Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Arohi Elevators Pvt. Ltd vs The Steel Authority Of India Ltd
2026 Latest Caselaw 2728 Jhar

Citation : 2026 Latest Caselaw 2728 Jhar
Judgement Date : 7 April, 2026

[Cites 2, Cited by 0]

Jharkhand High Court

M/S. Arohi Elevators Pvt. Ltd vs The Steel Authority Of India Ltd on 7 April, 2026

Author: Rajesh Shankar
Bench: Rajesh Shankar
                                                        ( 2026:JHHC:9725-DB )

IN THE HIGH COURT OF JHARKHAND AT RANCHI
                     W.P. (C) No. 2253 of 2026
M/s. Arohi Elevators Pvt. Ltd., Ashok Kunj, Ashok Nagar, No. 3, P.O. & P.S.
Argora, District - Ranchi through its Director Bajrang Bahadur Singh, aged
about 60 years, son of Late Surya Bhan Singh, resident of C-1670, Okhala
Industrial Area Phase-I, P.O. & P.S. Okhala Industrial Estate, District - South
Delhi.
                                                   .... .... Petitioner
                                   Versus
1. The Steel Authority of India Ltd., a Company registered under Companies
      Act, 1956 through its Chairman- cum-Managing Director, having its office
      Ispat Bhawan, Lodhi Road, P.O. & P.S. Delhi Lodhi Road, New Delhi.
2. Bokaro Steel Plant through its Managing Director, having its office at
      Bokaro Steel City, P.O. & P.S. Bokaro Steel City, District Bokaro,
      Jharkhand.
3. The Chief General Manager (Mechanical Maintenance), Bokaro Steel
      Plant, having its office at Bokaro Steel City, P.O. & P.S. Bokaro Steel City,
      District Bokaro, Jharkhand.
4. The General Manager (Contract Cell), SAIL, Bokaro Steel Plant, having
      its office at Bokaro Steel City, P.O. & P.S. Bokaro Steel City, District
      Bokaro, Jharkhand.
5. The Assistant Manager (L&A), Bokaro Steel Plant, having its office at
      Bokaro Steel City, P.O. & P.S. Bokaro Steel City, District Bokaro,
      Jharkhand
                                                       .... ....       Respondents
                            ------

CORAM : HON'BLE THE CHIEF JUSTICE HON'BLE MR. JUSTICE RAJESH SHANKAR

------

For the Petitioner          :      Mr Rahul Kumar, Advocate
For the Respondents         :      Mr Indrajit Sinha, Advocate
                                   Mr Ankit Vishal, Advocate
                            -----
02 /Dated: 07.04.2026

1.    Heard the learned counsel for the parties.

2. The petitioner challenges the order dated 24.02.2026, by which the Steel

Authority of India Limited (SAIL) has banned future business dealings with the

petitioner for a period of two years, starting from 03.10.2025 and ending on

02.10.2027.

3. Mr Rahul Kumar, learned counsel for the petitioner, submits that the

impugned order is non-speaking and demonstrates a complete lack of

consideration. He contends that even the petitioner's response to the show cause

( 2026:JHHC:9725-DB )

notice has not been properly considered. He argues that issuing non-speaking

orders or those which fail to consider the cause shown by the petitioner violates

the principles of natural justice and fair play and, therefore, must be regarded as

void. On these grounds, Mr Rahul Kumar submits that the impugned order dated

24.02.2026 should be quashed.

4. Mr Indrajit Sinha, learned counsel for SAIL, submits that the charge

against the petitioner was non-compliance with the provisions of the Payment of

Wages Act and denial of execution of any further work orders. He pointed out

that no less than two show-cause notices were issued to the petitioner, and after

due consideration of the petitioner's response, the impugned order was made. Mr

Sinha submitted that the petitioner's response did not deny the allegations; on

the contrary, the petitioner expressed an inability to comply with the provisions

of the Payment of Wages Act. He made particular reference to the petitioner's e-

mail dated 16th August 2025, in which the petitioner requested the foreclosure

of the contract and even offered to continue services until SAIL made alternate

arrangements to terminate the contract.

5. Accordingly, Mr Sinha submitted that there was no failure of natural

justice and the impugned order was entirely consistent with the contractual terms

and the petitioner's request.

6. The rival contentions now fall for our determination.

7. The record shows that the petitioner was engaged by SAIL under a

comprehensive maintenance contract for three Goods-cum-passengers' lifts

outside the Bokaro Steel Plant on a STE basis.

8. Upon realising that the petitioner was not complying with the provisions

of the Payment of Wages Act, even though the work orders had clearly stipulated

such compliance, a notice was issued to the petitioner, proposing the banning of

( 2026:JHHC:9725-DB )

future business dealings. The petitioner, by communication dated 16th August

2025, wrote to SAIL that their wage payment system is in sync with the labour

laws and the company's policy. The CLC's BSL requirement may not align with

the petitioner's established norms. Therefore, the petitioner expressed an

inability to modify the whole wage payment system for a single contract. By this

communication, the petitioner also requested foreclosure of the contract but

agreed to continue with their services until SAIL makes alternative arrangements

or terminates the contract.

9. The contents of the e-mail dated 16th August 2025 addressed by the

petitioner to the SAIL are transcribed below for the convenience of reference: -

"Arohi Elevators [email protected] Sat, Aug 16, 2025 at 11:24. To: MTB Eqpt Inspn [email protected] Cc: MAHESHKUMAR LAL <[email protected]>, KRISHNA [email protected], manoranjan [email protected] Dear Sir, Our wage payment system is in sync with labour laws and company's policy. The CLC requirement of BSL may not be in line with our established norms. We express our inability to modify the whole wage payment system for a single contract.

Hence we would request you to foreclose the contract. We agree to continue our services till you make alternate arrangements or terminate the contract. [Quoted text hidden) Regards"

10. Despite the above response, in which the petitioner requested foreclosure

of the contract after expressing inability to modify its wage payment system, no

less than two show-cause notices were issued to the petitioner regarding the ban

on future business dealings.

11. In the response furnished to the show cause notices, the petitioner

nowhere denied non-compliance or non-adherence but sought to raise the issue

of delayed payments by SAIL and other such issues. However, what is important

is the fact that there was no denial about the non-adherence to the requirements

of the Payment of Wages Act and disinclination to comply with such statutory

( 2026:JHHC:9725-DB )

provisions on the ground that the petitioner was unwilling "to modify the whole

wage payment system for a single contract".

12. Therefore, considering the materials on record, including the response to

flatly comply with even the statutory provisions, we do not think that there was

any failure of natural justice, non-application of mind or even unfairness on the

part of SAIL, issuing the impugned order, banning the petitioner from future

business dealings for a period of two years.

13. The claim that the impugned order is non-speaking is quite misconceived.

The reason for the ban is clearly outlined in the impugned order, supported by

the email and response to the show cause notices sent by the petitioner. The

impugned order was made after giving the petitioner due opportunity for

rectification and after careful consideration of their response.

14. Accordingly, we are satisfied that there is no illegality, procedural

impropriety, or unfairness involved in the decision-making process leading to

the issuance of the impugned order. This petition is, accordingly, meritless and

dismissed without any order for costs.

15. Let a copy of this order be sent to the Payment of Wages Authority at

Bokaro / Dhanbad, so that the Authority can inquire into the payment structure

being offered by the petitioner to its workmen.

16. The Registry to do the needful.

(M.S. Sonak, C.J.)

(Rajesh Shankar, J.) April 07, 2026 Ranjeet / R.Kr.

NAFR Uploaded on 09.04.2026

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter