Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Jayashree W/O Iranna Garagad vs Appasaheb S/O Nagangowda Biradar
2022 Latest Caselaw 12952 Kant

Citation : 2022 Latest Caselaw 12952 Kant
Judgement Date : 10 November, 2022

Karnataka High Court
Jayashree W/O Iranna Garagad vs Appasaheb S/O Nagangowda Biradar on 10 November, 2022
Bench: Suraj Govindaraj, G Basavaraja
                                                   -1-




                                                     RFA.CROB No. 100009 of 2017


                           IN THE HIGH COURT OF KARNATAKA, DHARWAD BENCH

                              DATED THIS THE 10TH DAY OF NOVEMBER, 2022

                                                PRESENT
                              THE HON'BLE MR JUSTICE SURAJ GOVINDARAJ
                                                  AND
                                THE HON'BLE MR JUSTICE G BASAVARAJA
                              RFA CROSS OBJ NO. 100009 OF 2017 (DEC/INJ-)
                      BETWEEN:

                      1.    SMT.JAYASHREE W/O IRANNA GARAGAD,
                            AGE : 47 YEARS, OCC: CIVIL ENGINEER,
                            R/O: HOUSE NO-9 SHIGGAON PARK
                            VIDYA NAGAR, HUBBALLI 580 026,
                            DIST. DHARWAD.]

                      2.    IRANNA S/O GANESH GARAGAD,
                            AGE ABOUT 46 YEARS, OCC: CIVIL ENGINEER,
                            R/O: H.NO.9, SHIGGAON PARK,
                            VIDYANAGAR, HUBBALLI-580026,
                            DIST. DHARWAD.
                                                            ...CROSS-OBJECTORS
                      (BY SRI. V M SHEELVANT AND SRI. M. L. VANTI, ADVOCATES)

                      AND:

VISHAL
                      1.     APPASAHEB S/O NAGANGOUDA BIRADAR,
NINGAPPA                     AGE ABOUT 70 YEARS, OCC: PENSIONER,
PATTIHAL
Digitally signed by
VISHAL NINGAPPA
                             R/O: SIDHARODAMATH NAGAR,
PATTIHAL
Date: 2022.11.10
16:48:28 +0530
                             OLD HUBBALLI, DIST. DHARWAD.

                      2.     THE COMMISSIONER
                             HUBBALLI DHARWAD MUNICIPAL CORPORATION
                             SIR SIDDAPPA KAMBLI MARG
                             HUBBALLI 580 024, DIST. DHARWAD.
                                      -2-




                                        RFA.CROB No. 100009 of 2017


3.   THE DEPUTY DIRECTOR OF TOWN PLANNING
     HUBBALLI-DHARWAD MUNICIPAL CORPORATION
     SIR SIDDAPPA KAMBLI MARG
     HUBBALLI 580 024, DIST. DHARWAD
                                                         ...RESPONDENTS

(BY SRI. S. S. PATIL, ADVOCATE FOR R1;
     SRI. G. I. GACHCHINAMATH, ADVOCATE FOR R2 & R3)


      THIS RFA CROSS-OBJECTION IS FILED ORDER 41
RULE 22 R/W. SECTION 151 OF CPC, AGAINST THE
JUDGMENT AND DECREE DATED 16.01.2017 PASSED IN
O.S.NO.129/2016 ON THE FILE OF THE III ADDITIONAL SENIOR
CIVIL JUDGE, HUBBALL, PARTLY DECREEING THE SUIT
FILED FOR DECLARATION, PERMANENT INJUNCTION AND
MANDATORY INJUNCTION. I


      THIS RFA CROSS-OBJECTION HAVING BEEN HEARD
AND RESERVED FOR JUDGMENT ON 03.11.2022, COMING ON
FOR PRONOUNCEMENT OF JUDGMENT THIS DAY, SURAJ
GOVINDARAJ J. PRONOUNCED THE FOLLOWING:

                               JUDGMENT

1. The above cross-appeal has been filed seeking for the

following reliefs:

a) That the appeal filed by the appellants/plaintiffs be allowed by setting aside the findings on issues No.2, 5 and 9 in judgment and decree passed in O.S.No.129/2016 dated 16.01.2017 on the file of III Additional Senior Civil Judge, Hubballi, holding that plaintiffs are entitled for declaration to the effect that they are entitled to four residential units in suit properties as mentioned in the joint

RFA.CROB No. 100009 of 2017

ownership building construction agreement dated 23.03.2015 after completion of construction work.

b) That the defendant/respondent herein be directed by means of mandatory injunction to clear the loan and to keep the suit properties free from the encumbrances to enable the plaintiffs/appellants herein to transfer / sell the same.

c) That the cost of the proceedings i.e., trial Court and this Hon'ble Court be ordered to be paid by defendants to plaintiff.

d) That any relief deemed fit circumstances of the case be ordered. .

2. O.S.No.129/2016 had been filed seeking for the following

reliefs:

a) It be declared that, the plaintiffs are entitled to share 4 residential units in the suit properties as mentioned in the "Joint Ownership Building Construction Agreement" dated 23.03.2015 after completion of construction;

b) The defendant, his servants and persons claiming through him be restrained by an order of permanent injunction not to obstruct the plaintiff to carry out and complete the construction as per the "Joint Ownership Building Construction Agreement" dated 23.03.2015;

c) The defendants be directed by means of mandatory injunction to clear the loan and to keep the suit properties free from the encumbrances to enable the plaintiffs to transfer/sell the same;

d) Costs of the suit; and

e) Such other relief as deemed fit be granted.

3. The III Addl. Senior Civil Judge, Hubballi, ('the trial Court',

for short) vide its judgment dated 16.01.2017 in

O.S.No.129/2016, had decreed the suit of the plaintiffs in

part. The defendant was restrained by way of permanent

prohibitory injunction from causing obstruction to the

completion of the construction by the plaintiffs as per the

RFA.CROB No. 100009 of 2017

Joint Ownership Building Construction Agreement dated

23.03.2015.

4. The cross-appellants are the plaintiffs before the trial Court.

The parties are referred to by their ranking before the trial

Court for easy reference.

5. In the suit it was claimed that:

5.1. The defendant is the owner of the house property with

ground floor comprised in CTS No.5048/2A2

measuring 277 sq. yards situate in Krishnapur

extension near Siddarudmath Nagar, Old Hubballi,

Hubballi.

5.2. It was contended that the plaintiff No.1 was a qualified

Civil Engineer and undertaking civil construction work

having expertise in 19 years. The plaintiffs and the

defendants had entered into a joint ownership building

construction agreement, which came to be registered

under document No.6441/14-15 on 23.03.2015.

5.3. That in terms of the agreement, the defendant

entrusted the construction of two floors over his

RFA.CROB No. 100009 of 2017

existing house property to the plaintiffs and on each

floor, the plaintiffs shall construct 4 residential units

measuring about 1859 square feet, apart from balcony

and staircase measuring 500 square feet, similar

construction to be made in the second floor, at the cost

of the plaintiffs. The obligation of providing all basic

amenities, obtaining building permission, completion

certificate etc., was that of the plaintiffs.

5.4. Both the parties have agreed to share equally the

newly constructed portion of the first floor and the

second floor. Even the share of the residential units

was agreed upon in the said agreement.

5.5. Apart there from, the defendant being the owner, who

had taken loan on the property, was required to

discharge the said loan to enable the plaintiffs to make

sale of the units falling to their share.

5.6. The construction was carried out within the time

period. There was no delay or lapses on the part of

RFA.CROB No. 100009 of 2017

the plaintiffs and the plaintiffs invested about 40-45

lakhs for construction.

5.7. When the construction was near completion, the

defendant was got issued a notice on 31.08.2015

calling upon the plaintiffs not to put up construction,

which was replied to.

5.8. The plaintiffs had issued a public notice cautioning

third parties from dealing with the property and

continued with the construction.

5.9. The defendant got issued a second notice on

06.02.2016 canceling the agreement which was also

replied to by the plaintiffs on 17.02.2016.

5.10. In the said notice, there are various allegations made

as regards the construction not being completed within

time and/or that the construction was not of standard

quality.

5.11. The same was replied by the plaintiffs contending that

the construction has been carried out without a break.

The plaintiffs have made all efforts to complete the

RFA.CROB No. 100009 of 2017

same and time was never the essence of the contract.

The quality of construction also being proper, the

defendant could not have any grievance as regards

the same.

5.12. It was further contended that the defendant had no

right to unilaterally terminate the contract. In the

meanwhile, it is alleged that in the quarrel which took

place with the defendant, the defendant along with his

son assaulted plaintiff No.1, for which she was treated

in the KIMS Hospital, Hubballi and it is in that

background that the plaintiffs sought for the aforesaid

relief of declaration that the plaintiffs are entitled to

share four residential units in the suit properties and

for injunction restraining the defendant from

completing the construction as per the Joint

Ownership Building Construction Agreement, as also

seeking fro the relief of clearance of the loan taken by

the defendant.

6. The defendant filed his written submission denying all the

allegations and contending that:

RFA.CROB No. 100009 of 2017

6.1. The plaintiffs had abandoned the construction work

and that the defendant was carrying out construction

at his own cost. The plaintiffs have violated the

agreement in as much as construction was not carried

out within the time frame and/or as per the standards

applicable. It was contended that, in terms of the

agreement dated 23.03.2015, the construction was to

be completed on or before 07.08.2015, time being the

essence of contract.

6.2. That the valuation the suit is not proper inasmuch as

valuation was made under Section 24(d) and 26(c) of

the Karnataka Court Fee and Suits Valuation Act,

Rs.1,000/- for the relief of declaration and Rs.1,000/-

for the relief of injunction. The suit had to be valued on

the agreement value which was registered for a sum of

Rs.39,92,000/-. The suit being essentially filed for

specific performance of the agreement, the valuation

was improper and that the Court could not have the

jurisdiction.

RFA.CROB No. 100009 of 2017

6.3. Apart from that, various allegations have been made

as regards the sub-standard, quality of the wood,

cement, bricks used in the construction, thickness of

the walls, load bearing capacity of the floor,

construction had gone bent requiring the defendant to

put four extra columns on southern side at his own

cost to prevent collapse of the building and it is in that

background that the agreement was cancelled.

6.4. The plaintiffs having abandoned the work, only 40% of

the construction was carried out and 60% remained to

be completed and in order to prevent any further loss

being caused to the defendant, the defendant did not

want the construction to go on.

6.5. The defendant has valued the construction work

carried out by the plaintiffs at Rs.22,00,000/-, which

the defendant is willing to make payment of. The

additional written statement also came to be filed by

the defendant contending that the declaratory relief as

sought for in the plaint cannot be granted in the

- 10 -

RFA.CROB No. 100009 of 2017

absence of the relief being sought for specific

performance.

6.6. It is again alleged that the violation made was

improper. The defendant contended that the

defendant had invested more than Rs.20,00,000/- for

continuance of construction from the stage where the

plaintiffs had abandoned the construction.

7. It is on the basis of the above pleadings, the trial Court

framed the following issues:

i. Whether the plaintiffs prove that they are the right to completion of the construction in the schedule properties as per the agreement dated 23.03.2015?

ii. Whether the plaintiffs prove that non co-operation by the defendant and the other reasons stated in para 7 of the plaint resulted in delaying the completion of the construction in the schedule property?

iii. Whether the defendant proves that non-completion of the construction within the time fixed in the agreement, resulted in termination of the agreement?

iv. Whether the plaintiffs prove that defendant is illegally causing obstruction to the ongoing construction in the schedule property?

v. Whether the plaintiffs prove that defendant is bound to clear the loan availed by creating charge on the schedule property?

vi. Whether this court no pecuniary jurisdiction to try the suit?

vii. Whether the court fee paid is insufficient?

viii. Whether the suit in the present form is not maintainable?

- 11 -

RFA.CROB No. 100009 of 2017

ix. Whether the plaintiffs are entitled for the reliefs claimed in the suit?

x. What order or decree?

8. The first plaintiff examined herself as PW1 and reiterated the

contentions taken up in the plaint. PW1 has admitted that:

8.1. The possession of the property was handed over on

08.08.2014.

8.2. She has admitted that the responsibilities of obtaining

permission, plan sanction etc., was that of the

plaintiffs. The plan for sanction was prepared by the

plaintiffs, which came to be approved by the Hubballi-

Dharwad Municipal Corporation.

8.3. There are various questions which have been posed

by the defendant as regards the cost of construction,

the manner of construction. It was denied that the

quality of construction was not proper. It was denied

that there is any delay in the construction being carried

out. It was denied that the construction was bent on

the southern side. She has stated that, since the

construction on the first floor was extended on the

- 12 -

RFA.CROB No. 100009 of 2017

southern side, there is requirement of putting up

pillars, which is the usual practice.

8.4. She has denied that the quality of construction

material, namely, sand, bricks and cement used is of

inferior quality.

8.5. She has denied that the bills which have been

produced for purchase of raw materials subsequent to

April, 2015 has been fabricated.

8.6. She has denied that the plaintiff did not have the funds

to put up construction. She has denied that she had

approached the defendant for funds.

8.7. She has denied that the external walls are not 9 inches

and reiterated that the external walls are of 9 inches.

8.8. She has denied that there is any conciliation talks

through the Annigeri Engineer.

8.9. The other suggestions put to her as regards delay in

construction has been denied.

- 13 -

RFA.CROB No. 100009 of 2017

9. The defendant examined himself as DW1 and reiterated the

grounds made in the written statement.

9.1. He alleged that the construction is not of proper

quality. There was delay in construction. The wall

width was lower than what was required. He had

spent a sum of Rs.15,00,000/- in putting up the

construction after the plaintiff had abandoned the

construction by availing loan.

9.2. He has further stated that he was willing to make

payment of a sum of Rs.22,00,000/- as full and final

settlement of the plaintiffs and in that background, he

has sought for the suit to be dismissed.

10. The defendant was cross-examined and during the course of

cross-examination questions were put to him as regards the

construction being within time, the quality being proper etc.,

which had been denied. The defendant also examined DW2

and DWs.2 to 4 to try and establish that the quality of

construction is not proper.

11. After considering the evidence on record, vide judgment

dated 16.01.2017, the III Addl. Senior Civil Judge, Hubballi

- 14 -

RFA.CROB No. 100009 of 2017

has partly decreed the suit and restrained the defendant from

interfering with the construction work to be carried out by the

plaintiffs. The plaintiffs having sought for a declaration that

the plaintiffs are entitled to the share of four residential

apartments and for a mandatory injunction directing the

defendant to clear the loan and get the suit properties free

from all encumbrances. Those reliefs have not been

granted. For non-grant of both the reliefs, the reason

attributed by the trial Court was that the construction was not

complete and until the construction is completed, there is no

manner of hand over of the possession of four units to the

plaintiffs and insofar as the loan is concerned, the trial Court

held that, until the construction is completed, no sale could

occur and as such, the appellant's claim for clearance of the

loan is premature without completion of construction.

12. The trial Court was of the opinion that there was no dispute

as regards the entitlement of four residential units as per the

joint agreement and therefore there is no question of giving

declaration on that aspect. The construction when

- 15 -

RFA.CROB No. 100009 of 2017

completed and the obligation under the joint memo being

discharged, the plaintiffs would be entitled for the same.

13. The cross-appellants are before this Court on the ground

that, the relief sought for ought to have been granted by the

trial Court, insofar as the declaration relating to the four units

and the clearance of the loan, that relief not having been

granted, this Court ought to grant such a relief. The

evidence as regards the joint agreement has been produced

above. There is no dispute as regards the execution of the

joint agreement.

14. The defendant had also filed an appeal in RFA

No.100039/2017 challenging the aforesaid order, which

came to be dismissed on 11.01.2019 on the submission

made by the counsel for the defendant that the appeal has

been rendered infructuous, since the construction has been

completed and the injunction which had been granted would

no longer apply. Though the plaintiff had objected to

dismissal of the appeal, this Court had held that the

contention raised by the plaintiff in the cross-objection would

be considered at the relevant time.

- 16 -

RFA.CROB No. 100009 of 2017

15. In view of the above, it is clear that the appeal filed by the

defendant has been dismissed and there is no challenge of

the defendant which is now pending. The appeal filed by the

plaintiffs is only restricted for the declaration as regards

entitlement of four units and for mandatory injunction for

clearance of the loan.

16. The trial court having rejected the contentions of the

defendant that there was any violation by the plaintiffs of the

agreement and having come to a positive conclusion that the

plaintiffs have right to continue with the construction, the

defendant not having a right to rescind the agreement, had

restrained itself from passing necessary orders as regards

the aforesaid reliefs, only on the ground that the construction

was not completed.

17. While the appeals were pending, construction has been

completed and the appeal filed by the defendant has been

withdrawn on the ground that it has been rendered

infructuous on account of the construction being completed.

- 17 -

RFA.CROB No. 100009 of 2017

18. In view of the above, the trial Court having restrained itself

only on account of the construction not being complete, now

that the construction is complete, we are of the considered

opinion that the plaintiffs are entitled for the reliefs which had

not been granted by the trial Court.

19. However, during the pendency of the above appeal, there

were certain other issues which have taken place as regards

the alleged violation of the plan sanctioned, as regards which

the Hubballi-Dharwad Municipal Corporation has initiated

proceedings under Section 321 of the Municipal Corporation

Act. When the same was brought to the notice of this court,

this court had called upon the parties to try and resolve the

issue and comply with the plan sanction so as to save the

building constructed. However, neither the appellant nor the

respondents were interested in resolving the matter.

20. The construction is now complete, there is no issue before

this Court as regards the nature of construction, quality of

construction or compliance of the plan sanctioned, more so,

when the appeal filed by the defendant has been dismissed.

The aspect of any violation of the plan sanctioned is one

- 18 -

RFA.CROB No. 100009 of 2017

which is required to be taken into consideration by the

HDMC which the HDMC has done by issuance of notice.

Those being separate independent proceedings are not

germane in the present appeal and would have to be

separately agitated in appropriate forum.

21. It is therefore made clear that the HDMC would be free to

continue with any proceedings initiated by it and take action,

if any, in accordance with law. However, in the event of the

HDMC coming to the conclusion that there is violation of the

plan sanctioned requiring any demolition of the construction

put up, we trust and believe that the HDMC would only

demolish the violation leaving the other construction

unaffected. In the event of there being no requirement of

demolition, then the constructed area would be divided

equally between the plaintiffs and the defendant.

22. Both parties contend that they have incurred expenses on

construction. Plaintiff contended that the plaintiff has put up

construction, defendant contended that the plaintiffs

abandoned construction forcing the defendant to take up

construction. Both the parties having constructed, it is not

- 19 -

RFA.CROB No. 100009 of 2017

clear if only one of them has violated the plan sanction, thus

It can safely be concluded that both have violated the plan

sanction on the basis of the admissions made by each of

them. That is not the matter for consideration before this

Court.

23. In the event of the HDMC coming to the conclusion that there

is no violation, then the constructed area on the first and

second floor would have to be equally divided between the

plaintiffs and defendants.

24. Hence we pass the following:

ORDER

i. The RFA Cross-objection is allowed.

ii. It is declared that the plaintiffs are entitled for four

residential units in the suit properties in terms of the

joint ownership building construction agreement dated

23.03.2015.

- 20 -

RFA.CROB No. 100009 of 2017

iii. The defendant is also directed to clear the loan, if not

already cleared and provide a no due certificate from

the bank to the plaintiffs.

iv. It is made clear that this Court has not expressed any

opinion as regards any violation of the plan and

HDMC is free to take such action as may be

necessary in this regard and if any of the parties are

aggrieved by the same, the parties are free to follow

their statutory remedies.

v. Upon completion certificate being issued by the

HDMC, the area as regards which the completion

certificate is issued, is directed to be shared between

the plaintiffs and the defendant in equal proportion

whether they make up four residential units or not.

Sd/-

JUDGE

Sd/-

JUDGE gab

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter