Citation : 2023 Latest Caselaw 6003 Kant
Judgement Date : 29 August, 2023
1
R
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 29TH DAY OF AUGUST 2023
BEFORE
THE HON'BLE MR.JUSTICE S. SUNIL DUTT YADAV
WRIT PETITION No.33180 OF 2016 (LA-RES)
BETWEEN:
M/S. DECO EQUIPMENTS PVT. LTD.,
C-38, HEBBAL INDUSTRIAL AREA
METAGALLI,
MYSORE -16
REPRESENTED BY ITS
MANAGING DIRECTOR
DERIC FERNANDES.
... PETITIONER
(BY SRI D.L.N. RAO, SENIOR ADVOCATE FOR
SRI RAGHAVENDRA KATTIMANI, ADVOCATE)
AND:
1. THE STATE OF KARNATAKA
BY ITS SECRETARY
DEPARTMENT OF REVENUE
M.S. BUILDING
BANGALORE - 560 001.
2. THE DEPUTY COMMISSIONER
MYSORE DISTRICT
MYSORE - 570 001.
2
3. M/S. BHABHA ATOMIC RESEARCH CENTRE
RARE MATERIAL PROJECT
MINISTRY OF ATOMIC ENERGY
GOVERNMENT OF INDIA,
MYSORE - 570 001
REP. BY ITS MANAGING DIRECTOR.
4. THE LAND ACQUISITION OFFICER/
ASSISTANT COMMISSIONER
HUNSUR TALUK
MYSORE DISTRICT - 570 001.
5. THE UNION OF INDIA
MINISTRY OF ATOMIC ENERGY
GOVERNMENT OF INDIA
NEW DELHI - 01
REP. BY ITS SECRETARY.
... RESPONDENTS
(BY SRI R. SRINIVAS GOWDA, AGA FOR R1, R2 & R4;
SRI OMKARESHA, ADVOCATE FOR R3;
SRI H. SHANTHI BHUSHAN, DSGI FOR R5)
***
THIS WRIT PETITION IS FILED UNDER ARTICLES 226
AND 227 OF CONSTITUTION OF INDIA, PRAYING TO QUASH
THE IMPUGNED AWARD BEARING NO.LAQ/CR/01/2006-07
DATED 20-01-2016 AS PER ANNEXURE-X PASSED BY THE 4 TH
RESPONDENT I.E., THE LAND ACQUISITION OFFICER AND
ETC.
THIS WRIT PETITION HAVING BEEN HEARD AND
RESERVED ON 14.07.2023 AND COMING ON FOR
PRONOUNCEMENT OF ORDERS, THIS DAY, THE COURT MADE
THE FOLLOWING:
3
ORDER
The petitioner has filed the present petition seeking
quashing of the Award at Annexure-'X' dated 20.01.2016
passed by respondent No.4 - Land Acquisition Officer,
Mysore District. The petitioner has also sought for
issuance of a writ of mandamus to draw up an Award in
terms of Section 26 of 'The Right to Fair Compensation
and Transparency in Land Acquisition, Rehabilitation and
Resettlement Act, 2013' ('hereinafter referred to as
'2013 Act').
2. The Preliminary Notification under Section
4(1) of the Land Acquisition Act, 1894 (hereinafter
referred to as '1894 Act') was issued on 15.03.2008
notifying the land of the petitioner. The Final Notification
under Section 6 and 17(1) of 1894 Act came to be
passed on 05.06.2009. The validity of the notification
came to be challenged in W.P.No.405/2010, which was
disposed off remitting the matter for fresh disposal after
affording an opportunity of hearing under Section 5-A of
1894 Act.
3. After rejecting the objections, the Notification
was published under Section 6(1) of 1894 Act. The
petitioner challenged the validity of the Notification in
W.P.No.10322/2013 and during the pendency of the said
Writ Petition, 2013 Act came into force and the petition
was disposed off as follows:-
"6. ... However, if an award has not been passed as on date, it would be necessary for determination of compensation under 2013 Act as is made plain under Section 24(1) of the 2013 Act...."
4. The Special Land Acquisition Officer (SLAO)
has passed an Award, the copy of which is enclosed as
Annexure-'X' and the market value is fixed on the basis
of the sale consideration of Sale Deed dated 21.04.2007
for Rs.78,00,000/- and following the norms fixed in the
Gazette Notification dated 04.07.2013.
5. The said Award has been assailed by the
petitioner contending that the Guidelines mandated
under Section 26 of 2013 Act have not been followed,
that the reliance on the Notification dated 04.07.2013,
which was passed prior to commencement of 2013 Act is
bad in law, that the value as the base price for
calculation of compensation under Section 26 of 2013
Act would be the value as on 01.01.2014, that the Apex
Court in the case of Hori Lal v. State of Uttar Pradesh
and Others1 [Hori Lal] has taken the market value as
on 01.01.2014.
6. The respondents on the other hand have
contended that the value for the purpose of Section 26 of
2013 Act ought to be the value as on the date of the
2019 SCC OnLine SC 129
Section 4(1) notification under 1894 Act, that the Land
Acquisition Officer has rightly followed the Guideline
under the Gazette Notification dated 04.07.2013.
7. Heard both sides.
8. The points for consideration are as follows:-
(a) Where Notification under Section 4(1) and Section 6 of the Land Acquisition Act, 1894 is passed but Award is passed only after coming into force of 2013 Act, the market value of the land is to be determined as on the date of Section 4(1) Notification of 1894 Act or on 01.01.2014 when 2013 Act has come into force?
(b) Whether the Special Land Acquisition Officer could have relied on the Gazette Notification dated 04.07.2013 while fixing the market value?
9. At the outset, this Writ Petition is entertained
as the contention advanced is that the Land Acquisition
Officer has not adhered to the direction passed in
W.P.No.10322/2013, which mandates passing of Award
under 2013 Act. Even otherwise, there is no serious
opposition to the entertaining of the Writ Petition,
directly.
CONSIDERATION:-
(a) Where Notification under Section 4(1) and Section 6 of the Land Acquisition Act, 1894 is passed but Award is passed only after coming into force of 2013 Act, the market value of the land is to be determined as on the date of Section 4(1) Notification of 1894 Act or on 01.01.2014 when 2013 Act has come into force?
10. The Preliminary Notification under Section
4(1) of 1894 Act was passed on 15.03.2008, and the
Base Value adopted was the consideration recorded in a
Sale Deed of 21.04.2007.
11. It must be noted that in terms of Section 24
of 2013 Act, "(1) Notwithstanding anything contained in
this Act, in any case of land acquisition proceedings
initiated under the Land Acquisition Act, 1894 (1 of
1894) - (a) where no award under Section 11 of the said
Land Acquisition Act has been made, then, all provisions
of this Act relating to determination of compensation
shall apply." If that were to be so, the proceedings of
acquisition initiated under the 1894 Act are saved and
compensation is to be determined under the provisions
of the 2013 Act.
12. Section 26 of 2013 Act provides for
determination of the market value and proviso to the
aforesaid section is in the nature of an Explanation and
stipulates, "Provided that the date for determination of
market value shall be the date on which the notification
has been issued under Section 11."
13. The base point for calculation of compensation
is the date of Notification under Section 11 of 2013 Act,
while this would take care of the circumstance of
determination of market value as regards those matters
where notification is passed under Section 11 of 2013
Act, but the determination of market value as regards
Notification under Section 4 of 1894 Act and where
award is sought to be passed subsequently under 2013
Act is not dealt with specifically.
14. The only manner of addressing such a
circumstance would be on the basis of the following legal
propositions:
(i) As regards notification under Section 4(1) of
the 1894 Act and where Award is sought to be
made after 2013 Act has come into force 'all
provisions' of 2013 Act shall be applicable2.
(ii) In terms of the Proviso to Section 26 of 2013
Act, the relevant date would be the date of
Notification under Section 11 of 2013 Act.
Section 24(1)(A) of 2013 Act
(iii) The earliest of the dates as regards
Notification under Section 11 of 2013 Act would be
01.01.2014 when the 2013 Act has come into force.
(iv) Accordingly, the market value even as
regards circumstance of 4(1) Notification under
1894 Act and where Award is sought to be passed
after coming into force of the 2013 Act would be as
on 01.01.2014.
15. It must be noted that in circumstances, where
the delay in passing of the Award, if could be attributed
to the land owner leading to the non-passing of Award
under the provisions of the 1894 Act and Award is
passed under 2013 Act, the Apex Court in Faizabad-
Ayodhya Development Authority, Faizabad v.
Dr.Rajesh Kumar Pandey3 has held that such land
(2022) SCC OnLine 879.
owner is not entitled for having the Award passed under
the provisions of 2013 Act.
However, in the present case, though initially the
petitioner had challenged the validity of the proceedings
in W.P.No.10322/2013, during the course of the
proceedings, the petitioner had settled for the relief of
entitlement of compensation in terms of 2013 Act and
accordingly, the petition was disposed off as follows:-
"6. ...However, if an award has not been passed as on date, it would be necessary for determination of compensation under the 2013 Act as is made plain under Section 24(1) of the 2013 Act...."
This order having attained finality, the controversy
stands narrowed.
16. As regards the contention of the petitioner
that the Central Government is bound by the order of
26th October 2015 bearing D.O. Letter No.13013/01/
2014-LRD (pt), which stipulates taking of 01.01.2014 as
the relevant date, thereafter the Central Government has
clarified by its communication dated 26.09.2018 vide
letter No.13013/2017-LRD that the D.O. Letter No.
13013/01/2014-LRD (pt) dated 26.10.2015 is not an
order under Section 113 of 2013 Act, but is only a D.O.
letter.
17. No doubt, in Hori Lal (supra), the Apex
Court has taken the relevant date as 01.01.2014,
however, the State Government which was the acquiring
body itself had conceded for taking 01.01.2014 as the
relevant date. There was no adjudication on such issue
after contest.
18. Suffice it to say that there are conflicting
judgments of the High Courts without clarity.
Accordingly, adjudication is made herein without
reference to the order/D.O. letter.
(b) Whether the Special Land Acquisition Officer could have relied on the Gazette Notification dated 04.07.2013 while fixing the market value ?
19. Sri D.L.N. Rao, learned Senior Counsel
appearing on behalf of Sri Raghavendra Kattimani for the
petitioner has rightly contended that reliance on the
Gazette Notification dated 04.07.2013 may not be proper
as the same is prior to coming into force of 2013 Act and
the determination of market value under Section 26 of
2013 Act is to be made taking note of the guidelines
contained in Section 26 of 2013 Act. The said contention
is accepted.
20. Accordingly, the Award at Annexure-'X' dated
20.01.2016 is quashed. The Land Acquisition Officer is
directed to pass a fresh Award while re-working the
compensation in light of the discussion at Point-(a) supra
and is to strictly adhere to the Guidelines under Section
26 and other applicable Rules made under the 2013 Act.
Accordingly, the Writ Petition is disposed off.
Sd/-
JUDGE
NP/VGR
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!