arbitration clause is not found in the

supplementary agreement dated 04.12.2018, as such the

dispute is not arbitrable and Court acting under Section 9

of the Act, 1996 does not have the jurisdiction to entertain

the petition.

11. The claim for payment of interest @ 18% per

annum is nothing but the claim for damages as such there

cannot be an order to furnish the security for the amount

claimed by way of damages.

12. Learned Senior Counsel appearing for the

appellants referring to Clauses No.3 and 15 of the MOU

dated 06.10.2018 urged that the MOU provided for certain

terms and conditions to be fulfilled by both parties to the

MOU. And Clause No.15 provides for termination of the

agreement only in the event of the appellants not fulfilling

the terms and conditions to the satisfaction of the

respondents. The appellants are liable to refund the entire

amount received by them along with interest @ 18% p.a.

only in the event of appellants defaulting in their

obligations under the agreement. It is further urged that

the question, who violated the terms and conditions is to

be decided by the competent forum. This being the

position, impugned order to furnish cash security for

Rs.50.00 crores and interest @ 18% per annum is

impermissible.

13. It is also urged that the Court acting under

Section 9 of Act, 1996 while passing the order to direct the

parties to the proceedings to furnish security is guided by

the provisions of Order XXXVIII of the Code of Civil

Procedure. It is contended that conditions precedent to

grant an order similar to an order XXXVIII of the Code

have not been fulfilled.

14. Alternatively, it is submitted that the appellants

are ready to deposit Rs.50.00 crores without obligation to

deposit interest on the said amount, and the same shall be

kept in a nationalized bank in an interest-earning deposit

and the amount be paid to the successful party after the

adjudication of the dispute by the competent forum.

15. Learned Senior Counsel appearing for the

respondents would submit that the order impugned is

passed taking into consideration that the appellants have

admitted the receipt of Rs.50.00 crores and the

termination clause No.15 entitles the respondents to

receive the security deposit paid by the respondents along

with interest @ 18% per annum in the event of

termination of the agreement.

16. It is further urged that the supplementary

agreement has only imposed additional obligations on the

appellants and has not diluted any of the obligations cast

on the appellants in terms of the MOU dated 6.10.2018

and the arbitration clause found in the agreement is intact

as clause No.13, of the supplementary agreement dated

04.12.2018 does not modify the arbitration clause.

17. It is further urged that the appellants have

failed to obtain the grant order from the KIADB as agreed

in the agreement dated 06.10.2018 and further without

any consent and knowledge of the respondents have

entered into an agreement for sale on 06.12.2019 in

respect of the portion of the properties covered by the

agreement dated 06.10.2018.

18. It is also submitted that the appellants created

a third-party right/charge over the portion of scheduled

properties and collected a huge amount from third parties

suppressing the MOU dated 06.10.2018 and 04.12.2018. It

is further urged that the Court under Section 9 of the Act,

1996 has ample power to pass appropriate interim orders

and is not governed by the requirements contained in

Order XXXVIII Rule 5 of the Code of Civil Procedure.

19. In support of his contention, the learned Senior

Counsel for the respondents relied upon the judgment of

the Apex Court in the case of ESSAR HOUSE PRIVATE

LIMITED vs ARCELLOR MITTAL NIPPON STEEL INDIA

LIMITED reported in 2022 LIVELAW (SC) 765.

20. It is further urged by the learned Senior

Counsel for the respondents that the order under challenge

is neither capricious nor perverse or arbitrary and there is

no scope to interfere with the impugned order.

21. This Court has considered the contentions

raised at the bar and perused the order under challenge.

22. As far as the contention relating to the scope

of the Court under Section 9 of the Act, 1996 is concerned,

the Apex Court in the case of ESSAR HOUSE PRIVATE

LIMITED supra in paragraphs No.49 & 50 has held as

under:

49. If a strong prima facie case is made out and the balance of convenience is in favour of interim relief being granted, the Court exercising power under Section 9 of the Arbitration Act should not withhold relief on the mere technicality of absence of averments, incorporating the grounds for attachment before judgment under Order 38 Rule 5 of the CPC.

50. Proof of actual attempts to deal with, remove or dispose of the property with a view to defeat or delay the realization of an impending Arbitral Award is not imperative for grant of relief under Section 9 of the Arbitration Act. A strong possibility of diminution of assets would suffice. To assess the balance of convenience, the Court is required to examine and weigh the consequences of refusal of interim relief to the applicant for interim relief in case of success in the proceedings, against the consequence of

grant of the interim relief to the opponent in case the proceedings should ultimately fail.

23. The Clause No. 13 of the supplementary

agreement prima facie indicates that terms of the MOU

dated 6.10.2018 are modified partially and other terms

and conditions of the MOU are intact. Prima facie there is

nothing on record to suggest that the arbitration clause

which is in the MOU dated 6.10.2018, is done away with in

the supplementary agreement. In the instant case,

admittedly the respondents have paid Rs.50.00 crores to

the appellants. And the appellants have acknowledged the

receipt of Rs.50.00 crores. Details of the payments are as

under:

Sl no    Cheque Date         Cheque No.                Amount
 1       10.10.2018     448108 drawn on          5,00,00,000
                        Federal Bank
 2       10.10.2018     448109 drawn on          7,50,00,000
                        Federal Bank
 3       10.10.2018     448111 drawn on          12,50,00,000
                        Federal Bank
 4       03.12.2018     878608                   25,00,00,000
                        Drawn on Vijaya Bank




24. Clause No.15 of the MOU provides for a refund

of the amount received along with the interest @ 18 % per

annum in the event of a appellants not fulfilling the terms

and conditions to the satisfaction of the respondents. From

the grounds urged in the appeal memo, it is seen that the

appellants raised the grounds on the maintainability of the

petition on the premise that there is no arbitration clause.

No specific default on the part of the respondents with

reference to their obligations in the MOU or supplementary

agreement is pointed out.

25. However, the contention of the respondents

relating to default on the part of the appellants is prima

facie made out as the appellants have not acquired

ownership over the properties mentioned in the MOU

within the time stipulated. In addition, it is also

forthcoming that appellants have also executed an

agreement for sale in favour of a third party in respect of

the portion of the properties covered under the MOU. This

being the position Clause No.15 is invoked by the

respondents and they are claiming a refund of Rs.50.00

crores along with interest as agreed under the MOU.

26. As already noticed receipt of Rs.50.00 crores is

admitted by the appellants. Prima facie no materials are

placed to counter the defaults pointed out by the

respondents. This being the position, the respondents have

raised a dispute to recover the security deposit paid by

them by invoking Clause No.15 of the MOU.

27. As an interim measure, the respondents prayed

for a restraint order against the appellants from alienating

the schedule properties and a direction to the appellants to

furnish a bank guarantee of Rs.80.60 crores.

28. The Court acting under Section 9 of the Act on

considering Clause No.15 of the MOU and on noticing the

agreement for sale dated 06.12.2019 executed by the

appellants in favour of M/s Micro Labs Limited for Rs.32.00

crores has concluded that the respondents have made out

a prima facie case for a grant of interim measure and

directed the appellants to furnish cash security to the tune

of Rs.50.00 crores along with interest @ 18% per annum.

29. Having regard to the fact that Rs.50.00 crores

are paid by the respondents and receipt of the same is

admitted by the appellants and having regard to Clause

No.15 of the MOU, the respondents are entitled to seek

refund of the security deposit, this Court is of the view that

the respondents have made out a case for a direction to

the appellants to deposit the amount paid by them.

30. As far as interest @ 18% per annum claimed

on Rs.50.00 crores from the date of payment is concerned,

this Court prima facie finds that said stipulation to pay

interest falls under Section 74 of the Indian Contract Act,

1872. It does not fall in the realm of unspecified damages.

Under these circumstances, this Court is also of the view

that a prima facie case is made out to lay a claim for

interest @ 18% per annum.

31. Having gone through the impugned order, this

Court does not find anything arbitrary, capricious or

perverse in the order directing the appellants to furnish

cash security to the tune of Rs.50.00 crores. However,

what is to be noticed is the Court directing cash security to

the tune of Rs.50.00 along with interest @ 18% per annum

further restraints the appellants from alienating,

transferring, parting with possession, and creating third

party interest over the schedule properties.

32. This Court is of the view that the further restraint

order is unjustified, after directing the appellants to furnish

cash security to the tune of Rs.50.00 crores along with

interest @ 18% per annum.

33. It is submitted that arbitration proceedings

have already commenced. Hence, taking into consideration

the scope of Section 9 in terms of the law laid down in the

case of ESSAR HOUSE supra, and the terms and

conditions of the MOU entered into between the parties,

this Court is of the view the order directing deposit

Rs.50.00 crores by the appellants is to be upheld.

34. The appellants shall furnish security of

immovable property to secure payment of interest @ 18%

per annum on Rs.50.00 crore from the date of payment till

the date of furnishing security, to the satisfaction of the

District Court.

35. The payment of Rs.50.00 crores and security

for the interest amount referred to above shall be

furnished within four weeks from today. On compliance of

the aforesaid order, the restraint order granted by the

District Court restraining alienation shall stand vacated.

36. The amount to be deposited in Court shall be

kept in Fixed deposit till the conclusion of the arbitral

proceeding and the same, along with interest shall be

disbursed in terms of the final award of the arbitrator.

37. This Court has not expressed anything on the

merits of the case. The observations made in this appeal

are only confined to the merits of Section 9 petition. All

the contentions of the parties, including maintainability of

the dispute before the arbitrator, non compliance of the

obligations of the respondents under the MOU and

supplementary agreement are kept open.

38. Hence the following,

ORDER

Impugned order dated 29.10.2022 in A.A.No.2/2022 on the file of VIII Additional District Court, Bengaluru rural is partly modified in the above said terms.

Appeal is partly allowed.

Sd/-

JUDGE

Sd/-

JUDGE BRN/GVP

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter