Citation : 2022 Latest Caselaw 11073 Kant
Judgement Date : 22 July, 2022
COMAP No.57/2021
1
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 22ND DAY OF JULY, 2022
PRESENT
THE HON'BLE MR. JUSTICE P.S. DINESH KUMAR
AND
THE HON'BLE MR. JUSTICE ANANT RAMANATH HEGDE
COMAP No.57 OF 2021
BETWEEN :
MSOURCE (INDIA) PRIVATE LIMITED
A PRIVATE LIMITED COMPANY
LIMITED BY SHARES INCORPORATED
UNDER THE COMPANIES ACT, 1956
HAVING ITS REGISTERED OFFICE AT
BAGMANE WORLD TECHNOLOGY CENTER
MARATHAHALLI OUTER RING ROAD
DODDENAKUNDI VILLAGE
MAHADEVAPURA, BANGALORE-560 048
REPRESENTED BY MR. SILVI JOSEPH ... APPELLANT
(BY SHRI. DHANANJAY JOSHI, SENIOR ADVOCATE FOR
SHRI. VACHAN AND VARSHA, ADVOCATES)
AND :
NAG INTERIORS PRIVATE LIMITED
A PRIVATE COMPANY LIMITED BY SHARES
INCORPORATED UNDER THE
COMPANIES ACT, 1956
HAVING ITS REGISTERED OFFICE AT
NO.83, NISA ENCLAVE, II FLOOR
MM ROAD, FRASER TOWN
BANGALORE-560 005
REPRESENTED BY ITS MANAGER. ... RESPONDENT
(BY SHRI. DHYAN CHINNAPPA, SENIOR ADVOCATE FOR
SHI. PRADEEP NAYAK, ADVOCATE FOR C/R)
COMAP No.57/2021
2
THIS COMMERCIAL APPEAL IS FILED UNDER SECTION
13(1A) OF THE COMMERCIAL COURTS ACT, 2015 R/W
SECTION 37(1)(C) OF THE ARBITRATION AND
CONCILIATION ACT, 1996 PRAYING
(A). SET ASIDE THE IMPUGNED JUDGMENT DATED
09.03.2021 IN COMM.A.S.NO.137/2015 PASSED BY THE
LXXXII ADDL. CITY CIVIL AND SESSIONS JUDGE (CCH-83),
BENGALURU (B). DIRECT THE RESPONDENT TO BEAR THE
ENTIRE COSTS OF THE ARBITRATION PROCEEDINGS AS
WELL AS OF THE PRESENT APPEAL; AND (C) ISSUE SUCH
FURTHER AND OTHER ORDERS AND / OR DIRECTIONS AS
THIS HON'BLE COURT MAY DEEM FIT AND PROPER IN THE
FACTS AND CIRCUMSTANCES OF THE CASE.
THIS COMMERCIAL APPEAL, HAVING BEEN HEARD
AND RESERVED FOR JUDGMENT ON 09.06.2022 COMING ON
FOR PRONOUNCEMENT OF JUDGMENT, THIS DAY,
P.S.DINESH KUMAR J, PRONOUNCED THE FOLLOWING:-
JUDGMENT
This appeal under Section 37(1)(c) of
Arbitration and Conciliation Act, 1996 is filed by the
respondent before the learned Arbitrator
challenging the order dated March 9, 2021 in Com.
A.S. No.137/2015 on the file of LXXXII Additional
City Civil and Sessions Judge, Bengaluru (CCH-83).
2. We have heard Shri. Dhananjay Joshi,
learned Senior Advocate for the appellant and COMAP No.57/2021
Shri. Dhyan Chinnappa, learned Senior Advocate for
caveator/respondent.
3. Brief facts of the case are, respondent
initiated arbitration proceedings against the
appellant contending inter alia that respondent had
carried out interior works in the Office of the
appellant and the appellant was due and liable to
pay a sum of `2,24,42,250/- with interest and a
sum of `3,08,538/- with interest.
4. Appellant resisted the claim contending
inter alia that there was delay of more than three
months in completion of the work by the
respondent; the PMC1 and the Architect had verified
the invoices and found several discrepancies in the
work done; appellant was not aware of the works
undertaken by the respondent beyond what was
specified in the Contract; notwithstanding the
Project Management Consultant COMAP No.57/2021
same, appellant had offered to pay `83,96,172/- in
full and final settlement of the claims; appellant
was not liable to pay the amounts, nor any
damages claimed by the respondent.
5. On consideration of material on record,
the learned Arbitrator has passed an Award
directing the appellant to pay `2,27,50,788/- with
interest at the rate of 18% p.a.
6. Appellant unsuccessfully challenged the
said Award in the Commercial Court. Hence, this
appeal.
7. Shri. Dhananjay Joshi, learned Senior
Advocate for the appellant mainly contended that:
• the Commercial Court has refused to interfere
with the Award with regard to exchange of
emails on the ground that the same was
neither raised nor argued by either party
before the learned Arbitrator;
COMAP No.57/2021
• without examining the grounds raised by the
appellant, the Commercial Court has held that
there is no illegality in the Award.
8. In addition to the above grounds,
assailing the order passed by the Commercial
Court, appellant has raised several grounds in the
Memorandum of Appeal assailing the Award passed
by the learned Arbitrator.
9. In substance, appellant's case is:
• respondent had undertaken work outside the
scope of tender and therefore, appellant was
not liable to make the payment with regard to
such works; and
• there was delay of three months in completion
of the work.
10. Shri. Dhyan Chinnappa, learned Senior
Advocate for the respondent submitted that the
payment in respect of the work/s, which was done COMAP No.57/2021
by the respondent was at the site belonging to the
appellant. The work was continuously monitored by
the PMC and the Architect, who were reporting to
the appellant. Appellant has got the measurement
of work done behind the back of respondent.
Appellant offered to make payment of `83.96 Lakhs
in respect of the work/s done by the respondent.
This itself proves that respondent has done the
work and what remained for consideration before
the learned Arbitrator was to consider the evidence
on record.
11. Shri. Praveen Solapur, R.W.1 has
admitted in his evidence that he was stationed at
the work site. He has further stated that PMC was
also at the site from the commencement of the
project till the end.
12. Learned Arbitrator has recorded findings
on the points for consideration and the same is COMAP No.57/2021
based on the evidence on record. Adverting to para
33 in Associate Builders Vs. Delhi Development
Authority2, Shri. Dhyan Chinnappa submitted that,
an Award based on little evidence or evidence which
does not measure up in quality to a trained legal
mind, would not be held to be invalid on that score.
With these submissions, he prayed for dismissal of
this appeal.
13. We have carefully considered rival
contentions and perused the records.
14. The sum and substance of respective
pleadings of the parties has been recorded by the
learned Arbitrator in the Award. As per the agreed
terms, the work assigned to the respondent was
required to be completed by April 15, 2011.
However, it was completed by May-June, 2011.
Respondent's case before the learned Arbitrator
(2015)3 SCC 49 COMAP No.57/2021
was, delay was not attributable to the respondent
because, firstly, additional works were entrusted;
secondly, there was delay in supply of materials;
and thirdly, the other vendors and Agencies like
electrical, air conditioning, fire, data cable etc.,
caused the delay. Appellant's case before the
Arbitrator was, the PMC and Architect had verified
the invoices and found several discrepancies.
Appellant was not liable to make the payment in
respect of work undertaken beyond what appellant
had prescribed. However, appellant considered
paying a sum of `83.96 Lakhs in respect of non-
tendered items of work to the extent the PMC and
the Architect had certified in full and final
settlement of respondent's claims.
15. Based on the pleadings, learned
Arbitrator has framed following points for
consideration:
COMAP No.57/2021
1. Whether claimant carried out non-tendered works at the instance of respondent and respondent's agents - PMC and the Architect?
2. Whether the said agents of respondent verified and certified some of the non- tendered items also?
3. Whether respondent is liable for payment towards non-tendered works only to the extent they are certified by PMC and Architect?
4. Whether respondent is still due, in all, to the claimant, respect of Purchase Order No.10404000855, Rs.2,24,42,250/-?
5. Whether, in respect of the said Purchase Order, Respondent is due in a sum of only Rs.83,96,172/-?
6. Whether claimant is entitled to interest at 18% p.a. on Rs.2,24,42,250/- from 23.1.2012 till date of payment?
7. Whether there is delay in claimant carrying out the work and therefore is liable for penalty?
8. Whether the delay was for the reasons stated in para-5 of the claim petition and COMAP No.57/2021
whether the said delay is justified and therefore, claimant is not liable for penalty?
9. Whether assigning of additional works / non-tender works implied that the original date of completion stood vacated by mutual consent, and that no fresh date of completion was specifically agreed to between the parties?
10.Whether claimant has suffered loss of profit and is entitled to Rs.60,00,000/- in that regard?
11.Whether respondent is due to the claimant, in respect of Purchase Order No.104040004223, a sum of Rs.3,08,538/-?
12.Is claimant entitled to interest thereon at 18% p.a. from 10.9.2012 till the date of payment?
13.To what reliefs are parties entitled?
16. On behalf of respondent, its Managing
Director, Shri. G.Suryanarayana was examined as
C.W.1 and Exs.P1 to P23 were marked. On behalf
of the appellant, one Praveen Solapur was COMAP No.57/2021
examined as R.W.1 and Exs.R1 to R16 were
marked.
17. Learned Arbitrator has recorded that
R.W.1 had sent an email dated August 1, 2011 to
go ahead with 'other works' and that the rates
would be finalized based on the rate analysis sheet
that would be submitted during the final bill.
18. It is further recorded that in reply to
notice dated February 5, 2013, appellant had stated
that a sum of Rs.34.82 Lakhs was set apart towards
non-tendered items, which were approved by the
Architect and the appellant. Learned Arbitrator has
further rightly recorded that appellant had
knowledge about the 'non-tendered' works.
19. Learned Arbitrator has further recorded
in para 6 of the Award that R.W.1 had admitted
that the work done by claimant as 'non-tendered'
work specified in page 360 of Ex.C6, was in addition COMAP No.57/2021
and not in lieu of 'quoted work' at Serial No.604.
Learned Arbitrator has further recorded that it was
admitted by R.W.1 that he was stationed at the
worksite on behalf of the claimant to monitor the
progress of the work and to manage various
vendors. The PMC used to be in the site from the
date of commencement of the project till the end.
20. Learned Arbitrator has recorded detailed
analysis of evidence and came to the conclusion
that all works were duly authorised and therefore,
claimant is liable to pay the same.
21. It is recorded by the Commercial Court
in the impugned order that the appellant has urged
following grounds in its appeal under Section 34 of
the Act:
COMAP No.57/2021
(i) The Arbitral Award is arbitrary, whimsical and wholly contrary to the facts and the evidence on record.
(ii) The learned Sole Arbitrator has not provided any reasons for his final decision in respect of each of the points that were to be determined in the proceedings.
(iii) The learned Arbitrator does not even make a reference to the terms of the Contract between the parties and has allowed the Claim of the Defendant by adopting a random sampling method of evidence, which is a process unknown to law.
(iv) The learned Arbitrator failed and neglected to take into consideration the only evidence of CW.1 and the same is not corroborated by any other evidence.
(v) The learned Arbitrator acted contrary to settled rules of evidence while observing that the Defendant is not liable to suffer any penalty on account of delayed completion of the project.
(vi) The learned Arbitrator passed the Award
without considering any of the
submissions of the Plaintiff and without there being any discussion thereof and without providing any reasons.
COMAP No.57/2021
(vii) The learned Arbitrator awarded the interest in breach of the mandate of Section 28(2) and (3) of the Arbitration and Conciliation Act, 1996.
(viii) The learned Arbitrator appears to be based on the principles stipulated in Section 70 of the Indian Contract Act, although there is no such pleadings and evidence to make out a Claim under the said provision.
22. The Commercial Court has recorded in
para 40 that it was argued on behalf of the
appellant that Commercial Court has to re-
appreciate the entire evidence. According to the
Commercial Court, the Award did not suffer from
any patent illegality nor was there any
contravention of any substantive law of India.
23. It was argued by Shri. Joshi that as held
by this Court in Union of India Vs. M/s. Warsaw
Engineers3, it is necessary for the Judicial Officer to
precisely record the submissions made by the
ComAp No.25/2021 decided on April 17, 2021 COMAP No.57/2021
learned Counsel for the appellant and the reply to
the specific grounds pleaded by the respondent. He
further contended that the Commercial Court has
not considered appellant's case in the light of
Warsaw Engineer's case.
24. Respondent's case before the Arbitrator
is that, appellant has got the work done but not
paid. It is held by the learned Arbitrator that R.W.1
had admitted that he was stationed in the work site
and PMC were also there right from the date of
commencement of the project. The consistent case
of the appellant is that it has offered to pay `83.96
Lakhs, as full and final settlement. In para (vii) of
the Memorandum of this appeal, appellant has
averred that it had offered to pay `81.09 Lakhs, in
full and final settlement. Thus, the appellant has
conceded to pay the said amount.
COMAP No.57/2021
25. We have carefully perused the Award
passed by the learned Arbitrator and the impugned
order. This appeal is filed under Section 37(1)(c) of
the Act, which provides for an appeal against an
order setting-aside or refusing to set-aside an
Arbitral Award under Section 34 of the Act.
26. In Associate Builders Vs. Delhi
Development Authority4, it is held as follows:
"33. It must clearly be understood that when a court is applying the "public policy"
test to an arbitration award, it does not act as a court of appeal and consequently errors of fact cannot be corrected. A possible view by the arbitrator on facts has necessarily to pass muster as the arbitrator is the ultimate master of the quantity and quality of evidence to be relied upon when he delivers his arbitral award. Thus an award based on little evidence or on evidence which does not measure up in quality to a trained legal mind would not be held to be invalid on this score Very often an arbitrator is a lay person not necessarily trained in law. Lord Mansfield, a famous
(2015)3 SCC 49 (Para 33) COMAP No.57/2021
English Judge, once advised a high military officer in Jamaica who needed to act as a Judge as follows:"General, you have a sound head, and a good heart; take courage and you will do very well, in your occupation, in a court of equity. My advice is, to make your decrees as your head and your heart dictate, to hear both sides patiently, to decide with firmness in the best manner you can; but be careful not to assign your reasons, since your determination may be substantially right, although your reasons may be very bad, or essentially wrong".It is very important to bear this in mind when awards of lay arbitrators are challenged.] . Once it is found that the arbitrators approach is not arbitrary or capricious, then he is the last word on facts. In P.R. Shah, Shares & Stock Brokers (P) Ltd. v. B.H.H. Securities (P) Ltd. [(2012) 1 SCC 594 : (2012) 1 SCC (Civ) 342] , this Court held: (SCC pp. 601-02, para 21) "21. A court does not sit in appeal over the award of an Arbitral Tribunal by reassessing or reappreciating the evidence. An award can be challenged only under the grounds mentioned in Section 34(2) of the Act. The Arbitral Tribunal has examined the facts and held that both the second respondent and the appellant are liable. The case as put forward by the first COMAP No.57/2021
respondent has been accepted. Even the minority view was that the second respondent was liable as claimed by the first respondent, but the appellant was not liable only on the ground that the arbitrators appointed by the Stock Exchange under Bye-law 248, in a claim against a non-member, had no jurisdiction to decide a claim against another member. The finding of the majority is that the appellant did the transaction in the name of the second respondent and is therefore, liable along with the second respondent. Therefore, in the absence of any ground under Section 34(2) of the Act, it is not possible to re-examine the facts to find out whether a different decision can be arrived at."
27. Having perused the Award passed by the
Arbitral Tribunal, we are of the considered view that
the same is based on detailed analysis of the
evidence on record. Therefore, no exception can be
taken to the order of the Commercial Court
dismissing the petition under Section 34 of the Act.
COMAP No.57/2021
Hence, no interference is called for in this appeal
and it is accordingly dismissed.
No costs.
Sd/-
JUDGE
Sd/-
JUDGE
SPS
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!