Citation : 2023 Latest Caselaw 1464 Kant
Judgement Date : 21 February, 2023
1
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 21ST DAY OF FEBRUARY, 2023
BEFORE
THE HON'BLE MRS. JUSTICE M G UMA
REGULAR SECOND APPEAL NO. 714 OF 2017 (SP)
BETWEEN:
SRI. A. PAPANNA
S/O LATE ANNAIAH
AGED ABOUT 72 YEARS
RE/AT HINKAL VILLAGE
MYSORE TALUK
MYSORE DISTRICT - 570 017.
... APPELLANT
(BY MR: C.M. NAGABHUSHAN, A/W
MR: ANANDA K., ADVOCATES)
AND:
SRI. D.M. PATEL
S/O M.M. PATEL
AGED ABOUT 64 YEARS
R/AT NO.10
INDUSTRIAL SUBURB
MYSURU - 570 016.
... RESPONDENT
(BY MR: CHANDRAKANTH R. GOULAY, ADVOCATE)
THIS R.S.A. IS FILED UNDER SECTION 100 OF CPC AGAINST
THE JUDGMENT AND DECREE DATED: 23.01.2017 PASSED IN
R.A.NO.579/2016 ON THE FILE OF THE II ADDITIONAL DISTRICT
JUDGE, MYSURU, ALLOWING THE APPEAL AND MODIFIYING THE
JUDGMENT AND DECREE DATED: 13.04.2016 PASSED IN
OS.NO.1024/2007 ON THE FILE OF THE I ADDITIONAL SENIOR
CIVIL JUDGE AND CJM., MYSURU.
2
THIS R.S.A. HAVING BEEN HEARD AND RESERVED FOR
JUDGMENT ON 14.11.2022 COMING ON FOR PRONOUNCEMENT OF
ORDERS THIS DAY, THE COURT DELIVERED THE FOLLOWING:
JUDGMENT
The defendant is before this Court impugning the
judgment and decree dated 23.01.2017 passed in RA No.579
of 2016 on the file of the learned II Additional District Judge,
Mysuru (hereinafter referred to as 'the First Appellate Court'
for brevity), allowing the appeal and modifying the judgment
and decree dated 13.04.2016 passed in OS No.1024 of 2007
on the file of the learned I Additional Senior Civil Judge and
CJM, at Mysuru (hereinafter referred to as 'the Trial Court' for
brevity), and decreeing the suit of the plaintiff for specific
performance of the contract directing the defendant to
execute the registered sale deed by receiving a sum of
Rs.30,00,000/-.
2. For the sake of convenience, parties are referred
to as per their status and rank before the Trial Court.
3. Brief facts of the case are that, the plaintiff filed
the suit OS No.1024 of 2007 against the defendant seeking
specific performance of the contract i.e., the agreement to sell
dated 16.08.2004. It is the contention of the plaintiff that the
defendant approached him with an intention to sell 20 guntas
of land in Sy.No.4/2B situated at Hinkal Village, Mysuru Taluk,
proclaiming that he is the absolute owner in possession of the
property. The parties have agreed for a total consideration
amount of Rs.3,20,000/-. It was agreed to pay Rs.1,75,000/-
as advance and the balance amount at the time of executing
the sale deed. The defendant undertook to hand over the
possession of the property in favour of the plaintiff at the time
of executing the sale deed and also to hand over the original
documents. Accordingly, the agreement dated 16.08.2004
was executed and the same was registered by the defendant
after accepting the part consideration amount of
Rs.1,75,000/-.
4. It is contended by the plaintiff that after execution
of the sale agreement, he came to know that the land bearing
Sy.No.4/2B is involved in litigation under Urban Land (Ceiling
and Regulation) Act, 1976 (hereinafter referred to as 'ULC
proceedings' for brevity) and major portion of the land was
not free from encumbrance. Immediately, the plaintiff
approached the defendant who promised to settle all those
disputes as he has challenged the order passed by the Deputy
Commissioner, Mysuru before the High Court in Writ Petition
No.31306 of 2003. The defendant also promised to complete
the sale transaction as agreed and to hand over the
possession of the property immediately after disposal of the
writ petition and getting Sy.No.4/2B mutated in his name.
Accordingly, ULC proceedings ended in favour of the
defendant and his name was mutated in the revenue records
in respect of Sy.No.4/2B measuring 1.20 acres of Hinkal
Village.
5. It is contended that the defendant demanded the
balance consideration amount of Rs.1,45,000/- towards
litigation expenses and assured to execute the registered sale
deed by delivering the possession of the property.
Accordingly, the plaintiff paid the balance consideration
amount. Therefore, it is contended that the entire sale
consideration was paid by the plaintiff to the defendant. In
spite of that, the defendant was not ready and willing to
perform his part of the contract. The plaintiff issued the legal
notice, calling upon the defendant to perform his part of the
contract and to execute the sale deed as undertaken. The
defendant has neither replied nor complied with the demand
made by the plaintiff.
6. It is stated that the defendant had sent a legal
notice to the plaintiff on 28.03.2007 through his advocate
contending that he had executed the agreement for sale
dated 16.08.2004 in favour of the plaintiff and had received
Rs.1,75,000/- towards part sale consideration. It is contended
that the balance amount at the rate of Rs.1,000/- per square
feet is due and the time is the essence of the contract. It is
also stated in the notice that since the plaintiff was not ready
and willing to perform his part of the contract, the defendant
revoked the agreement of sale. The defendant knowing fully
well about the agreement dated 16.08.2004 and receipt of the
balance consideration amount, suppressed the same and
taken up a new contention.
7. It is also contended that the defendant even
though received the entire consideration amount of
Rs.3,20,000/- falsely claiming that the plaintiff is due in a
sum of Rs.1,45,000/-. The plaintiff in order to avoid the
controversy was ready to make the payment once again. It is
stated that the cause of action for the suit arose on
16.08.2004, when the agreement of sale is executed and
when the balance consideration amount is paid. Therefore,
prayed for a decree for specific performance of the agreement
to sell by accepting the balance consideration of
Rs.1,45,000/-.
8. The defendant appeared before the Trial Court
and filed the written statement denying the contention taken
by the plaintiff. Execution of the agreement dated
16.08.2004 and paying of the advance of Rs.1,75,000/- are
all denied. On the other hand, it is contended that the
plaintiff being a business man with an intention to acquire the
property had orally entered into a gentleman agreement with
the defendant agreeing for the sale consideration amount of
Rs.1,75,00,000/-, but to avoid income tax, to save the stamp
duty and registration charges, the consideration amount was
shown less. The defendant agreed for the same. It is
contended that time was the essence of the contract.
9. It is further contended that the plaintiff has
already filed another suit against the defendant in OS No.868
of 2007 seeking similar relief of specific performance of the
contract. Since the parties and the relief claimed in both the
suits are one and the same, it is contended that the suit is not
maintainable. The defendant contended that he entered into
the agreement for sale with the plaintiff in respect of the land
bearing Sy.No.4/2B measuring 20 guntas situated at Hinkal
Village with the boundaries mentioned therein. It was
mutually agreed that the sale consideration for the above said
property is Rs.1.75 crores, if the defendant gets quashed the
notification made under ULC Act in Writ Petition No.31306 of
2003 filed before this Court. The said writ petition came to be
disposed of on 28.06.2005. The agreement referred to by the
plaintiff was entered into only to produce before the
Department of Income tax and such other authority and to
save the stamp duty. Separate sale agreement has been
executed agreeing to pay the sale consideration of
Rs.30,00,000/- which was meant to be shown to the lenders
of the plaintiff. Taking advantage of these two agreements,
the plaintiff is seeking specific performance of the contract
under both the agreements, which is unsustainable in law.
10. It is contended that the plaintiff has filed OS
No.1025 of 2007 against the defendant seeking specific
performance of the agreement dated 28.07.2004. The
agreement dated 28.07.2004 and 16.08.2004 are one and the
same and are in respect of the same property. The
agreement dated 16.08.2004 is a registered agreement,
whereas agreement dated 28.07.2004 is an unregistered
agreement. Therefore, it is contended that the plaintiff is not
entitled for the relief of specific performance of the contract.
Accordingly, he prays for dismissal of the suit.
11. The plaintiff got amended the southern and
northern boundary of the schedule property by deleting the
earlier boundary shown as South: A Papanna's Land and
North:Sy.No.6, amended it as North: A Papanna's land and
South : Sy.No.6. An additional written statement came to be
filed after amendment of the plaint and contended that the
amendment was an afterthought and therefore, prayed for
dismissal of the suit.
12. Plaintiff filed rejoinder contending that the earlier
suit filed for specific performance of the contract came to be
decreed and the defendant has preferred RA No.143 of 2011
which was remanded for fresh disposal. It is contended that
the defendant is trying to make out a new case by filing
amended written statement and the same is liable to be
dismissed. The contention taken by the defendant that the
parties have entered into gentleman agreement to pay sale
consideration of Rs.1.75 crores to avoid income tax, stamp
duty etc., are all denied. It is contended that the defendant
deliberately suppressed the fact that there was litigation
pending with regard to ULC proceedings. The defence taken
by the defendant that OS No.868 of 2007 was filed in respect
of the same property is also denied. It is contended that the
plaintiff and the defendant mutually agreed under two
different agreement for purchase of two different properties,
measuring 20 guntas each, with different boundaries.
Therefore, it is stated that the contention taken in the written
statement are all false and untenable. It is also stated that
agreement dated 28.07.2004 and 16.08.2004 are quite
different in respect of two distinct properties and therefore,
prayed for decreeing the suit.
13. On the basis of these pleadings, the Trial Court
framed the following issues and additional issue for
consideration:
(1) ªÁ¢AiÀÄÄ zÁªÁ D¹ÛAiÀÄ£ÀÄß ¥ÀæwªÁ¢AiÀÄÄ 3,20,000.00 gÀÆ.UÀ½UÉ ªÀiÁgÁl ªÀiÁqÀ®Ä M¦àzÀgÀÄ. PÀæAiÀÄzÀ PÀgÁgÀÄ §gÉzÀÄPÉÆnÖzÁÝgÉ. 1 ®PÀëzÀ 75 ¸Á«gÀ gÀÆ.UÀ¼À£ÀÄß ªÀÄÄAUÀqÀªÁV ¥ÀqÉ¢zÁÝgÉ. PÀæAiÀÄzÀ PÀgÁgÀÄ §gÉzÀÄPÉÆnÖzÁÝgÉ. PÀæAiÀÄ ¥ÀvÀæ §gÉzÀÄ £ÉÆÃAzÁ¬Ä¹PÉÆqÀĪÀAvÉ MvÁ۬ĹzÀÝgÀÆ ¤gÁPÀj¹zÁÝgÉ JA§ÄzÁV gÀÄdĪÁvÀÄ ªÀiÁqÀÄvÁÛ£ÉAiÉÄÃ?
(2) vÀ£Àß ¥Á°£À PÀgÁj£À°è£À PÀvÀðªÀåªÀ£ÀÄß AiÀiÁªÁUÀ®Æ ¤ªÀð»¸À®Ä ¹zÀÞ¤gÀĪÀÅzÁV gÀÄdĪÁvÀÄ ªÀiÁqÀÄvÁÛ£ÉAiÉÄÃ?
(3) ¥ÀæwªÁ¢AiÀÄÄ ªÀiÁgÁl ªÀiÁqÀ®Ä M¦àgÀĪÀ zÁªÁ D¹Û £ÀUÀgÀ ¨sÀÆ«Äw PÁAiÉÄÝ C£ÀéAiÀÄ «ªÁzÀzÀ°è EvÀÄÛ. CzÀ£ÀÄß DvÀ£ÀÄ ªÀÄgɪÀiÁazÁÝ£É JA§ÄzÁV ªÀÄvÀÄÛ CzÀÄ wêÀiÁð£ÀªÁzÀ £ÀAvÀgÀ PÀæAiÀÄ¥ÀvÀæ §gÉzÀÄPÉÆnÖ®è JA§ÄzÁV ªÁ¢ gÀÄdĪÁvÀÄ ªÀiÁqÀÄvÁÛ£ÉAiÉÄÃ?
(4) ¥ÀæwªÁ¢AiÀÄÄ vÁ£ÀÄ zÁªÁ D¹ÛAiÀÄ£ÀÄß ªÁ¢UÉ ªÀiÁgÁl ªÀiÁqÀ®Ä M¦à PÀæAiÀÄzÀ PÀgÁgÀÄ §gÉzÀÄPÉÆnÖgÀĪÀÅzÁVzÉ. DzÀgÉ PÀæAiÀÄzÀ ªÉÆvÀÛ 1 PÉÆÃn 75 ®PÀë gÀÆ.UÀ¼ÁVzÉ. ªÁ¢AiÀÄÄ ªÀåªÀºÁgÀ¸ÀÜ£ÁVzÀÄÝ ¸ÁÖöåA¥ï qÀÆånAiÀÄ£ÀÄß ªÀgÀªÀiÁ£À vÉjUÉ G½¸À®Ä ªÀÄvÀÄÛ £ÉÆÃAzÁªÀt ±ÀĮ̪À£ÀÄß PÀrªÉÄ ªÀiÁrPÉÆ¼Àî®Ä £ÁªÀÄPÁªÀ¸ÉÜUÁV MAzÀÄ PÀgÁgÀ£ÀÄß §gɹPÉÆArgÀÄvÁÛ£É ªÀÄvÀÄÛ vÁ£ÀÄ D¹ÛAiÀÄ ¸ÀA§AzsÀzÀ J¯Áè «ZÁgÀUÀ¼À£ÀÄß DvÀ¤UÉ w½¹zÀÄÝ DvÀ£ÀÄ CzÀ£ÀÄß ¥Àj²Ã°¹ MAzÀÄ wAUÀ¼ÉƼÀUÁV D¹ÛAiÀÄ£ÀÄß Rjâ¸À®Ä M¦à PÀæAiÀÄzÀ PÀgÁgÀÄ ªÀiÁrPÉÆArzÁÝ£É. DzÀgÉ M¥ÀàAzÀzÀAvÉ MAzÀÄ wAUÀ¼ÉƼÀUÁV PÀæAiÀÄzÀ ¨ÁQ ºÀtªÀ£À£ÀÄß ¥ÁªÀw ªÀiÁr®è, vÀ£Àß ¥Á°£À PÀgÁj£À PÀvÀðªÀåªÀ£ÀÄß ¤ªÀð»¸À®Ä
AiÀiÁªÁUÀ®Æ ¹zÀݤ®è. ¸ÀªÀÄAiÀĪÉà PÀgÁj£À ªÀÄÄRå CA±À (time is
essence of contract) JA§ÄzÁV gÀÄdĪÁvÀÄ ªÀiÁqÀÄvÁÛ£ÉAiÉÄÃ?
(5) zÁªÁªÀ£ÀÄß ªÀi˰åÃPÀj¹gÀĪÀÅzÀÄ, £ÁåAiÀiÁ®AiÀÄPÉÌ ±ÀÄ®Ì ¥ÁªÀw ªÀiÁrgÀĪÀÅzÀÄ ¸Àj¬Ä®è. ªÀiÁgÀÄPÀmÉÖ ¨É¯ÉAiÀÄ ªÉÄÃ¯É zÁªÁªÀ£ÀÄß ªÀi˰åÃPÀj¸À¨ÉÃPÁVvÀÄÛ JAzÀÄ ¥ÀæwªÁ¢AiÀÄÄ gÀÄdĪÁvÀÄ ªÀiÁqÀÄvÁÛ£ÉAiÉÄÃ?
(6) ¤¢üðµÀÖ ¥Á®£ÉUÁV rQæ ªÀiÁrzÀ°è CxÀªÁ ªÀiÁqÀzÉà EzÀݰè AiÀiÁªÀ ¥ÀPÀëUÁgÀ¤UÉ ºÉaÑ£À ºÁ¤ GAmÁUÀÄvÀÛzÉ? ¥ÀPÀëUÁgÀgÀÄ AiÀiÁªÀ ¥ÀjºÁgÀ ºÉÆAzÀ®Ä CºÀðgÀÄ?"
Additional issue:
"Whether the defendant proves that, the suit schedule property covered under agreement of sale dated 16.08.2004 and property covered under agreement of sale dated 28.07.2004 are one and the same, as contended in para 14(b) of the amended written statement?"
14. The plaintiff examined himself as PW1 and got
marked Exs.P1 to P10 in support of his contention. The
defendant examined himself as DW1 and examined DWs.2
and 3 and got marked Exs.D1 to 17 in support of his defence.
The Trial Court after taking into consideration all these
materials on record, answered issue Nos.1, 3 and 4 partly in
the Affirmative and issue Nos.2 and 5 and additional issue
No.1 in the Negative, accordingly, decreed the suit of the
plaintiff in part. The prayer for specific performance of the
contract was rejected. The defendant was directed to repay
Rs.1,75,000/- paid under the agreement - Ex.P.1, with
interest at 12% p.a. from the date of agreement till the date
of realization.
15. Being aggrieved by the same, the plaintiff has
preferred RA No.579 of 2016. The First Appellate Court on re-
appreciation of the materials on record, allowed the appeal
with costs and decreed the suit for specific performance of the
contract directing the plaintiff to pay additional sum of
Rs.30,00,000/- to the defendant. Being aggrieved by the
same, the defendant is before this Court.
16. Heard Sri C M Nagabhushan and Sri K Ananda,
learned counsel for the appellant and Sri Chandrakanth R
Goulay, learned counsel for the respondent. Perused the
materials on record including the Trial Court records.
17. Learned counsel for the appellant contended that
the plaintiff has filed OS No.1025 of 2007 before the Trial
Court in respect of similar agreement dated 28.07.2004,
alleging that the defendant had agreed to sell the schedule
property and therefore sought for specific performance of the
contract. The said suit was partly allowed directing the
defendant to pay Rs.30,00,000/-. But the prayer of the
plaintiff for specific performance of the contract was rejected.
The said judgment directing payment of the amount was
challenged by the defendant by preferring the first appeal
before this Court, which is still pending for consideration.
However, the co-ordinate Bench of this Court directed the
defendant to deposit 50% of the amount and accordingly, the
amount was deposited. The plaintiff had withdrawn the said
amount. The plaintiff had never challenged the judgment
refusing specific performance of the contract i.e., the
agreement dated 28.07.2004. On the other hand, he
accepted the judgment by withdrawing the amount that was
deposited by the defendant.
18. Learned counsel further submitted that the plaintiff
contended that similar agreement was also entered into
between the parties on 16.08.2004 and filed the present suit
seeking specific performance of the contract. There is no
explanation as to why two different agreements for sale were
entered into in respect of the same property. There is also no
explanation as to why the second suit for specific performance
of the contract was filed by the plaintiff when his first suit is
already partly decreed and specific performance of contract
was refused. Learned counsel further submitted that the Trial
Court and the First Appellate Court recorded a concurrent
finding that the subject matter of the agreements dated
28.07.2004 and 16.08.2004 are one and the same. The
plaintiff had never challenged such finding recorded by the
Trial Court and the First Appellate Court and thereby accepted
the said finding. Under such circumstances, the present suit
for specific performance of the contract in respect of the same
property, is not maintainable.
19. Learned counsel further submitted that even
according to the plaintiff, the time fixed for performance of
the contract is two months from 16.08.2004. The sale
consideration is said to be Rs.3,20,000/- and the plaintiff
contended that the entire amount of consideration is already
paid. However, during cross examination he admits that he
has not paid the entire consideration amount, but some
amount is due to be paid to the defendant. This shows the
conduct of the plaintiff who seeks specific performance of the
contract.
20. Learned counsel also submitted that the plaintiff
issued the legal notice as per Ex.P2 on 12.03.2007 i.e., after
lapse of more than 2½ years after entering into the
agreement in question. The said notice was never served on
the defendant. The defendant issued the notice as per Ex.P6
on 28.03.2007 repudiating the contract as the plaintiff was
not ready and willing to perform his part of the contract. In
spite of that, the plaintiff has not stated anything in the plaint
regarding his readiness and willingness to perform his part of
the contract, thereby, he has not complied with the
requirements of Section 16(c) of the Specific Relief Act.
21. It is further contended that the second agreement
dated 16.08.2004 is a sham document and it is unenforceable
in law. It is stated that the first agreement for sale is dated
28.07.2004. The total consideration agreed to be paid was
Rs.30,00,000/-, but under the second agreed dated
16.08.2004 the consideration agreed is only Rs.3,20,000/-.
There is absolutely no explanation for this disparity in the
amount agreed to be paid as consideration. Even according to
the plaintiff, the consideration agreed under Ex.P2 is
inadequate which is a valid reason to deny specific
performance of the contract as per Explanation-2 of Section
25 of the Contract Act. The Trial Court on proper appreciation
of the materials on record, rejected the prayer of the plaintiff
for specific performance of the contract. However, the First
Appellate Court without proper appreciation of the materials
on record, decreed the suit of the plaintiff. The finding
recorded by the First Appellate Court that the plaintiff was not
aware of ULC proceedings, is erroneous.
22. Learned counsel further stated that the plaintiff had
filed an application before the First Appellate Court seeking
permission to amend the plaint by inserting a paragraph to
plead his readiness and willingness to perform the contract.
The said application came to be rejected by the First Appellate
Court, but however decreed the suit of the plaintiff without
there being any pleading regarding readiness and willingness
to perform the contract.
23. Learned counsel contended that Ex.P1 is a
registered document and Ex.P4 is an unregistered document.
Ex.P4 is already enforced by the plaintiff by filing a suit for
specific performance of the contract. The Trial Court rejected
the claim for specific performance of the contract and ordered
for refund of the amount already paid. Under such
circumstances, the plaintiff cannot now seek for enforcement
of Ex.P1, solely on the ground that it is a registered
document. Learned counsel drawn the attention of this Court
to Ex.P2 to contend that the plaintiff issued the legal notice
demanding specific performance of the contract, alternatively
claimed huge sum of Rs.20,55,000/- with interest at 18% p.a.
There is absolutely no basis for claiming such a huge amount
when the consideration amount itself is only Rs.3,20,000/-
and he paid an amount of Rs.1,75,000/- as advance. This
shows the conduct of the plaintiff to take advantage of the
situation.
24. It is also contended that the First Appellate Court
referred to the financial capacity of the plaintiff by referring to
the withdrawal of the amount deposited by the defendant on
24.04.2013, but it had not taken into consideration the fact
that no materials are placed before the Court to determine the
financial capacity of the plaintiff from 2004 till 2007. He
placed reliance on the decisions in Ravi Setia Vs. Madan lal
and others1 and U.N. Krishna Murthy (since deceased
through Lr's) Vs. A.M.Krishnamurthy2 in support of his
contentions. Therefore, the impugned judgment and decree
passed by the First Appellate Court was perverse, erroneous
and calls for interference by this Court. Hence, he prays for
allowing the appeal.
25. Per contra, learned counsel for the respondent
submitted that the plaintiff has proved execution of Ex.P1 -
the agreement for sale dated 16.08.2004. It is a registered
agreement for sale. The First Appellate Court never held that
the subject matter of the agreement dated 28.07.2004 and
the schedule property are one and the same. On the other
hand, the finding on additional issue No.1 recorded by the
First Appellate Court disclose that both the properties are
different. Learned counsel further submitted that Ex.P1 -
agreement is dated 16.08.2004 and before expiry of the
period of limitation, the legal notice as per Ex.P2 was issued
(2019) 9 SCC 381
AIR 2022 SC 3361
on 12.03.2007. There was no reply by the defendant.
However, a notice as per Ex.P6 was issued terminating the
agreement in question. The defendant himself had filed an
application seeking appointment of a Commissioner for
identification of the schedule property. The same came to be
rejected by the Trial Court. The defendant had filed writ
petition challenging the order of the Trial Court, but the writ
petition also came to be dismissed.
26. Learned counsel further contended that normally
the time is not considered as the essence of the contract. The
First Appellate Court assigned valid reasons to hold that the
plaintiff was ever ready and willing to perform his part of the
contract. The conduct of the defendant from the date of
agreement was also considered by the First Appellate Court in
decreeing the suit of the plaintiff. Learned counsel further
submitted that the defendant has consciously entered into
Ex.P1 with the plaintiff. There is absolutely no reason as to
why the agreement is to be ignored. The First Appellate Court
on re-appreciation of the materials on record arrived at a right
conclusion. There is no perversity or illegality in the
impugned judgment and decree. Since there is no merits in
the appeal, the same is liable to be dismissed. Accordingly, he
prays for dismissal of the appeal with costs.
27. The appeal was admitted vide order dated
01.12.2021 and the following substantial questions of law
were formulated:
"1) Whether the first appellate court was justified in decreeing the suit in the absence of necessary pleadings with regard to readiness and willingness of the plaintiff to perform his part of the contract and having regard to Section 16(c) of the Specific relief Act?
2) whether the judgment and decree
passed by the first appellate court is in
compliance of the requirements of Order 41 Rule 3 of CPC?"
28. This Court vide order dated 31.10.2022 has
formulated the following additional substantial question of
law:
"Whether the First Appellate Court was justified in allowing the appeal and decreeing the suit of the plaintiff by answering point No.2 in favour of the plaintiff, when a categorical finding
on point No.1 is recorded and answered it in favour of the defendant?"
29. It is the specific contention of the plaintiff that the
defendant had executed the agreement for sale dated
16.08.2004 agreeing to sell 20 guntas of land bearing Survey
No.4/2B situated at Elkal village Mysuru taluk for a total
consideration of Rs.3,20,000/-. An amount of Rs.1,75,000/-
was paid in advance and it was agreed that the balance
consideration amount would be paid at the time of registration
of the sale deed. The agreement was registered. It was also
contended that when the plaintiff approached the defendant
about the ULC proceedings which was pending in respect of
the schedule property, he promised to settle it and demanded
for the balance consideration amount. Accordingly, the
plaintiff paid balance amount of Rs.1,45,000/-. Since the
defendant was not ready to execute the sale deed, the legal
notice came to be issued. In the meantime, the defendant
also issued a notice terminating the agreement, contending
that, time is the essence of contract and the plaintiff is not
willing and ready to perform his part of the contract and
therefore, the agreement was revoked. Thus, it is the
contention of the plaintiff that even though, he was ready and
willing to perform his part of the contract, the defendant was
not ready to execute the sale deed and therefore, sought for
specific performance of the contract.
30. On going through the pleadings of the plaintiff
before the Trial Court, it is clear the plaintiff has not
specifically averred that he was ready and willing to perform
his part of the contract. On the other hand, he contended
that entire consideration of Rs.3,20,000/- was already paid
and nothing is due to be paid. However, it is stated that the
plaintiff to avoid controversy is ready to make payment of
Rs.1,45,000/- for the second time. With these pleadings, the
parties went to adduce the evidence before the Trial Court.
During cross examination of PW1, he categorically admitted
that the entire amount of consideration was not paid by him.
This admission of the plaintiff assumes importance in view of
Section 16(c) of the Specific Relief Act. When the plaintiff fails
to prove his readiness and willingness to perform his part of
the contract, he will not be entitled for specific performance of
the contract.
31. It is pertinent to note that when the defendant
challenged the impugned judgment and decree passed by the
Trial Court before the First Appellate Court, the plaintiff had
filed an application seeking permission to amend the
pleadings i.e., to insert a paragraph regarding his readiness
and willingness to perform the contract. The said application
was accompanied by an affidavit sworn by the plaintiff,
wherein he had categorically stated that he could not plead
readiness and willingness in the plaint as the same was
omitted by mistake. Therefore, it is clear that even the
plaintiff admitted that there is no pleading regarding his
readiness and willingness to perform his part of the contract,
in the plaint. The conduct of the plaintiff in contending that
he had already paid the entire balance consideration amount,
but admitting during cross examination that he had not paid
the entire balance consideration amount and some amount is
due from him to be paid to the defendant also assumes
importance while deciding the readiness and willingness of the
plaintiff to perform the contract.
32. The Hon'ble Apex Court in Katta Sujatha Reddy
and another Vs Siddamsetty Infra Projects Private
Limited and Others3, considered the question regarding the
readiness and willingness to perform the contract and held in
paras 66 and 67, which reads as under:
"66. The next aspect which this Court needs to consider is whether the parties had requisite willingness and readiness to perform the contract. The aforesaid requirement is one of the essential ingredients under Section 16 of the Specific Relief Act, 1963 which reads as under:
"16. Personal Bars to relief.-Specific Performance of a contract cannot be enforced in favour of a person-
(c) who fails to aver and prove that he has performed or has always been ready and willing to perform the essential terms of the contract which c are to be performed by him, other than terms the performance of which has been prevented or waived by the defendant."
67. It is clear that in order to prove readiness and willingness, the burden is on the purchaser to prove that they were always ready
(2023) 1 SCC 355
and it is only the vendor who refused to perform the contract for extraneous considerations."
33. The Hon'ble Apex Court in U.N Krishnamurthy
(supra), considered the requirement of pleading and proving
the readiness and willingness on the part of the plaintiff to
perform his part of the contract and considering its various
decisions rendered earlier, held in paras 25 and 30 as under:
"25. To aver and prove readiness and willingness to perform an obligation to pay money, in terms of a contract, the plaintiff would have to make specific statements in the plaint and adduce evidence to show availability of funds to make payment in terms of the contract in time. In other words, the plaintiff would have to plead that the plaintiff had sufficient funds or was in a position to raise funds in time to discharge his obligation under the contract. If the plaintiff does not have sufficient funds with him to discharge his obligations in terms of a contract, which requires payment of money, the plaintiff would have to specifically plead how the funds would be available to him. To cite an example, the plaintiff may aver and prove, by adducing evidence, an arrangement with a financier for disbursement of adequate funds for timely compliance with the
terms and conditions of a contract involving payment of money.
30. This Court, in effect, held that for determining whether the Plaintiff was ready and willing to perform his part of the agreement it is necessary for the Court to consider the conduct of the Plaintiff prior and subsequent to filing the suit for specific performance. The relevant part of the judgment is extracted hereinbelow:-
"5. ...Section 16(c) of the Act envisages that plaintiff must plead and prove that he had performed or has always been ready and willing to perform the essential terms of the contract which are to be performed by him, other than those terms the performance of which has been prevented or waived by the defendant. The continuous readiness and willingness on the part of the plaintiff is a condition precedent to grant the relief of specific performance. This circumstance is material and relevant and is required to be considered by the court while granting or refusing to grant the relief..."
34. Thus, the position of law is very well settled that
the plaintiff has to plead and prove his readiness and
willingness to seek the decree for specific performance of the
contract, which is lacking in the present case. When the
plaintiff admits that he had not paid the entire consideration
amount and also admits that there was no pleading in the
plaint regarding his readiness and willingness to perform his
part of the contract, the plaintiff is not entitled for grant of
specific performance of the contract.
35. Admittedly, there were two agreements entered
into between the plaintiff and defendant, wherein, the
defendant had agreed to sell the specified property in favour
of the plaintiff. The suit agreement is dated 16.08.2004
whereas the other agreement is dated 28.07.2004.
Admittedly, the plaintiff filed suit OS No.1025 of 2007 seeking
specific performance of the contract in respect of the
agreement dated 28.07.2004. The said suit came to be
decreed in-part directing the defendant to refund an amount
of Rs.30,00,000/-, but refused to grant specific performance
of the contract. The said judgment was not challenged by the
plaintiff. The defendant challenged it. While granting stay of
the impugned judgment and decree passed by the Trial Court,
the First Appellate Court directed the defendant to deposit
50% of the amount and accordingly, the defendant deposited
the amount. It is not in dispute that the plaintiff had
withdrawn the said amount of 50% of the decreetal amount.
36. In the meantime, the plaintiff filed the present suit
seeking specific performance of the contract dated
16.08.2004. The description of the schedule property in both
the suits are identical except in stating the western boundary.
In OS No.1025 of 2007, the western boundary is mentioned
as ring road and in the present case it is mentioned as road.
The plaintiff during cross examination specifically stated that
the schedule property in the present case is abutting the ring
road and also admits its boundaries. The First Appellate Court
framed the specific point for consideration as to whether the
schedule property in OS No.1024 of 2007 was identical with
the schedule property in OS No.1025 of 2007 and recorded a
categorical finding that the properties are identical. The
plaintiff accepted this finding and has never challenged the
same.
37. Now, I have to consider what is the effect of the
finding of First Appellate Court that the schedule properties in
both the suits are identical. When there are two agreements
in respect of the same property i.e., one dated 28.07.2004
and the other one dated 16.08.2004, the plaintiff has to
choose as to which of the agreement he would chose to seek
specific performance of the contract from the defendant. The
agreement dated 16.08.2004 which is referred to in this suit
is a registered agreement, but the fact remains that the
plaintiff has already enforced the agreement dated
28.07.2004 and obtained a decree for refund of an amount of
Rs.30,00,000/-. The said judgment was never challenged by
the plaintiff. When the defendant deposited 50% of the
decreetal amount before the Court as per the directions of the
First Appellate Court, the plaintiff has chosen to withdraw the
said amount and thereby accepted the judgment rejecting the
claim for specific performance of the contract and decreeing
the suit for only refund of the amount.
38. Now, the question arises as to whether the
plaintiff can enforce the agreement dated 16.08.2004 after
enforcing the agreement dated 28.07.2004 in respect of the
same property. Naturally, the answer will be in the Negative.
The First Appellate Court held that there is no bar for entering
any number of agreements in respect of a property between
the parties, but that does not mean to say that the plaintiff
can enforce all such agreements. The plaintiff has to chose
between the agreements to seek enforcement of the contract.
Under such circumstances, the plaintiff now cannot contend
that these two agreements are separate and distinct relating
to different properties. He also cannot maintain the suit for
enforcing the second agreement, after enforcing the first
agreement in respect of the same property. When the plaintiff
has not chosen to challenge the decree passed in OS No.1025
of 2007 refusing to grant specific performance of the contract,
he cannot contend that he is entitled for the decree for
specific performance of the contract in the present suit.
39. The agreement dated 16.08.2004 was entered into
between the plaintiff and defendant in respect of the schedule
property for a total consideration Rs.3,20,000/- and the
defendant accepted advance amount of Rs.1,75,000/-. It was
agreed between the parties that the balance amount is to be
paid by the plaintiff and the defendant has to execute the
same within two months from the date of agreement. But the
plaintiff got issued the notice as per Ex.P2, calling upon the
defendant to execute the sale deed only on 12.03.2007, which
was also not served on the defendant. In the meantime, the
defendant issued notice as per Ex.P6, repudiating the contract
on the ground that the plaintiff was not ready and willing to
perform his part of the contract. It is only thereafter the
plaintiff has filed the present suit on 19.06.2007.
40. As per Section 55 of the Contract Act, when a
party to the contract promises to do a certain thing at or
before a specified time, and if he fails to do so at or before
the specified time, the contract become voidable at the option
of the promisee when the intention of the parties was that,
the time is the essence of the contract. In the present case,
both the parties entered into an agreement fixing the time for
performance of the contract as two months from the date of
contract. The plaintiff kept quite for about three years to seek
specific performance of the contract from the defendant and
had filed the suit just about two months earlier to the expiry
to the period of limitation.
41. The First Appellate Court even after recording its
categorical finding that the subject matter of the suit OS
No.1024 of 2007 was identical with the suit property in OS
No.1025 of 2007, proceeded to decree the suit of the plaintiff
without any basis. As already discussed above, the finding of
the First Appellate Court that the parties are free to enter into
any number of contracts cannot be the basis to enforce the
second agreement in respect of the same property after
enforcing the first agreement. The First Appellate Court even
after observing the conduct of the plaintiff in not approaching
the defendant with the balance consideration amount, on the
other hand, contending that the entire sale consideration
amount is paid, however admitting during cross examination
that the balance amount is still due to be paid, proceeded to
decree the suit which is nothing but perverse and illegal.
Similarly, the First Appellate Court even after dismissing the
application filed by the plaintiff seeking amendment of the
plaint with regard to his readiness and willingness to perform
the contract could not have decreed the suit for specific
performance of the contract.
42. The finding of the First Appellate Court regarding
the financial condition of the plaintiff to pay the balance
consideration amount is also erroneous as it has taken into
consideration the withdrawal of an amount of about
Rs.17,00,000/- on 30.04.2013 as per Ex.D6, ignoring the fact
that the date of agreement is 16.08.2004 and the period fixed
for payment of balance consideration was two months. The
financial condition of the plaintiff after about 13 years is of no
help to the plaintiff to decide his financial condition to perform
his part of the contract.
43. Thus, I am of the opinion that the suit of the
plaintiff for specific performance of the contract was liable to
be dismissed. The First Appellate Court committed an error in
decreeing the suit of the plaintiff. Therefore, the same are to
be set aside. In the result, the suit of the plaintiff for specific
performance of the contract is dismissed. Since the Trial
court was right in directing the defendant to refund the
amount of Rs.1,75,000/- which was admittedly paid by the
plaintiff under Ex.P1, the said judgment and decree is
required to be restored.
44. From the discussions held above, the substantial
questions of law Nos.1 and 3 are to be answered in favour of
the defendant - appellant and against the plaintiff -
respondent. Learned counsel for the appellant has not
addressed any argument about the substantial question of law
No.2, hence, the same is answered against the appellant.
45. Hence, I proceed to pass the following:
ORDER
(i) The appeal is allowed with cost, through out.
(ii) The judgment and decree dated 23.01.2017 passed
in RA No.579 of 2016 on the file of the learned II
Additional District Judge, Mysuru, is hereby set aside.
(iii) The judgment and decree dated 13.04.2016, passed
in O.S No.1024 of 2007 on the file of the learned I
Additional Senior Civil Judge and CJM, at Mysuru is
restored.
Registry is directed to send back the Trial Court records
along with copy of this judgment.
Sd/-
JUDGE
*bgn/-SKS
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!